Outdoor lifestyle plaza and modern residences at Seascape Rashid Yachts and Marina by Emaar in Dubai Construction Update May 2026 Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina · Construction Update

Seascape Construction Update - May 2026

May 2026 Inspection: DLD Register Places Seascape at 79.13% Construction Progress at Rashid Yachts & Marina

Glazing on Building 1, open MEP ceilings in corridors and apartment finishing marked the 06 May 2026 inspection, when the DLD register recorded Seascape at 79.13 percent.

Direct advisor access. Every message answered personally, never by a call center.

79.13%DLD Register Reading
06 May 2026Inspection Date
November 2026Scheduled Handover
2513DLD Project Number

DLD Register Record, May 2026

Seascape Construction Snapshot: May 2026

A 29.35 point rise since the 49.78% reading of 30 June 2025 took Seascape to 79.13% on 06 May 2026, well into the finishing band, where the open questions move from the buildings themselves to when the last packages close out. This is the latest reading in the supplied record; re-verify DLD project 2513 on Dubai REST before relying on it.

Project Name

Seascape at Rashid Yachts & Marina

Project Number

2513

Project Status

Active

Construction Progress

79.13%

Inspection Date

06 May 2026

Construction Start

13 April 2023

Total Units

Approx. 391 units

Total Built Area

46,460.50 sq m

Expected Completion

November 2026

Data source: the Dubai Land Department project register (Dubai REST) reading for the RERA inspection of 06 May 2026, the latest reading in the supplied record; the Independent Progress Monitoring Report for that date records the status as Main Contract - Progressing and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is project imagery, not a photograph from this inspection. Last updated: May 2026 (latest reading in the record, compiled September 2026).

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

The 06 May 2026 Inspection

Seascape Construction Progress Summary

Between the 30 June 2025 and 06 May 2026 inspections, Seascape moved from 49.78% to 79.13%, a 29.35 point gain over 310 days, or about 2.84 points a month on a 30-day month (arithmetic on the two dated readings, not a forecast). Over that span the inspection notes moved on from a finished superstructure with services and envelope under way to a completed structure, with external works now added to the packages in progress.

Completed
  • Enabling works and foundations
  • Structure of all four buildings, from G+6 to G+18, over the two-level basement
In Progress at 79.13%
  • Internal work, recorded at an advanced stage
  • External envelope of the four buildings
  • External works, listed for the first time in this series
  • MEP services and internal finishes, at different stages
Ahead of Handover
  • Close-out of the envelope, external works, MEP and finishes packages
  • Register readings rising from 79.13% to 100%
  • Pre handover inspection, then handover scheduled for November 2026
Next readingNone in the supplied record after 06 May 2026; any later inspection appears first in the DLD project register on Dubai REST.
Registered completion30 November 2026 per the register (read September 2026), 208 days after this inspection; the scheduled handover is November 2026.
Remaining distance20.87 percentage points separated the 06 May 2026 reading from 100%.

Payment Linked Progress

What 79.13% Progress Means for Seascape Buyers

Near the end of a construction linked plan, the weight of payment shifts to completion: in the Seascape launch plan of record, the largest single instalment, 20%, is labelled upon 100% construction completion and dated November 2026, against an estimated date. With the register at 79.13% and the structure complete, four actions matter most.

Before Any Remaining Transfer

Verify the escrow account

Anything still due before handover should go only to the DLD regulated escrow account registered for project 2513, held with Dubai Islamic Bank (PJSC) according to the register. Seascape escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Reread your SPA completion clauses

Check how your sale and purchase agreement defines construction completion, the handover notice period and the final payment, and set those clauses against the November 2026 scheduled handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Window Open Now

Book the snagging inspection

At 79.13%, with 208 days between the reading and the registered completion date, Seascape sits inside the usual booking window for a pre handover inspection. Apartments call for glazing, balcony and tile checks; the two-level townhouses add internal stairs, balustrades and wet areas on both floors. The Seascape snagging inspection guide sets out both checklists.

Every Cycle

Re-verify the latest reading

The 06 May 2026 figure of 79.13% is the latest reading in the supplied record, and the register may already carry a later one. Seascape construction updates sets each dated reading side by side.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 79.13%?

A finishing-band entry gives up most of the payment runway in exchange for a structure the inspection report already lists as completed: what remains at Seascape is envelope, external works, services and finishes, with handover scheduled for November 2026. Every payment goes to the DLD-registered escrow account for project 2513, released against construction progress recorded at RERA inspections.

Entering at 79.13% (May 2026)
  • Structure recorded as completed at the 06 May 2026 inspection
  • About seven months from that reading to the November 2026 scheduled handover
  • 80/20 launch plan, the final 20% due on construction completion
Typical Launch Entry
  • Piling, frame and envelope all still ahead at reservation
  • A multi-year wait between booking and the keys
  • Every row of the instalment schedule still to be paid
AED 1.65M ≈ USD 449KCurrent Starting Price
80/20 Plan20% Due on Completion
November 2026Scheduled Handover
Ask What Is Available at Seascape

The inspection record says nothing about which units remain; availability shifts between cycles and is confirmed at the moment you ask.

About the Development

Seascape Project Details

Seascape at Rashid Yachts & Marina by Emaar aerial view of residential buildings marina yachts and waterfront pools in Dubai, Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar Properties

At the 06 May 2026 inspection, Seascape's four buildings had their structure completed and were in the finishing stage, with approximately 391 homes across 1, 2 and 3 bedroom apartments and two-level 3 bedroom townhouses. Current starting price: AED 1.65M ≈ USD 449K.

