Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands project rendering used for the May 2026 construction update showing planned contemporary villas along a landscaped residential street in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Islands · Construction Update

Seychelles at DAMAC Islands Construction Update - May 2026

Seychelles 1 Read 2.49% at the 1 May 2026 DLD Inspection as Enabling Works Progressed

RERA's 1 May 2026 Seychelles 1 inspection found mobilisation ongoing, enabling works progressing at an advanced stage, and infrastructure works moving ahead with deep service excavation.

Direct advisor access. Every message answered personally, never by a call center.

2.49%Seychelles 1 DLD Reading
1 May 2026Seychelles 1 Inspection
Q2 2029Expected Handover
3698Seychelles 1 DLD Project

Recorded DLD Inspection Data

Seychelles at DAMAC Islands Construction Snapshot

2.05 points higher than at the 4 November 2025 inspection, Seychelles 1 (DLD project 3698) read 2.49% on 1 May 2026. A figure this low marks ground preparation rather than building, so for a buyer the paperwork around each instalment, from escrow to Oqood to the SPA dates, carried more weight than the gauge itself. The DLD registers the Seychelles cluster in two phases; the record shown here is Seychelles 1, and Seychelles 2, registered separately with its own DLD record, is not covered by this reading.

Project Name

Damac Islands - Seychelles 1

Project Number

3698 (Seychelles 1)

Project Status

Active (Seychelles 1); IPMR: Enabling Works - Progressing

Construction Progress

2.49% (Seychelles 1)

Inspection Date

1 May 2026 (Seychelles 1)

Construction Start

1 October 2025 (Seychelles 1)

Total Units

678 across the Seychelles cluster

Total Built Area

35,067.46 sq m (Seychelles 1 DLD register)

Expected Completion

Q2 2029

Data source: the DLD project register entry Damac Islands - Seychelles 1 (project 3698, status Active, registered 5 May 2025, construction started 1 October 2025, registered completion date 30 June 2029) and the RERA Independent Progress Monitoring Report for the Seychelles 1 inspection of 1 May 2026, whose Progress Status reads Enabling Works - Progressing. The report states no percentage of its own, so 2.49% and the 0.44% logged on 4 November 2025 are Seychelles 1 readings taken from the DLD register. The page stands as the record of that 1 May 2026 Seychelles 1 inspection and describes the site as it stood on that day; a newer DLD inspection may have been published since. The image at the top is a DAMAC rendering of planned villas, not a view of the works. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: May 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Seychelles at DAMAC Islands Construction Progress Summary

From 0.44% on 4 November 2025 to 2.49% on 1 May 2026, Seychelles 1 added 2.05 points across 178 days, and the RERA report filed for the May visit set its Progress Status at Enabling Works - Progressing. That report describes Seychelles 1 as 204 G+2 and G+1 townhouses and villas, to be built in concrete with block walls and finished inside and out; each ledger line below draws only on that report and the Seychelles 1 register entry.

Completed
  • DLD registration of Seychelles 1 on 5 May 2025
  • Seychelles 1 construction start recorded on 1 October 2025, 149 days after registration
  • Seychelles 1 trust account listed with Emirates NBD
  • First Seychelles 1 reading on record: 0.44% on 4 November 2025
In Progress at 2.49% (Seychelles 1)
  • Mobilisation, ongoing when Seychelles 1 was inspected on 1 May 2026
  • Enabling works, progressing at an advanced stage at that visit
  • Infrastructure works, progressing with deep service excavation
Ahead of Handover
  • The concrete structure and blockwork of the 204 Seychelles 1 homes the report describes
  • Internal and external finishes across the G+2 and G+1 house types
  • Further RERA readings for Seychelles 1, and the Seychelles 2 record once supplied
  • Seychelles 1 registered completion date 30 June 2029; expected handover Q2 2029
Next inspectionThe register publishes no date for the next visit. Each new Seychelles 1 reading is posted on Dubai REST after RERA inspects the site, and a reading newer than the 1 May 2026 Seychelles 1 figure may be listed there by now.
Completion targetThe DLD record for Seychelles 1 lists a registered completion date of 30 June 2029, in line with the expected Q2 2029 handover; each phase's contractual completion date is the one in its SPA.
Remaining distance97.51 percentage points lay between the 1 May 2026 Seychelles 1 reading and 100%. Arithmetic, not a forecast: measured between the two register readings, Seychelles 1 gained about 0.35 points per 30-day month (2.05 points in 178 days), and its whole-build average from the registered start comes to about the same 0.35 (2.49 points in 212 days); reaching 100% by the registered completion date would take Seychelles 1 about 2.53 points per 30-day month over the 1,156 days that followed the reading. The registered date is the developer's filing for Seychelles 1, not a promise, and nothing here predicts the handover.

