Skyscape Avenue by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a split composition of project renderings showing high-rise residential towers in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2

Skyscape Avenue Construction Updates

A Three-Tower Register Record, Read for Skyscape Avenue in Sobha Hartland 2

Skyscape Avenue sits inside DLD project 3160, a three-tower registration recorded at 38.27% on 21 September 2026, 767 days after its August 2024 start, with foundations completed.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

38.27%Construction Progress
21 September 2026Latest RERA Inspection
640 residences in Skyscape AvenueTotal Units
Project 3160 (registered as Skyscape)DLD Registration

Construction Snapshot

Skyscape Avenue at a Glance

Skyscape Avenue is the 640-residence Sobha Realty tower in Sobha Hartland 2 that the developer's floor plans identify as Tower B of the Skyscape development. The Dubai Land Department does not record it as a project of its own: Skyscape Avenue is one of the towers of the development registered with the DLD as project 3160 "Skyscape", which can be searched under that number on Dubai REST. Every register figure below, from the 15 August 2024 start to the 38.27% read on 21 September 2026, therefore describes all three towers together, and the one figure that belongs to this tower alone is its 640 residences.

DLD Project Number

3160 (registered as Skyscape)

Project Status

Active, Main Contract Progressing

Construction Start

15 August 2024

Total Units

640 residences in Skyscape Avenue

Total Built-Up Area

200,769.72 sq m (joint DLD register)

Registered Completion Date

31 December 2029

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Skyscape Avenue Construction Update Timeline

The Skyscape record holds a single dated reading so far: 38.27% at the RERA inspection of 21 September 2026. Its inspection card also lists a previous reading of 30.08%, 8.19 points lower, but without a date, so it sits on the track below as an undated dot and not as a table row. Three register dates frame the build around those readings: construction started on 15 August 2024, the project was registered on 09 October 2024, and the registered completion date is 31 December 2029, the last day of the Q4 2029 quarter in which Skyscape Avenue is scheduled for handover.

Inspection MonthConstruction ProgressInspection DateFull Update
September 202638.27%21 September 2026View the September 2026 update

Pace Analysis

How Fast Skyscape Avenue Has Been Built

With one dated inspection in the Skyscape record, pace here is arithmetic across register dates rather than a speed measured between two inspections. Both figures cover the whole three-tower registration and neither is a forecast:

  • Aug 2024 to Sep 2026: whole-build average from the 15 August 2024 start to 38.27% on 21 September 2026, over 767 daysAbout 1.50 points per month
  • Sep 2026 to Dec 2029: rate needed to cover the remaining 61.73 points by the 31 December 2029 registered completion date, over 1,197 daysAbout 1.55 points per month

What this record cannot show yet is a curve. A single dated reading gives two fixed points, the August 2024 start and 21 September 2026, so there is no acceleration or taper to read, and the 30.08% previous value cannot be placed in time. The RERA report of 21 September 2026 does show where the registration stands inside that average: enabling and foundation works completed, with structure, MEP, the external envelope and finishes all logged at different stages across three buildings. The next dated inspection will turn these two arithmetic figures into the first measured pace for project 3160. For an end user planning a Q4 2029 move, that reading is the one to watch; for an investor funding the construction 40% of the 60/40 plan, it shows whether register progress and the payment dates in each SPA are moving together.

Get the Next Inspection Figure First

Tell me you are tracking Skyscape Avenue and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Skyscape Avenue at Sobha Hartland 2

A register percentage only means something next to what is being delivered. The full project guide covers the tower this record follows:

Skyscape Avenue by Sobha Realty in Sobha Hartland 2 project rendering of three high-rise residential towers with curved balconies and a shared podium in Dubai - Presented by Tohid Fetrat

Skyscape Avenue by Sobha Realty | Apartments in Sobha Hartland 2

Explore Skyscape Avenue apartments in Sobha Hartland 2, Dubai, with floor plans, payment details, lifestyle amenities and availability.

View the Skyscape Avenue Project Guide

Considering a Mid-Construction Entry?

Units at Skyscape Avenue are listed as available, and the mix across the five layouts keeps moving while the structure rises. If this record is what brought you here, ask me what is open now before you weigh it against finished homes nearby.

Ask About Remaining Availability on WhatsApp

Stage Record

Skyscape Avenue Build Stages, Mapped to the Inspections

Each stage below is pinned to the register dates and the 21 September 2026 inspection notes for the Skyscape registration, so the windows show where the three-building project actually stood rather than a textbook sequence; no stage is assigned to Skyscape Avenue on its own.

Aug 2024 to Oct 2024

Site Start and Registration

Construction is recorded as started on 15 August 2024, 55 days before the Skyscape registration date of 09 October 2024; both dates appear here exactly as the register prints them.

Aug 2024 to Sep 2026

Enabling Works and Foundations

By the 21 September 2026 inspection, enabling and foundation works were recorded as completed for all three buildings of project 3160, with mobilisation still listed as ongoing.

Current Phase38.27% at 21 Sep 2026

Structure Across Three Buildings

Structural works are logged as progressing at different stages across the registration, and the 38.27% register reading is the combined figure for that whole structural front, not a level for one tower.

Already under way at 21 Sep 2026

Envelope, MEP and Internal Works

MEP, internal works, the external envelope and internal finishes were already recorded as progressing at different stages on site, overlapping the structure rather than waiting for it to finish.