For a buyer entering in the finishing band, the building itself is no longer the open question; the quality of the finish is, and it is checked at handover, scheduled for November 2026.

Seascape at Rashid Yachts & Marina Project Guide

Site Context in May 2026

Explore Seascape Location on Dubai Map

Seascape's four buildings stand on plot 441 in Madinat Dubai Almelaheyah, next to the community park and the canal pool at Rashid Yachts & Marina. The May 2026 report is the first in this series to list external works among the packages in progress, work that on this footprint covers the ground around four buildings of very different heights, from Building 1 at G+18 to Building 4 at G+6, and their edges toward the park and the pool.

The wider district centres on a marina of 430 wet berths taking yachts up to 100 metres long, with the Promenade's restaurants and shops and the canal pool close by and Seagate next to Seascape on the masterplan; Emaar's fact sheet puts Sheikh Zayed Road about 10 minutes and Downtown Dubai about 20 minutes from the site. For a buyer planning to move in or rent out soon after the November 2026 handover, how ready those facilities are is worth checking alongside the building's own 79.13%. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Seascape on Dubai Map

Buyer Resources for This Project

Investing in Seascape During Final Construction Progress

In the finishing band, the last escrow transfers, residency eligibility and the pre handover inspection all arrive within months of each other. Each resource below is matched to where Seascape stood at the 06 May 2026 reading.

Seascape at Rashid Yachts and Marina construction updates featuring resort style pools, landscaped courtyards, and contemporary waterfront residences. Presented by Tohid Fetrat
You Are Here

Seascape Construction Updates

This page: Seascape's 06 May 2026 inspection record, structure completed and finishes progressing at 79.13%.

Luxury waterfront view at Seascape Rashid Yachts and Marina by Emaar with UAE Golden Visa card in Dubai Presented by Tohid Fetrat

Seascape at Rashid Yachts & Marina Golden Visa: Four Residential Buildings

Seascape at Rashid Yachts & Marina, approximately 391 Emaar units, qualifies at 2 and 3 bedroom apartments and the townhouse.

Read Seascape Golden Visa Guide
Luxury waterfront residences at Seascape Rashid Yachts and Marina with escrow account security icons in Dubai Presented by Tohid Fetrat

Seascape at Rashid Yachts & Marina Escrow: Dubai Islamic Bank on Record

Seascape at Rashid Yachts & Marina, DLD project 2513, escrows 395 units at Dubai Islamic Bank, 79.13% certified May 2026.

Verify Seascape Escrow Account
Why Snagging Matters at This Stage of Seascape at Rashid Yachts and Marina featuring contemporary waterfront residences surrounded by landscaped gardens. Presented by Tohid Fetrat

Seascape at Rashid Yachts & Marina Snagging for Apartments and Two-Level Townhouses

Seascape at Rashid Yachts & Marina is Emaar Properties' four-building address beside the community park and canal pool, approximately 391 residences.

Book Seascape Snagging

Update Timeline

Other Seascape Construction Updates

Trace how Seascape reached the finishing stage through the earlier readings, starting with the June 2025 inspection that came before this one.

All Seascape Construction Updates

FAQs

Seascape Construction Progress in May 2026: Frequently Asked Questions

Seascape, DLD project 2513, stood at 79.13% in the Dubai Land Department project register for the inspection of 06 May 2026, the latest reading in the record behind this page. That is 29.35 points above the 49.78% of 30 June 2025, a span of 310 days, or about 2.84 points a month on a 30-day month (arithmetic, not a forecast). The register app also shows 69.45% as the previous inspection figure, undated, 9.68 points below the current reading. A later reading may already be on Dubai REST, and each dated reading is listed on the Seascape construction updates page.

At the 06 May 2026 reading, 20.87 percentage points and 208 days separated Seascape from 100% and from the 30 November 2026 registered completion date, as the register listed it when this page was compiled in September 2026. The scheduled handover is November 2026. Registered dates can be revised between inspection cycles, and the two figures are stated side by side as recorded facts, not as a forecast of either delay or early delivery.

The Independent Progress Monitoring Report for 06 May 2026 records enabling, foundation and structure as completed and internal work at an advanced stage, with the external envelope, external works, MEP and internal finishes progressing at different stages. Its photographs, which belong to the RERA record and are not published here, show the tallest building with its balconies and glazing in place, a corridor with the ceiling grid still open over exposed services, a closed-in corridor with floor protection, and an apartment with glazed doors fitted and a worker on a mobile scaffold. The register app lists 10 inspection photos for that date.

The June 2025 report listed substructure and superstructure as completed and internal works at a very advanced stage; the May 2026 report records the structure as completed, describes internal work as at an advanced stage, and adds external works to the packages progressing alongside the envelope, MEP and internal finishes. The reports give no reason for the change of wording, so it is best read as the inspector's description on each date rather than as a measure; the percentage comes from the register, not from these notes.

The supplied record does not show the 80% mark being reached. The 2022 launch schedule of record dated the 7th instalment of 10% March 2026 and marked it upon 80% construction completion, against an estimated construction completion date, while the register reading on 06 May 2026, after that date, was 79.13%. How a particular SPA ties an instalment to recorded progress, and whether the date or the milestone governs, is set by that SPA, and nothing here indicates what any buyer has paid.

On the 06 May 2026 record, the remaining work sits in the packages still listed as progressing: the external envelope, external works around the buildings, MEP services and internal finishes, plus the internal work described as advanced. After those, the register reading has to reach 100%, the developer issues the handover notice under the terms of each SPA, and buyers typically hold a pre handover inspection before accepting their unit. The inspection report gives no date for any of these steps.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Seascape at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts