Selvara by Emaar in Grand Polo Club & Resort construction updates cover image featuring a project rendering of a modern villa with landscaped frontage, palm trees, and private car porch in Dubai - Presented by Tohid Fetrat

Emaar · Grand Polo Club & Resort

Selvara at Grand Polo Construction Updates

The Dated Build Record for 237 Villas in Dubai Investment Park Second

Selvara at Grand Polo recorded 2.81% construction at its 14 May 2026 RERA inspection, the second reading on a register that opens with enabling works and piling.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

2.81%Construction Progress
14 May 2026Latest RERA Inspection
237 villasTotal Units
Project 3822DLD Registration

Construction Snapshot

Selvara at Grand Polo at a Glance

Selvara is Emaar's 237-villa phase on plot 3939 in Dubai Investment Park Second, entered on the Dubai Land Department register as project 3822 on 13 June 2025 and under construction since 02 November 2025. Because the register describes it as 237 villas in a G+2 form, averaging 3,802 sq ft each, a single percentage on this page stands for 237 separate building footprints rather than for one rising structure, which is worth holding in mind when reading the 2.81% recorded on 14 May 2026. The registered anchors behind that figure are below.

DLD Project Number

3822

Project Status

Active

Construction Start

02 November 2025

Total Units

237 villas

Total Built-Up Area

79,477.06 sq m

Registered Completion Date

30 April 2029

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Selvara at Grand Polo Construction Update Timeline

This record is deliberately short: Selvara carries one dated RERA reading, 2.81% on 14 May 2026, sitting above an earlier 0.65% figure that the register holds without an inspection date. The movement between the two is 2.16 points, but there is no interval to divide it by, so the track below marks only the dated reading and the table links the full report behind it. Every later inspection joins this table as it is recorded.

Inspection MonthConstruction ProgressInspection DateFull Update
May 20262.81%14 May 2026View the May 2026 update

Pace Analysis

How Fast Selvara at Grand Polo Has Been Built

With one dated reading on the register, pace at Selvara is read three ways: what the site has averaged since groundbreaking, what moved between the two recorded figures, and what the registered completion date now demands.

  • 02 Nov 2025 to 14 May 2026: enabling and foundations, 2.81 points over 193 daysAbout 0.44 points per month
  • Undated previous reading to 14 May 2026: 0.65% to 2.81% on the registerPlus 2.16 points between readings
  • 14 May 2026 to 30 Apr 2029: 97.19 points still to record over 1,082 daysAbout 2.73 points per month required

There is no curve here yet, and saying so is more useful than drawing one. The honest shape of this record is a single dated point at 2.81% and a long straight line to 100%. The average since groundbreaking, about 0.44 points per month, is the arithmetic of enabling work: mobilization, piling and deep infrastructure services consume months of programme and register very little percentage, which is what the first winter of a 237-villa phase looks like rather than evidence of drift. The figure that deserves attention is the third one. Holding 30 April 2029 means averaging about 2.73 points per month from here, roughly six times the rate the register has recorded so far, and a villa phase absorbs that only once substructures are out of the ground and shells rise across the plot in parallel rather than one at a time. For an investor, that makes the next two readings the ones worth waiting for, because they are where the rate either steps up or does not. For a buyer already committed, it turns the 2029 date into something to verify against each new inspection rather than assume. One caveat on all of it: the 14 May 2026 reading was 126 days old when this page was written, so every figure above describes the last confirmed position for Selvara, not today's site.

Get the Next Inspection Figure First

Tell me you are tracking Selvara at Grand Polo and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Selvara at Grand Polo at Grand Polo Dubai

A percentage only means something next to what it is building. The full project guide covers what the 2.81% on this page is working toward:

Selvara at Grand Polo Club and Resort by Emaar, a modern luxury villa exterior with private car porch and landscaped frontage in Dubai. Presented by Tohid Fetrat.

Selvara at Grand Polo: Single-Typology Villas Near the Green Core

Selvara at Grand Polo is Emaar's release of 237 four bedroom villas in a single typology, close to the Green Core.

View the Selvara at Grand Polo Project Guide

Considering an Early-Stage Entry?

Four of the nine launch instalment dates had already passed before the 14 May 2026 inspection, so entering now means joining a schedule partly behind it rather than starting at the booking step. Availability at Selvara shifts between inspection cycles; ask me what is left before the next reading publishes.

Ask About Remaining Availability on WhatsApp

Stage Record

Selvara at Grand Polo Build Stages, Mapped to the Inspections

Each stage below is tied to the window it actually occupies in Selvara's own record, so the two stages already on the register read as history and the three ahead of them read as the distance still to be recorded.

13 Jun 2025 to 02 Nov 2025

Registration and Main Contract

Project 3822 was entered on the DLD register on 13 June 2025 against plot 3939; the construction start recorded for Selvara is 02 November 2025, 142 days later.

Current PhaseNov 2025 onward, 2.81% at the latest reading

Mobilization, Enabling Works and Piling

At 2.81% on 14 May 2026 the work was still at and below ground level: enabling works and piling under way on plot 3939, with deep infrastructure services running alongside them.

