Seascape at Rashid Yachts & Marina Construction Updates
The Register Record of Four Buildings Rising Beside the Rashid Yachts & Marina Canal Pool
Seascape reached 79.13% in the DLD register on 06 May 2026, leaving envelope, MEP and finishes to close across four Mina Rashid buildings before November 2026 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Seascape at Rashid Yachts & Marina at a Glance
Seascape is Emaar's group of four residential buildings holding approximately 391 homes at Rashid Yachts & Marina, registered with the Dubai Land Department as project 2513 on 05 December 2022. Construction started on 13 April 2023, the register read 79.13% at the 06 May 2026 inspection, the latest in the supplied record, and handover is scheduled for November 2026. What makes this record unusual is the spread of heights it averages: Building 1 rises to G+18 while Buildings 2 to 4 stop between G+6 and G+8, all over one shared two-level basement, so a single register figure stands for very different amounts of work in each building.
2513
Active
13 April 2023
Approx. 391 units
46,460.50 sq m
30 November 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Seascape at Rashid Yachts & Marina Construction Update Timeline
Three dated register readings make up the Seascape record so far: 8.96% on 01 May 2024, with piling almost finished below ground; 49.78% on 30 June 2025, with substructure and superstructure recorded complete; and 79.13% on 06 May 2026, with finishes moving through all four buildings. The 70.17 points between the first and the latest reading were added in just over two years, across gaps of 425 and 310 days, and each table row opens the full monthly update for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 79.13% | 06 May 2026 | View the May 2026 update |
| June 2025 | 49.78% | 30 June 2025 | View the June 2025 update |
| May 2024 | 8.96% | 01 May 2024 | View the May 2024 update |
Pace Analysis
How Fast Seascape at Rashid Yachts & Marina Has Been Built
Two dated pairs sit inside the Seascape record. Dividing the points gained by the days between readings, on a 30-day month, gives this arithmetic, which describes the record and is not a forecast:
- May 2024 to Jun 2025: piling and foundations to completed frames, 8.96% to 49.78% over 425 daysAbout 2.88 points per month
- Jun 2025 to May 2026: envelope, MEP and internal finishes, 49.78% to 79.13% over 310 daysAbout 2.84 points per month
What stands out is how flat this curve is. Seascape added 40.82 points while its four frames went up and 29.35 points while envelope, MEP and finishes moved through them, yet the monthly rate barely shifted, from about 2.88 to about 2.84. Measured from the 13 April 2023 start, the whole build averages about 2.12 points a month over the 1,119 days to the 06 May 2026 reading, pulled down by the 384 days of basement and piling work that came before the first dated reading of 8.96%. At the latest reading the record shows 20.87 points remaining and 208 days to the 30 November 2026 registered completion date; those two facts sit side by side here, and no forecast is drawn from them. For an end user, the next dated register reading is the one that will show whether finishing slows as November 2026 approaches; for an investor, the near-identical pace of two very different phases is the clearest signal this record has given so far.
Get the Next Inspection Figure First
Tell me you are tracking Seascape at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Seascape at Rashid Yachts & Marina at Mina Rashid
A register percentage means more once you know what it is measuring. The project guide sets out what the Seascape record on this page is building toward:

Seascape at Rashid Yachts & Marina: Four Buildings by the Park
Seascape at Rashid Yachts & Marina is an Emaar complex of four buildings with about 391 apartments and two-level townhouses.
View the Seascape at Rashid Yachts & Marina Project GuideConsidering a Near-Handover Entry?
With handover scheduled for November 2026, the choice of remaining Seascape homes keeps narrowing as the finishing stage runs on. If this record is what brought you here, ask me what is available today before the options shrink further.
Ask About Remaining Availability on WhatsAppStage Record
Seascape at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it actually occupied between the 13 April 2023 start and the 79.13% reading of 06 May 2026, using what the RERA progress report for each date described across Building 1 at G+18 and the three lower buildings.
Enabling Works, Piling and Basement
From the 13 April 2023 start, work below ground ran until the 01 May 2024 inspection found piling nearly finished and foundation works still under way, at 8.96%.
Substructure and Four Concrete Frames
By 30 June 2025 the report listed substructure and superstructure completed for all four buildings, from G+6 to G+18, with the register at 49.78%.
Envelope, MEP and Internal Works
With internal works already very advanced in June 2025, envelope, MEP and finishes carried the register another 29.35 points to 79.13% on 06 May 2026.
External Works and Apartment Finishing
The 06 May 2026 report added external works to the active list, while envelope, MEP and internal finishes were still under way in parallel across the buildings.
