Skyvue Spectra by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of two residential towers linked by an elevated skybridge in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2

Skyvue Spectra Construction Updates

A Q1 2029 Handover, Followed Reading by Reading on the Shared Skyvue Register

Skyvue Spectra's four-tower Skyvue registration read 10.54% on 30 July 2026, an opening entry that measures shared groundwork rather than Spectra's own 327-apartment tower.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

10.54%Construction Progress
30 July 2026Latest RERA Inspection
327 apartments in Skyvue SpectraTotal Units
Project 3435, listed as SkyvueDLD Registration

Construction Snapshot

Skyvue Spectra at a Glance

Within Sobha Realty's four-tower Skyvue development in Sobha Hartland 2, Skyvue Spectra is the 327-apartment building that the developer factbook configures as G+5P+42+ROOF: a ground level, five podium levels, 42 floors and a roof. The Dubai Land Department keeps no separate entry per tower. All four sit under one record, project 3435, named simply Skyvue; that is the name to enter when you look the project up, and it is why every register figure quoted here describes the four towers as a group, never Spectra on its own. The shared record took 485 days to move from its 01 April 2025 construction start to the 10.54% reading of 30 July 2026; for Spectra's apartments, Sobha Realty names Q1 2029 as the handover.

DLD Project Number

3435, listed as Skyvue

Project Status

Active

Construction Start

01 April 2025

Total Units

327 apartments in Skyvue Spectra

Total Built-Up Area

235,150.80 sq m (joint DLD register)

Registered Completion Date

31 March 2030 (whole Skyvue registration)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Skyvue Spectra Construction Update Timeline

Three register dates and one dated reading make up this record so far. The Skyvue entry was registered on 25 February 2025, its construction start was entered as 01 April 2025, thirty-five days later, and the first reading that carries a date is 10.54% from the inspection of 30 July 2026. The register also lists an earlier reading of 5.11% with no date beside it, so that reading appears on the track as an unlabelled dot and has no table row of its own. The July 2026 update for Skyvue Spectra opens with a Sobha Realty rendering of the planned entrance, which shows design intent, not the site.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202610.54%30 July 2026View the July 2026 update

Pace Analysis

How Fast Skyvue Spectra Has Been Built

One dated reading cannot yet give an inspection-to-inspection pace for the Skyvue registration. The register dates do support two pieces of arithmetic, both for the whole four-tower entry and both arithmetic, not a forecast:

  • 01 Apr 2025 to 30 Jul 2026: whole-build average, 10.54 points over 485 daysAbout 0.65 points per month
  • 30 Jul 2026 to 31 Mar 2030: rate needed for 100% by the registered completion date, 89.46 points over 1,340 daysAbout 2.00 points per month

Put next to each other, 0.65 and 2.00 describe where the Skyvue record starts, not how it will run. The first figure averages roughly sixteen months that took the shared site from an entered start into mobilisation, enabling works and foundations, work that adds little to a percentage while it is under way. The second is only the average the registration would need to reach 100% by 31 March 2030. Neither figure belongs to Skyvue Spectra: the register reports one number for the group, so no rate toward Spectra's own Q1 2029 handover can be drawn from it, and the undated 5.11% supplies no second dated point. A genuine inspection-to-inspection rate needs a second dated reading, and the next one the register publishes after 30 July 2026 will supply it. For a buyer who plans to live in one of the 327 apartments, the useful question is whether readings start to climb once structure takes over the site; for an investor, it is how many inspection cycles that takes. Both answers arrive with later dated readings, not with this first set of sums.

Get the Next Inspection Figure First

Tell me you are tracking Skyvue Spectra and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Skyvue Spectra at Sobha Hartland 2

Sobha Realty's plans for Skyvue Spectra are what the 10.54% register reading of 30 July 2026 eventually has to turn into, and the project guide sets them out tower first rather than register first:

Skyvue Spectra by Sobha Realty in Sobha Hartland 2 project rendering of residential towers connected by a raised skybridge with a green arrow pointing towards the upper tower section in Dubai - Presented by Tohid Fetrat

Skyvue Spectra: 327 Residences in One of the Four Skyvue Towers

Skyvue Spectra is a Sobha Realty high-rise in Sobha Hartland 2, with 1 to 3 bedroom layouts and a 60/40 plan.

View the Skyvue Spectra Project Guide

Considering an Early-Stage Entry?

Availability at Skyvue Spectra shifts with each release while the Skyvue site is still in its groundwork phase. If this record is what brought you here, ask me which apartment types are open today before you settle on a layout.

Ask About Remaining Availability on WhatsApp

Stage Record

Skyvue Spectra Build Stages, Mapped to the Inspections

Five windows frame this record, from the February 2025 registration of project 3435 to the Q1 2029 handover Sobha Realty gives for Skyvue Spectra: two carry dated register evidence, a third is noted in the July 2026 report, and the last two have no reading yet.

25 Feb 2025 to 01 Apr 2025

Registration and Entered Start

The DLD registered the Skyvue project, number 3435, on 25 February 2025 and entered 01 April 2025 as its construction start, thirty-five days afterward.

Current PhaseFrom Apr 2025, 10.54% on 30 Jul 2026

Mobilisation, Enabling Works and Foundations

RERA's report of 30 July 2026 finds the shared site still being mobilised, with enabling works and foundations advancing, and the register at 10.54% for all four towers.

Noted on 30 Jul 2026

Structure Works on the Shared Site

The same report also has structure works in progress but names no building, so it gives no structural figure for Skyvue Spectra on its own.

After later readings, before Q1 2029

Glazed Facade, Interiors and Amenities

The double-glazed curtain wall facade and apartment fit-out set out in the developer factbook, along with the planned amenities, have no reading yet.

