Sobha Elwood Villas Construction Updates
The Dated Register Record of 305 Forest-Set Villas Off the Dubai-Al Ain Road
Sobha Elwood Villas read 14.35% on the DLD project register on 20 July 2026, the opening dated reading of a record following 305 standalone Dubailand villas.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Sobha Elwood Villas at a Glance
Sobha Elwood Villas is Sobha Realty's collection of 305 standalone villas inside the Sobha Elwood master community on the Dubai-Al Ain Road in Dubailand, with handover expected in Q2 2027. Construction started on 15 July 2025, and the DLD project register read 14.35% on 20 July 2026, 370 days later. Because the build is spread across 305 separate G+1 and G+2 homes rather than a single structure, each reading on this page is one figure for every villa plot and the streets between them.
3602
Active
15 July 2025
305 Villas
184,671.13 sq m
30 June 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Sobha Elwood Villas Construction Update Timeline
The Sobha Elwood Villas record holds one dated reading so far: 14.35% on 20 July 2026, a year and five days after the 15 July 2025 start. The register also lists a previous inspection reading of 10.18% with no date attached, so it sits on the track below as an unlabelled dot and has no row in the table. Each dated reading links its full monthly update, and July 2026 opens the series.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 14.35% | 20 July 2026 | View the July 2026 update |
Reading the dates: the DLD register lists 30 June 2028 as the registered completion date for project 3602, an administrative anchor set at registration on 29 April 2025, while the expected handover for buyers is Q2 2027. The register's previous inspection reading of 10.18% carries no date, which is why it appears on the track but not in the table.
Pace Analysis
How Fast Sobha Elwood Villas Has Been Built
With a single dated reading, Sobha Elwood Villas has no measured pace between inspections yet. What its own register dates do allow is arithmetic, set out below and labelled for what it is:
- Jul 2025 to Jul 2026: whole-build average from the 15 July 2025 start, 0% to 14.35% over 370 daysAbout 1.16 points per month (arithmetic, not a forecast)
- Jul 2026 to Jun 2028: rate to reach 100% by the registered completion date, 85.65 points over 711 daysAbout 3.61 points per month (arithmetic, not a forecast)
- Previous inspection to 20 Jul 2026: 10.18% to 14.35%, earlier reading undated in the register4.17 points, no time span on record
None of these three figures is a velocity. The first spreads the 14.35% reading over the 370 days since ground was broken; the second spreads the 85.65 points still to be recorded over the 711 days to the registered completion date of 30 June 2028; the third is a gap between two readings, one of which has no date. A true pace for Sobha Elwood Villas needs a second dated register reading after 20 July 2026, and that reading is the one to watch: for an investor it is the first test of how quickly 305 separate villa structures move together, and for an end user it is the first figure to set against the milestone schedule in your SPA.
Get the Next Inspection Figure First
Tell me you are tracking Sobha Elwood Villas and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Sobha Elwood Villas at Sobha Elwood
A 14.35% reading only means something next to what is being built: 305 detached villas in G+1 and G+2 forms, each with its own pool. The full project guide covers what buyers are tracking toward on this page:

Sobha Elwood Villas: Pool Villas in a Forest-Themed Community
Sobha Elwood Villas is a Sobha Realty collection of 305 standalone villas, each with a private pool and backyard.
View the Sobha Elwood Villas Project GuideConsidering an Early-Construction Entry?
Availability at Sobha Elwood Villas shifts as the build advances and villa plots are taken. If the record on this page is what brought you here, ask me which villa types and plots remain before you settle on a layout.
Ask About Remaining Availability on WhatsAppStage Record
Sobha Elwood Villas Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates in the Sobha Elwood Villas record rather than a generic sequence. The 20 July 2026 inspection found structural and services packages progressing side by side, so two of the stages share the same window.
Registration and Site Activation
Project 3602 entered the DLD register on 29 April 2025, and construction started on 15 July 2025, opening the plot for the 305-villa build.
Enabling Works, Foundations, and Villa Structures
Enabling works, foundation, substructure and superstructure were all recorded progressing at the 20 July 2026 inspection, with the DLD register at 14.35%.
Internal Works, MEP, and Infrastructure
The same 20 July 2026 inspection already recorded internal works, MEP and site infrastructure progressing, running alongside the villa structures rather than after them.
Villa Exteriors, Private Pools, and Landscaping
Exteriors, the private pool planned for every villa and plot landscaping carry no dated reading so far; each will be placed here as register readings record it.
Finishing and Handover of the 305 Villas
Interior finishing, villa systems and handover, expected in Q2 2027; the DLD register lists a registered completion date of 30 June 2028 for project 3602.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sobha Elwood Villas's own record.
Buyer Position
Tracking Your Position at Sobha Elwood Villas
This page is one of four project resources that together cover a Sobha Elwood Villas purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sobha Elwood Villas Construction Updates
This page: the dated DLD register record for Sobha Elwood Villas, from construction start to handover.

