Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands construction updates cover image featuring a project rendering of a modern villa with tall windows, balconies and landscaped frontage in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Islands

Seychelles at DAMAC Islands Construction Updates

Townhouses and Villas Tracked Phase by Phase, Starting With Seychelles 1

Seychelles 1 recorded 2.49% on the DLD register at its 1 May 2026 inspection, enabling-works progress that opens the townhouse-and-villa cluster's record toward a Q2 2029 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

2.49%Construction Progress
1 May 2026Latest RERA Inspection
678 homes across the Seychelles clusterTotal Units
Project 3698DLD Registration

Construction Snapshot

Seychelles at DAMAC Islands at a Glance

Seychelles at DAMAC Islands brings 678 DAMAC Properties homes, 4 and 5 bedroom townhouses alongside 6 bedroom villas, into one cluster of the DAMAC Islands masterplan in Dubailand, with handover expected in Q2 2029. The DLD registers the Seychelles cluster in two phases; the record shown here is Seychelles 1 (project 3698), which entered the register on 5 May 2025 and recorded its construction start 149 days later, on 1 October 2025. Seychelles 2 is registered separately with its own DLD record; it is not covered by this reading, and its record joins this page once it is supplied. The most recent Seychelles 1 figure on hand comes from 1 May 2026 and had aged 187 days by the time this page was drafted, so a later Seychelles 1 inspection may well have been filed since. The mix of formats shows up inside the first phase as well: the RERA report lists the 204 Seychelles 1 homes as G+2 and G+1 townhouses and villas, so a single Seychelles 1 percentage covers houses of two different heights.

DLD Project Number

3698

Project Status

Active; IPMR: Enabling Works - Progressing

Construction Start

1 October 2025

Total Units

678 homes across the Seychelles cluster

Total Built-Up Area

35,067.46 sq m (Seychelles 1 DLD register)

Registered Completion Date

30 June 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Seychelles at DAMAC Islands Construction Update Timeline

So far the record holds two dated Seychelles 1 register readings under DLD project 3698, 0.44% on 4 November 2025 and 2.49% on 1 May 2026, separated by 178 days and 2.05 points. Ahead of both stand the Seychelles 1 registration of 5 May 2025 and its recorded construction start of 1 October 2025. The DLD record for Seychelles 1 lists a registered completion date of 30 June 2029, in line with the expected Q2 2029 handover; each phase's contractual completion date is the one in its SPA. On the track the lime dot marks 2.49% for Seychelles 1 in May 2026, and the green dot almost touching it is the November 2025 Seychelles 1 figure, left unlabelled so the two do not overprint. Only the May row of the table links a monthly update, because no monthly page was published for November 2025.

Inspection MonthConstruction ProgressInspection DateFull Update
May 20262.49%1 May 2026View the May 2026 update

Pace Analysis

How Fast Seychelles at DAMAC Islands Has Been Built

Because both Seychelles 1 readings carry dates, one pace can be measured directly; the other two lines below are arithmetic, not a forecast, and all three use 30-day months:

  • 4 Nov 2025 to 1 May 2026: Seychelles 1 enabling works, 0.44% to 2.49% over 178 days, measured between the two register readings, not a forecastAbout 0.35 points per month
  • 1 Oct 2025 to 1 May 2026: Seychelles 1 mean rate from its recorded start, 2.49 points over 212 days, arithmetic, not a forecastAbout 0.35 points per month
  • 1 May 2026 to 30 Jun 2029: rate the Seychelles 1 registered completion date would require, 97.51 points over 1,156 days, arithmetic, not a forecastAbout 2.53 points per month

The first two lines agree, and the agreement is the main finding: across the whole span from its 1 October 2025 start, and again across the 178 days between its two readings, Seychelles 1 added points at one even rate. That evenness says more about the kind of work on file than about how quickly homes go up. At the Seychelles 1 inspection of 1 May 2026, RERA noted mobilisation still ongoing, enabling works progressing at an advanced stage and infrastructure works taken down to deep service excavation, below-ground work that generally moves a phase percentage very little. The third line asks something else: it divides the 97.51 Seychelles 1 points outstanding at 1 May 2026 by the time remaining until the Seychelles 1 registered completion date. The registered date is the developer's filing for Seychelles 1, not a promise. For a family planning to live in a Seychelles townhouse or villa, the reading worth waiting for is the first Seychelles 1 report that mentions the concrete frames and blockwork of the homes; for an investor, the figure to follow is how the distance between each new Seychelles 1 reading and the third line changes from one inspection to the next.