Ahead: the first points after 2.81%

Villa Substructure and Superstructure

The registered G+2 form across 237 villas is the phase that converts programme into percentage; none of it had reached the register by the 14 May 2026 reading.

Ahead: toward the 50% and 70% marks

Facades, Roofing and Internal Fit-Out

The launch schedule ties instalments to 50% and 70% construction completion, both of which sit inside this phase and a long way beyond the 2.81% on record.

Ahead: toward 30 Apr 2029

Landscaping, Commissioning and Handover

The remaining 97.19 points from the 14 May 2026 reading close in this window, against a registered completion date of 30 April 2029 and a 90% instalment marker before it.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Selvara at Grand Polo's own record.

Buyer Position

Tracking Your Position at Selvara at Grand Polo

This page is one of four project resources that together cover a Selvara at Grand Polo purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Selvara by Emaar in Grand Polo Club & Resort construction updates cover image featuring a project rendering of a modern villa with landscaped frontage, palm trees, and private car porch in Dubai - Presented by Tohid Fetrat
You Are Here

Selvara at Grand Polo Construction Updates

This page: every dated RERA reading for Selvara, from the 2.81% May 2026 inspection onward.

Selvara by Emaar in Grand Polo Club & Resort Golden Visa eligibility concept with a Golden Visa card above modern villa exteriors and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Selvara at Grand Polo Golden Visa, Roughly Three Times Over

Selvara at Grand Polo, Emaar's 237-villa release in Dubai Investment Park Second, offers only the 4 bedroom villa, and it qualifies.

Read the Selvara at Grand Polo Golden Visa Guide
Selvara by Emaar in Grand Polo Club & Resort escrow account protection concept with shield and padlock icons above an outdoor swimming pool and landscaped clubhouse setting in Dubai - Presented by Tohid Fetrat

Selvara at Grand Polo Escrow, the First Selvara Release on Record

Selvara at Grand Polo, DLD project 3822, holds 237 units with National Bank of Ras Al Khaimah, 2.81% certified May 2026.

Verify the Selvara at Grand Polo Escrow Account

Approaching Handover

Between 2.81% and Handover: What Selvara at Grand Polo Buyers Should Do Now

At this end of the record there is very little building to inspect and a great deal of paperwork that decides how the next three years go. The distance from 2.81% to the registered completion date is 97.19 points, and the launch schedule keeps moving on calendar dates while the percentage barely moves, so the three checks below belong in the gap between readings rather than after the next one.

First, confirm where each instalment actually lands before you release it; the Selvara at Grand Polo escrow account page names the bank holding the project 3822 account and sets out how drawdowns are released against recorded progress.

Second, settle residency planning early rather than late: at AED 6.20M the ticket clears the property threshold years before the villa exists, and the Selvara at Grand Polo Golden Visa guide separates what can be filed during construction from what waits for the title deed.

Third, read the record itself rather than the marketing around it. The Selvara May 2026 construction update is the only dated cycle published for Selvara so far, and the next inspection figure is the only thing that will change the numbers on this page.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Grand Polo Dubai Structure

A build record is only half the picture; the other half is what is going up around it. These three pages put Selvara's 2.81% in its masterplan, community, and developer context:

Grand Polo Villas and Townhouses for Sale luxury villa with private pool and outdoor lounge at Grand Polo Club and Resort Dubai Presented by Tohid Fetrat

Grand Polo Dubai Properties for Sale

Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.

See Grand Polo Dubai Properties for Sale
Grand Polo Club and Resort by Emaar clubhouse overlooking the polo fields with palm lined landscape in Dubai Presented by Tohid Fetrat

Grand Polo Dubai Community Overview

Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.

Explore the Grand Polo Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Selvara at Grand Polo Construction Updates Frequently Asked Questions

The figures come from independent progress monitoring commissioned for RERA, not from Emaar's own reporting. The report covering Selvara is filed against DLD project number 3822 and developer number 1211, and the one dated 14 May 2026 is the source of the 2.81% shown throughout this page.

This page is rewritten each time a new inspection is recorded against project 3822, not on a fixed calendar. Selvara has one dated reading so far, 14 May 2026, so there is no established interval yet for this project; the Selvara at Grand Polo May 2026 construction update holds the detail behind it.

Alongside the percentage, the 14 May 2026 report for Selvara records the project number 3822, plot 3939 in Dubai Investment Park Second, the developer name and number, the trust account bank, a project description of 237 villas in a G+2 form, a progress status, and a short note on the activity seen on site that day.

It records which contractual phase the project sits in rather than how much is built. At the 14 May 2026 inspection Selvara carried the status Main Contract, Progressing, meaning the main construction contract was live and running while the recorded figure stood at 2.81%.

The register holds an earlier Selvara reading of 0.65% with no inspection date attached to it, so only the 14 May 2026 reading can be placed on a timeline. Construction started on 02 November 2025, which is why the record is this short: the project is 193 days old at its first dated inspection.

This hub holds the full history for Selvara: every dated reading, the pace arithmetic between them, and the stage record. Each monthly page covers one inspection cycle in detail, and so far that is the Selvara at Grand Polo May 2026 inspection page alone. Older monthly pages stay published rather than being overwritten, so the 2.81% reading remains readable in its original context after later figures land.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Selvara at Grand Polo construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.