Q1 2029 handover, 31 Mar 2030 registered

Completion and Handover

Sobha Realty gives Q1 2029 for handing the 327 Skyvue Spectra apartments to buyers; the register's completion date for the whole Skyvue registration is 31 March 2030.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Skyvue Spectra's own record.

Buyer Position

Tracking Your Position at Skyvue Spectra

This page is one of four project resources that together cover a Skyvue Spectra purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Skyvue Spectra by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of two residential towers linked by an elevated skybridge in Dubai - Presented by Tohid Fetrat
You Are Here

Skyvue Spectra Construction Updates

This page: dated Skyvue register readings for Skyvue Spectra, from the 25 February 2025 registration onward.

Skyvue Spectra by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic showing a gold visa card over a rendered landscaped waterfront and pool area in Dubai - Presented by Tohid Fetrat

Skyvue Spectra Golden Visa: Four Bedroom Types Above AED 2M

Skyvue Spectra, in Sobha Realty's four-tower Skyvue development, qualifies at the 1.5, 2, 2.5 and 3 bedroom types above AED 2M.

Read the Skyvue Spectra Golden Visa Guide
Skyvue Spectra by Sobha Realty in Sobha Hartland 2 escrow account concept graphic showing a shield and padlock over a rendered circular pool and landscaped courtyard in Dubai - Presented by Tohid Fetrat

Skyvue Spectra Escrow Account and the Skyvue Registration

Skyvue Spectra's escrow for 327 apartments sits at Dubai Islamic Bank on DLD project 3435, certified at 10.54% in July 2026.

Verify the Skyvue Spectra Escrow Account

Approaching Handover

Between 10.54% and Handover: What Skyvue Spectra Buyers Should Do Now

With the Skyvue registration reading 10.54% on 30 July 2026, a Skyvue Spectra buyer on Sobha Realty's 60/40 plan pays construction-stage installments long before there is an apartment to inspect, and each SPA, not the register, decides when they fall due. That makes the next payment, not the handover appointment, the deadline for the three checks below.

First, confirm before every transfer that the receiving account is the escrow account held at Dubai Islamic Bank for project 3435; the Skyvue Spectra escrow account check shows how to match it to the register entry.

Second, if residency is part of the plan, test your unit type against the AED 2M ≈ USD 545K threshold in the Skyvue Spectra Golden Visa threshold guide; the 1 Bedroom from AED 1.25M ≈ USD 340K falls below it, while the 1.5, 2, 2.5 and 3 Bedroom types sit above it.

Third, compare each new register reading with the 30 July 2026 baseline in the Skyvue Spectra July 2026 construction record, so that any shift in momentum shows up ahead of the installment it might affect.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Sobha Hartland 2 Structure

The Skyvue register follows a construction site; the market, the master community and the developer around that site decide what a Skyvue Spectra apartment is worth by handover. These three pages cover each of them:

Aerial view of Sobha Hartland 2 properties for sale in Dubai showing modern residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments

Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.

See Sobha Hartland 2 Properties for Sale
Aerial night view of Sobha Hartland 2 in Dubai showing illuminated residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra

Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.

Explore the Sobha Hartland 2 Community
Sobha Developer Dubai – luxury skyscraper with rooftop pool and skyline view of Burj Khalifa

Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels

Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.

View the Sobha Realty Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Skyvue Spectra Construction Updates Frequently Asked Questions

Skyvue Spectra is at an early construction stage within DLD project 3435, the Active register entry named Skyvue, which read 10.54% at the inspection of 30 July 2026 for all four Skyvue towers together. RERA's monitoring report of the same date gives the status Main Contract, Progressing, with enabling and foundation works under way on the shared site. The dated entries are in the Skyvue Spectra inspection timeline above.

The 30 July 2026 inspection put the four-tower Skyvue registration, which includes Skyvue Spectra, at 10.54%, up 5.43 points from a previous register reading of 5.11%. The register prints no date for that earlier reading, so the 5.43-point rise cannot be spread over a known number of months. The Skyvue Spectra July 2026 construction update covers that inspection in full.

Skyvue Spectra is expected to be handed to buyers in Q1 2029, the quarter Sobha Realty gives for the tower, and Sobha Realty's project documents name 31 March 2029 as its anticipated completion date. The DLD entry, which spans all four Skyvue towers, carries 31 March 2030 as its registered completion date; a date set for the whole registration is not required to line up with the handover quarter of one tower within it. When the 30 July 2026 inspection put the registration at 10.54%, the remaining distance to 100% for the four towers combined was 89.46 points.

Skyvue Spectra holds 327 apartments in 1, 1.5, 2, 2.5 and 3 bedroom types, according to Sobha Realty. The register entry for project 3435 counts units and area for all four Skyvue towers at once, so its totals are not Skyvue Spectra figures, and this page gives no built-up area for the tower because the record publishes no tower-level area.

Across the whole Skyvue registration, the 10.54 points recorded by 30 July 2026 average about 0.65 points per month over the 485 days since the 01 April 2025 start. To finish by the registered completion date of 31 March 2030, the registration would need about 2.00 points per month over the remaining 1,340 days. Both are arithmetic, not a forecast, and neither is a rate for Skyvue Spectra alone; the Skyvue Spectra pace analysis shows the working.

The record for Skyvue Spectra begins with the DLD registration of the Skyvue project on 25 February 2025, followed by a construction start entered as 01 April 2025, thirty-five days later. The first dated reading came at the 30 July 2026 inspection, 10.54% for the four-tower registration, and each later inspection on this page is measured from that point.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Skyvue Spectra construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status