Get the Next Inspection Figure First

Tell me you are tracking Seychelles at DAMAC Islands and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Seychelles at DAMAC Islands

The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands project rendering of a modern two-storey villa with large glass windows, palm trees and landscaped gardens in Dubai - Presented by Tohid Fetrat

Seychelles at DAMAC Islands: Townhouses and Villas at Three Price Levels

Seychelles at DAMAC Islands brings 678 DAMAC Properties homes to Dubailand, pairing 4 and 5 bedroom townhouses with 6 bedroom villas.

View the Seychelles at DAMAC Islands Project Guide

Considering an Early-Stage Entry?

Homes in Seychelles come from two phases that the DLD records separately, in three types, and the mix still for sale changes as sales progress. Tell me what drew you to the Seychelles 1 record and I will check which townhouses and villas can be bought today and which phase each belongs to.

Ask About Remaining Availability on WhatsApp

Stage Record

Seychelles at DAMAC Islands Build Stages, Mapped to the Inspections

The five stages below follow the order of a low-rise build, and each carries the Seychelles 1 window it occupies on the register: two are dated from the Seychelles 1 entry between 5 May 2025 and the 2.49% Seychelles 1 reading of 1 May 2026, and three have no Seychelles 1 date yet because the register has not reached them.

May 2025 to Oct 2025

DLD Registration and Recorded Start

The DLD entered Seychelles 1 as project 3698 on 5 May 2025, and its construction start was recorded 149 days later, on 1 October 2025, opening the register record for its 204 homes.

Current PhaseOct 2025 onward, Seychelles 1 at 2.49% on 1 May 2026

Mobilisation, Enabling Works and Services

Seychelles 1 read 0.44% on 4 November 2025 and 2.49% on 1 May 2026. The May report set Seychelles 1 at Enabling Works - Progressing, with mobilisation ongoing, enabling works progressing at an advanced stage and infrastructure works on deep service excavation.

Not yet in the record

Concrete Frames and Blockwork

RERA describes the Seychelles 1 homes as concrete structures with block walls; on 1 May 2026, no Seychelles 1 note yet referred to that work.

Still to come

Inside and Outside Finishes

Finishing inside and outside the homes follows the frames, across the G+2 and G+1 house types listed for Seychelles 1, with each Seychelles phase tracked on its own record.

Toward Q2 2029

Completion and Handover

Handover across the Seychelles cluster is expected in Q2 2029. On the register, Seychelles 1 carries 30 June 2029 as its completion date; for an individual home, the binding date is the one in its SPA.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Seychelles at DAMAC Islands's own record.

Buyer Position

Tracking Your Position at Seychelles at DAMAC Islands

This page is one of four project resources that together cover a Seychelles at DAMAC Islands purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands construction updates cover image featuring a project rendering of a modern villa with tall windows, balconies and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Seychelles at DAMAC Islands Construction Updates

This page: every dated Seychelles 1 register reading, the pace between them, and Q2 2029.

Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands Golden Visa concept graphic showing a gold visa card over a rendered modern villa and swimming pool in Dubai - Presented by Tohid Fetrat

Seychelles Golden Visa: Three Home Types and an Off-Plan Application

Seychelles at DAMAC Islands, by DAMAC Properties, lists townhouses and villas that each clear the AED 2M Golden Visa threshold alone.

Read the Seychelles at DAMAC Islands Golden Visa Guide
Seychelles at DAMAC Islands by DAMAC Properties in DAMAC Islands escrow concept graphic showing a shield and padlock beside a rendered modern villa with a driveway in Dubai - Presented by Tohid Fetrat

Seychelles 1 Escrow: Pay the Account Your SPA Names

Seychelles 1, DLD project 3698 on plot 14061, holds payments for 204 units in Emirates NBD escrow, apart from Seychelles 2.

Verify the Seychelles at DAMAC Islands Escrow Account

Approaching Handover

Between 2.49% and Handover: What Seychelles at DAMAC Islands Buyers Should Do Now

With Seychelles 1 recorded at 2.49% on 1 May 2026 and its RERA notes on that date about mobilisation, enabling works and service excavation, the record describes ground preparation rather than houses, so the useful checks for a Seychelles buyer sit in documents. DAMAC's DAMAC Islands payment plan sets each instalment by months from the sale, not by a construction stage, which means a due date in your SPA arrives whatever the next reading shows. This is the plan DAMAC issued at the DAMAC Islands launch in November 2024; confirm the current schedule for your Seychelles phase with DAMAC and in the SPA.

First, send each transfer only to the escrow account of the phase you bought into. Every Seychelles phase is a separate DLD project with its own escrow account: Seychelles 1 (project 3698) uses Emirates NBD, while anyone buying in Seychelles 2 should copy the account details from the SPA or Oqood of that home, confirm them on Dubai REST and never pay into the Seychelles 1 account; the Seychelles at DAMAC Islands escrow account page walks through that check.