Completion and Handover
The 20.87 points left at the last reading stand between the record and handover in November 2026; the register lists 30 November 2026 as the registered completion date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Seascape at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Seascape at Rashid Yachts & Marina
This page is one of four project resources that together cover a Seascape at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Seascape at Rashid Yachts & Marina Construction Updates
This page: the DLD register record for Seascape, three dated readings from 8.96% to 79.13%.

Seascape at Rashid Yachts & Marina Golden Visa: Four Residential Buildings
Seascape at Rashid Yachts & Marina, approximately 391 Emaar units, qualifies at 2 and 3 bedroom apartments and the townhouse.
Read the Seascape at Rashid Yachts & Marina Golden Visa Guide
Seascape at Rashid Yachts & Marina Escrow: Dubai Islamic Bank on Record
Seascape at Rashid Yachts & Marina, DLD project 2513, escrows 395 units at Dubai Islamic Bank, 79.13% certified May 2026.
Verify the Seascape at Rashid Yachts & Marina Escrow Account
Seascape at Rashid Yachts & Marina Snagging for Apartments and Two-Level Townhouses
Seascape at Rashid Yachts & Marina is Emaar Properties' four-building address beside the community park and canal pool, approximately 391 residences.
Book Seascape at Rashid Yachts & Marina SnaggingApproaching Handover
Between 79.13% and Handover: What Seascape at Rashid Yachts & Marina Buyers Should Do Now
By the 06 May 2026 reading the Seascape frames were long finished, and what separates 79.13% from handover is envelope, MEP, external works and finishes across four buildings of very different heights. A handover notice tends to leave only a short window to book the appointment, so the three steps below belong in the months before November 2026, not in the week a notice arrives.
First, arrange an independent defect inspection so problems in your apartment or two-level townhouse are recorded before you accept it; the Seascape snagging inspection page explains timing and what is checked.
Second, compare your remaining instalments with the recorded milestones on the Seascape escrow account page: the 2022 launch schedule dates its 80% construction row March 2026, the register read 79.13% on 06 May 2026, and your SPA sets the terms that actually apply to you.
Third, if residency matters to you, settle whether your price tier qualifies through the Seascape Golden Visa page before handover, since title deed timing shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A build record is only half the picture; the other half is what surrounds it. These three pages put the Seascape record in its marina, community and developer context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Seascape at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Seascape, DLD project 2513, is an active project whose latest dated register reading in the supplied record is 79.13%, for the inspection of 06 May 2026. The RERA progress report for that date lists enabling, foundation and structure as completed, with external envelope, external works, MEP and internal finishes progressing, and handover is scheduled for November 2026. The full record is in the Seascape inspection timeline above.
Seascape's three dated readings in the Dubai Land Department project register are 8.96% on 01 May 2024, 49.78% on 30 June 2025 and 79.13% on 06 May 2026. The latest reading is 29.35 points above the June 2025 figure, which was itself 40.82 points above May 2024; the detail behind the latest reading is in the Seascape May 2026 construction update.
Seascape averaged about 2.88 points a month between 01 May 2024 and 30 June 2025 (40.82 points over 425 days) and about 2.84 points a month between 30 June 2025 and 06 May 2026 (29.35 points over 310 days), both on a 30-day month. Measured from the 13 April 2023 start, the whole-build average to the 06 May 2026 reading is about 2.12 points a month over 1,119 days. These figures are arithmetic on dated readings, not a forecast; the breakdown is in the Seascape pace analysis above.
Yes. The register lists 30 November 2026 as the registered completion date for project 2513 (read September 2026), which falls in the scheduled November 2026 handover month. At the 06 May 2026 reading of 79.13%, the record stood 20.87 points and 208 days short of that date; the two facts are stated side by side without a forecast, and this page's record is updated when the next register reading appears.
The Seascape record covers approximately 391 residences, one, two and three bedroom apartments plus two-level 3 bedroom townhouses, in four buildings: Building 1 at G+18, Building 2 at G+7, Building 3 at G+8 and Building 4 at G+6, all over a two-level basement. Each register reading on this page, including the 79.13% of 06 May 2026, is one figure for that whole complex.
The RERA progress reports for the Seascape inspections of 01 May 2024, 30 June 2025 and 06 May 2026 each give a progress status of Main Contract - Progressing and describe the works on site, but print no percentage. The figures on this page, 8.96%, 49.78% and 79.13%, come from the Dubai Land Department project register for those same inspection dates, as shown in the Dubai REST app.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Seascape at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.