Sobha Elwood Villas Golden Visa: Each Standalone Villa by Itself
Sobha Realty's 305 standalone villas at Sobha Elwood Villas, beside the Dubai-Al Ain Road, qualify at all three villa types.
Read the Sobha Elwood Villas Golden Visa Guide
Sobha Elwood Villas Escrow: Sobha Realty's Account at First Abu Dhabi Bank
Sobha Realty's Sobha Elwood Villas, DLD project 3602, escrows 305 units at First Abu Dhabi Bank, 14.35% certified July 2026.
Verify the Sobha Elwood Villas Escrow AccountApproaching Handover
Between 14.35% and Handover: What Sobha Elwood Villas Buyers Should Do Now
At 14.35% on 20 July 2026, Sobha Elwood Villas is in the stretch where foundations and villa structures are still being recorded, and most of a buyer's payment decisions lie ahead of the Q2 2027 handover. These three steps are easiest to settle while the record is short, before your next installment falls due.
First, confirm that every installment goes to the DLD-registered trust account for project 3602 with First Abu Dhabi Bank P.J.S.C.; the Sobha Elwood Villas escrow account page shows how to check the account against the official record.
Second, if residency matters to your plans, settle eligibility early through the Sobha Elwood Villas Golden Visa page, since every villa type is priced from AED 9.92M ≈ USD 2.70M upward and the guide sets out how an off-plan villa purchase is assessed.
Third, follow the record itself: each dated register reading after 20 July 2026 is added to the inspection timeline above and published as its own monthly update, beginning with the Sobha Elwood Villas July 2026 construction update.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Elwood Structure
A build record is only half the picture; the other half is what is planned around it. These three pages set the 305-villa record in its market, community and developer context:

Sobha Elwood: Forest-Inspired 4, 5 and 6 Bedroom Villas in Dubailand
Sobha Elwood is a forest-inspired Dubailand community by Sobha Realty, with nearly 50% of its master plan green and open space.
See Sobha Elwood Properties for Sale
Sobha Elwood Community Overview
Read the full community guide: master plan, zones and parks, villa types, pricing, connectivity and what living here is actually like.
Explore the Sobha Elwood Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Sobha Elwood Villas Construction Updates Frequently Asked Questions
Sobha Elwood Villas, DLD project 3602, is in its early construction stage: the Dubai Land Department project register read 14.35% on 20 July 2026, and the inspection on that date recorded foundation, substructure and superstructure works progressing across the villa site. The full record is in the inspection timeline above.
One so far. The 14.35% DLD register reading of 20 July 2026 is the only dated reading on record, 4.17 points above the previous inspection reading of 10.18%, which the register lists without a date. That dated reading has its own Sobha Elwood Villas July 2026 inspection report page.
No. The DLD register lists 30 June 2028 as the registered completion date for project 3602, while the expected handover for buyers of Sobha Elwood Villas is Q2 2027. This page prints the register date only in its record slots and uses Q2 2027 wherever handover is meant.
The build covers 305 villas, the count shown in the DLD register for project 3602 and in the RERA report's description of G+1 and G+2 villas. Each is a standalone 4, 5 or 6 bedroom home, so every register reading for Sobha Elwood Villas is one figure covering 305 separate structures and the infrastructure between them.
Construction started on 15 July 2025, 77 days after project 3602 was registered with the DLD on 29 April 2025. The first dated reading on this page's record, 14.35% on 20 July 2026, came 370 days after that start.
No measured pace exists yet, because only one reading on record carries a date. As arithmetic, not a forecast, the 14.35% recorded by 20 July 2026 averages about 1.16 points per 30-day month over the 370 days since the 15 July 2025 start. The working is set out in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sobha Elwood Villas construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.