To Q4 2029, registered 31 Dec 2029

Completion and Handover

61.73 points separate the 38.27% reading from 100%; Skyscape Avenue is scheduled for handover in Q4 2029, and the registration's completion date is recorded as 31 December 2029.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Skyscape Avenue's own record.

Buyer Position

Tracking Your Position at Skyscape Avenue

This page is one of four project resources that together cover a Skyscape Avenue purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Skyscape Avenue by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a split composition of project renderings showing high-rise residential towers in Dubai - Presented by Tohid Fetrat
You Are Here

Skyscape Avenue Construction Updates

This page: the dated Skyscape register record for Skyscape Avenue, from August 2024 to handover.

Skyscape Avenue by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic with a gold card beside a landscaped pedestrian garden and residential towers in Dubai - Presented by Tohid Fetrat

Skyscape Avenue Golden Visa: Eligible Apartments and Off-Plan Requirements

Discover which Skyscape Avenue apartments meet Dubai Golden Visa requirements, with eligible layouts, off-plan application timing and ownership guidance.

Read the Skyscape Avenue Golden Visa Guide
Skyscape Avenue by Sobha Realty in Sobha Hartland 2 escrow account concept graphic featuring a shield and padlock over a project rendering of towers beside a swimming pool in Dubai - Presented by Tohid Fetrat

Skyscape Avenue Escrow Account: Dubai Islamic Bank and DLD Verification

Verify Skyscape Avenue escrow details, Dubai Islamic Bank registration and DLD payment safeguards before transferring funds for your apartment.

Verify the Skyscape Avenue Escrow Account

Approaching Handover

Between 38.27% and Handover: What Skyscape Avenue Buyers Should Do Now

The 38.27% register reading of 21 September 2026 leaves 61.73 points of construction ahead for the Skyscape registration, and for Skyscape Avenue buyers on the 60/40 plan that stretch is where the construction 40% is paid, on dates each SPA sets. Those dates do not wait for the next inspection to be published, so the three checks below belong before your next construction-stage transfer, not after it.

First, match every construction-stage transfer to the Dubai Islamic Bank account set out on the Skyscape Avenue escrow account page, which explains why that account belongs to the whole Skyscape registration rather than to one tower.

Second, if residency is part of your plan, confirm on the Skyscape Avenue Golden Visa guide whether your layout clears the threshold, since only the 2, 2.5 and 3 Bedroom tiers do and the off-plan route runs through Oqood until the title deed is issued.

Third, read each new reading against the last one: the Skyscape Avenue September 2026 construction update sets out what the RERA report found on site at 38.27%, and the next dated inspection will be the first that allows a measured pace.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Sobha Hartland 2 Structure

A register reading for three towers is easier to judge with the community around them in view. These three pages put the Skyscape Avenue build in its market, masterplan and developer context:

Aerial view of Sobha Hartland 2 properties for sale in Dubai showing modern residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments

Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.

See Sobha Hartland 2 Properties for Sale
Aerial night view of Sobha Hartland 2 in Dubai showing illuminated residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra

Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.

Explore the Sobha Hartland 2 Community
Sobha Developer Dubai – luxury skyscraper with rooftop pool and skyline view of Burj Khalifa

Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels

Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.

View the Sobha Realty Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Skyscape Avenue Construction Updates Frequently Asked Questions

Skyscape Avenue is under construction as part of DLD project 3160, registered as Skyscape and recorded as Active, which read 38.27% at the RERA inspection of 21 September 2026. That figure covers all three towers of the Skyscape registration, not Skyscape Avenue alone, and the inspection report lists the main contract as progressing with structural works at different stages. The dated record is in the Skyscape Avenue inspection timeline above.

Progress for Skyscape Avenue is read from DLD project 3160, registered as Skyscape, which records one percentage for all three towers together: 38.27% at the RERA inspection of 21 September 2026. This page dates every reading it can, files the register's undated previous figure of 30.08% as a dot without a month, and never splits the percentage tower by tower. The site notes behind the dated reading are in the September 2026 inspection record for Skyscape Avenue.

Handover of Skyscape Avenue is scheduled for Q4 2029, and the registered completion date for the whole Skyscape registration, as recorded on 21 September 2026, is 31 December 2029, the closing day of that quarter, so the two dates point to the same quarter. The registered date has not passed, and with 61.73 points still between the 38.27% reading and 100%, this page's record is updated as each new inspection is entered for project 3160.

Skyscape Avenue has 640 residences, the figure for this tower alone, while DLD project 3160 registers the three towers of the Skyscape development together as one project. The register's project details, like its 38.27% reading of 21 September 2026, describe that whole registration, so this page uses 640 for Skyscape Avenue and prints no registration-wide unit total or area as if it belonged to one tower.

Averaged from the 15 August 2024 construction start, the Skyscape registration's 38.27% reading of 21 September 2026 works out to about 1.50 points per month over 767 days. Reaching 100% by the 31 December 2029 registered completion date would take about 1.55 points per month over the remaining 1,197 days. Both figures are arithmetic, not a forecast, and a measured pace between two dated inspections is not yet possible because the previous 30.08% reading carries no date. The working is in the Skyscape pace analysis above.

The DLD register records the construction start for project 3160 as 15 August 2024 and the project's registration as 09 October 2024, so the recorded start comes 55 days before the registration date; both dates are shown as the register prints them. The first dated reading in this record followed on 21 September 2026, at 38.27% for the whole registration.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Skyscape Avenue construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status