Second, if residency matters to you, set the value on your Oqood, and later on your title deed, against the AED 2M ≈ USD 545K line explained in the Seychelles at DAMAC Islands Golden Visa guide: at listed prices the 4 Bedroom Townhouse from AED 2.25M ≈ USD 613K clears it by AED 250,000 ≈ USD 68K, and the 6 Bedroom Villa, listed from AED 6.50M ≈ USD 1.77M, sits AED 4.50M ≈ USD 1.23M above it, so every listed type is over the line, with the value recorded for your own unit deciding the case.

Third, read progress only from dated figures: the Seychelles at DAMAC Islands May 2026 construction update documents the Seychelles 1 visit of 1 May 2026 in full, and new Seychelles 1 readings, plus the first Seychelles 2 figures, are entered in the timeline on this page as soon as they reach me.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Islands Structure

Seychelles 1 percentages read better with the surroundings in view. The three pages below place the cluster in the DAMAC Islands market, its masterplan and its developer's wider record:

Aerial view of DAMAC Islands properties for sale in Dubai showing modern residences, landscaped greenery and expansive lagoon style water features, Presented by Tohid Fetrat

DAMAC Islands Properties for Sale | Villas & Townhouses

Explore villas and townhouses for sale across DAMAC Islands, with project prices, property sizes, payment plans and handover dates.

See DAMAC Islands Properties for Sale
DAMAC Islands by DAMAC Properties aerial masterplan showing lagoon network island amenities and villa communities in Dubai - Presented by Tohid Fetrat

DAMAC Islands Community Overview

Read the DAMAC Islands guide: six themed lagoon clusters of waterfront villas and townhouses, with masterplan and payment plans.

Explore the DAMAC Islands Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Seychelles at DAMAC Islands Construction Updates Frequently Asked Questions

The most recent DLD figure supplied puts Seychelles at DAMAC Islands at the enabling stage: Seychelles 1 (project 3698), one of the two phases the cluster is registered in, read 2.49% on 1 May 2026 under the RERA progress status Enabling Works - Progressing. That RERA report gives a status in words and no percentage, so the 2.49% for Seychelles 1 is taken from the register entry itself. Because that figure was 187 days old by the time this page was written, Seychelles 1 may have been inspected again since; the Seychelles 1 stage record places the reading among the five build stages.

The Seychelles 1 entry (DLD project 3698) opens with registration on 5 May 2025 and a recorded construction start on 1 October 2025, 149 days later. Two dated Seychelles 1 readings follow, 0.44% on 4 November 2025 and 2.49% on 1 May 2026, a rise of 2.05 points between them. The May visit itself is described in the Seychelles 1 May 2026 inspection update.

Q2 2029 is the expected handover quarter for Seychelles at DAMAC Islands, and the DLD record for Seychelles 1 (project 3698) ends inside it, with a registered completion date of 30 June 2029. That Seychelles 1 date is the developer's filing for one phase only: no completion date is shown here for Seychelles 2, and the date that binds an individual home is the one written into its SPA. If the Seychelles 1 filing is ever revised, the change shows first on Dubai REST, and the timeline on this page is updated from there.

Seychelles at DAMAC Islands contains 678 homes across the cluster, offered as 4 Bedroom Townhouses, 5 Bedroom Townhouses and 6 Bedroom Villas. For Seychelles 1 (project 3698), the RERA progress report on the 1 May 2026 inspection lists 204 G+2 and G+1 townhouses and villas, planned as concrete-framed homes with block walls; Seychelles 2 is registered separately with its own DLD record. Sizes, prices and layouts are in the Seychelles at DAMAC Islands project guide.

Between 0.44% on 4 November 2025 and 2.49% on 1 May 2026, Seychelles 1 (DLD project 3698) gained 2.05 points in 178 days. To stand at 100% on its registered completion date of 30 June 2029, Seychelles 1 would need the remaining 97.51 points within the 1,156 days that followed the May reading. Both spans are converted to rates per 30-day month in the Seychelles 1 pace analysis, as arithmetic, not a forecast. Readings taken while Seychelles 1 was still on enabling works and service excavation say little about how fast its homes will rise once their structures start.

Seychelles 2 readings appear here once its DLD data is supplied; no date for that is known, and until then this record follows Seychelles 1 (project 3698) alone, last supplied at 2.49% on 1 May 2026. Seychelles 2 is registered separately with its own DLD record; buyers in Seychelles 2 check their own phase's record on Dubai REST and the escrow details in their SPA. Its first readings will be entered as separately labelled rows in the Seychelles construction timeline, so the figures of the two phases are never mixed.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Seychelles at DAMAC Islands construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status