Time-Linked Instalments

What 2.49% Progress at Seychelles 1 Means for Seychelles Buyers

Under DAMAC's DAMAC Islands payment plan, instalments fall due by months from sale rather than at construction milestones, so the 2.49% Seychelles 1 reading neither brought a payment forward nor held one back; it recorded how far the ground works had come while the schedule kept running. For Seychelles buyers at this enabling stage, four checks carry the most weight.

Before Any Instalment

Verify the escrow account

Every Seychelles phase is a separate DLD project with an escrow account of its own. Seychelles 1 (Damac Islands - Seychelles 1, project 3698) lists Emirates NBD as its trust account bank; a Seychelles 2 buyer should read the account details off their own SPA or Oqood, then confirm them on Dubai REST, instead of paying into the Seychelles 1 account. Seychelles at DAMAC Islands escrow account verification sets out each step, and the lookup takes about two minutes against the official DLD project record.

Before the Next Due Date

Reread your SPA instalment schedule

DAMAC's DAMAC Islands payment plan (launch sheet, November 2024) asks for 20% plus the 4% DLD registration fee on booking, 55% in 39 instalments after booking and 25% on completion. Set each instalment date in your SPA, and the way it defines completion, beside the Q2 2029 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood records an off-plan purchase with the DLD until a title deed can follow at completion. Make sure the entry shows your Seychelles phase, home and price exactly as your SPA does; the 4% DLD registration fee, settled at booking, goes to the DLD and never into the escrow account.

Every Cycle

Follow each new reading

Seychelles 1 has two readings on record so far, 4 November 2025 and 1 May 2026, roughly six months apart, and another may have been posted since. Seychelles at DAMAC Islands construction timeline collects each reading as it is supplied and will carry the Seychelles 2 record once it arrives.

General framework, not legal advice: instalment dates, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly. This is the plan DAMAC issued at the DAMAC Islands launch in November 2024; confirm the current schedule for your Seychelles phase with DAMAC and in the SPA.

Buying at Seychelles 1's 2.49% Stage?

Coming in at the enabling stage trades a thin inspection record for time: instalments are spread over the build years and the price is set long before the keys. Every instalment goes to the DLD-registered escrow account of your phase (project 3698 for Seychelles 1), released against construction progress.

Entering at Seychelles 1's 2.49% Reading
  • A 2.05 point Seychelles 1 gain between two dated register readings
  • Cluster handover expected in Q2 2029
  • Launch-sheet plan: 55% across 39 instalments, 25% at completion
Typical Near-Handover Entry
  • Most construction risk resolved before signing
  • Keys months away instead of years
  • A larger share of the price due close to handover
AED 2.25M ≈ USD 613KStarting Price
75/25 Plan25% Due on Completion
Q2 2029Expected Handover
Ask What Is Available at Seychelles at DAMAC Islands

Limited units available when this page was prepared; no unit count is published, and availability shifts between cycles.

About the Development

Seychelles at DAMAC Islands Project Details

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands project rendering of a modern two-storey villa with large glass windows, palm trees and landscaped gardens in Dubai - Presented by Tohid Fetrat
DAMAC Islands · DAMAC Properties

Seychelles at DAMAC Islands groups 678 townhouses and villas in one cluster registered with the DLD in two phases, and when Seychelles 1 was inspected in May 2026 its works were at the enabling stage. Entry is a 2,208 sq ft four-bedroom townhouse listed from AED 2.25M ≈ USD 613K.

A five-bedroom townhouse of 3,178 sq ft is listed from AED 3.10M ≈ USD 844K, and six-bedroom villas of 4,440 sq ft are listed from AED 6.50M ≈ USD 1.77M. Each listed price clears the AED 2M ≈ USD 545K Golden Visa line, though what counts is the buyer's own title deed or Oqood value. Buying now means the longest runway to the Q2 2029 handover; the picture shown is a DAMAC rendering.

Seychelles at DAMAC Islands Project Guide

Site Context This Cycle

Explore Seychelles at DAMAC Islands Location on Dubai Map

DAMAC's launch material marks Seychelles on its DAMAC Islands community map without drawing the cluster's phases, and the inspection on this page covers Seychelles 1 alone. In a low-rise phase of G+2 and G+1 houses, roads and buried services generally have to reach every plot before homes can rise, and the 1 May 2026 report for Seychelles 1 reflects that order: its infrastructure entry was deep service excavation, and none of its notes concerned the homes.

DAMAC places the masterplan in Dubailand and quotes community drive times of about 20 minutes to the Expo 2020 Venue and 30 minutes to Burj Al Arab, figures for DAMAC Islands as a whole rather than timed from a Seychelles plot. Its central hub fountain, aqua park and jungle river are presented as planned amenities of the masterplan, so a buyer weighing occupancy or letting from the Q2 2029 handover is judging the district by its plan rather than by finished streets. See where the cluster sits on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Seychelles at DAMAC Islands on Dubai Map

Buyer Resources for This Project

Investing in Seychelles at DAMAC Islands During the Enabling Stage

At the enabling stage the checks that protect a buyer are documentary rather than on site: the escrow account, the Oqood entry and residency eligibility. Each resource below is matched to the position recorded for Seychelles 1 in May 2026.

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands construction updates cover image featuring a project rendering of a modern villa with tall windows, balconies and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Seychelles at DAMAC Islands Construction Updates

This page: Seychelles 1 on 1 May 2026, 2.49% with enabling works and deep service excavation.

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands Golden Visa concept graphic showing a gold visa card over a rendered modern villa and swimming pool in Dubai - Presented by Tohid Fetrat

Seychelles Golden Visa: Three Home Types and an Off-Plan Application

Seychelles at DAMAC Islands, by DAMAC Properties, lists townhouses and villas that each clear the AED 2M Golden Visa threshold alone.

Read the Seychelles at DAMAC Islands Golden Visa Guide
Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands escrow concept graphic showing a shield and padlock beside a rendered modern villa with a driveway in Dubai - Presented by Tohid Fetrat

Seychelles 1 Escrow: Pay the Account Your SPA Names

Seychelles 1, DLD project 3698 on plot 14061, holds payments for 204 units in Emirates NBD escrow, apart from Seychelles 2.

Verify the Seychelles at DAMAC Islands Escrow Account

Update Timeline

Other Seychelles at DAMAC Islands Construction Updates

This is the first monthly page for Seychelles, so there is no earlier month to open; the hub keeps every Seychelles 1 reading in sequence and gains new months as they are supplied.

All Seychelles at DAMAC Islands Construction Updates

FAQs

Seychelles at DAMAC Islands Construction Progress in May 2026: Frequently Asked Questions

At the inspection dated 1 May 2026, the DLD register showed Seychelles 1 (project 3698), one of the cluster's two registered phases, at 2.49%, a rise of 2.05 points on the 0.44% recorded for Seychelles 1 on 4 November 2025. The RERA monitoring report for that Seychelles 1 visit classed the stage as Enabling Works - Progressing and printed no percentage of its own, so both figures are Seychelles 1 register readings. Seychelles 2 is registered separately with its own DLD record, and this reading does not describe it.

It can. The 30 June 2029 entry in the Seychelles 1 DLD record is the date the developer filed for that phase, and a filing of this kind can be revised between inspections. At the 1 May 2026 Seychelles 1 reading it matched the cluster's expected Q2 2029 handover; the date that binds an individual buyer is the completion date written into their own SPA, and any revision to the Seychelles 1 filing would show in a subsequent monthly update.

RERA's Independent Progress Monitoring Report on Seychelles 1, dated 1 May 2026, listed three activities: mobilisation, which was ongoing; enabling works, which were progressing at an advanced stage; and infrastructure works, which were progressing with deep service excavation. In the same report Seychelles 1 is described as 204 G+2 and G+1 townhouses and villas, meaning homes of ground plus two upper floors and of ground plus one, to be built with a concrete structure and blockwork and finished inside and out.

No. The phrase in the 1 May 2026 RERA report refers to the Seychelles 1 enabling works only: the preparatory package of site set-up, ground preparation and access that generally comes before any homes are built. The phase as a whole read 2.49% in the Seychelles 1 register entry that day, with a Progress Status of Enabling Works - Progressing, and the report's notes for Seychelles 1 mentioned no work on the homes themselves.

Service excavation is the digging of trenches for the buried networks a residential cluster runs on, such as drainage, water, power and telecoms, and it generally comes ahead of roads, landscaping and the homes. Its mention in the 1 May 2026 report for Seychelles 1 shows that the phase's infrastructure works had reached the below-ground utilities by that date, which is consistent with a Seychelles 1 reading of 2.49%: services in the ground first, houses afterwards.

Seychelles 1 moved from 0.44% on 4 November 2025 to 2.49% on 1 May 2026, a gain of 2.05 points in 178 days, which works out at about 0.35 points per 30-day month. That rate is arithmetic between the two Seychelles 1 register readings, not a forecast: both readings fall within the enabling stage, which says little about how quickly the homes themselves will go up. The Seychelles at DAMAC Islands construction updates hub keeps every Seychelles 1 reading in one timeline.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Seychelles at DAMAC Islands correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts