Sunset Bay 2 by Imtiaz in Island A at Dubai Islands project rendering used for the August 2026 construction update showing layered residential balconies, landscaped terraces and a waterfront outlook in Dubai - Presented by Tohid Fetrat

Imtiaz · Island A, Dubai Islands · Construction Update

Sunset Bay 2 Construction Update - August 2026

August 2026 DLD Register Reading Puts Sunset Bay 2 at 70.2% Construction Progress on Island A

Internal, external and MEP works lead activity at Sunset Bay 2, where the 4 August 2026 RERA report records structural works complete and the register reads 70.2%.

Direct advisor access. Every message answered personally, never by a call center.

70.2%DLD Register Reading
4 August 2026Inspection Date
Q1 2027Expected Handover
3570DLD Project Number

DLD Register Data

Sunset Bay 2 Construction Snapshot

A 27.0 point gap above the previous DLD register reading of 43.2%, a figure the register shows without a date, puts Sunset Bay 2 at the opening of the finishing band, where the questions that remain turn on the completion payment and handover.

Project Name

Sunset Bay 2 by Imtiaz

Project Number

3570

Project Status

Active

Construction Progress

70.2%

Inspection Date

4 August 2026

Construction Start

20-02-2025

Total Units

66 residences

Total Built Area

7,875.74 sq m

Expected Completion

Q1 2027

Data source: DLD project register reading shown against the inspection report dated 4 August 2026 for project 3570, listed under the register name Sunset Bay Two By Imtiaz; the RERA Independent Progress Monitoring Report of the same date supplies the site notes and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is a developer rendering, not a site photograph. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Sunset Bay 2 Construction Progress Summary

The RERA report dated 4 August 2026 marks the point where Sunset Bay 2 stops being a structural job: enabling, foundation and structural works are recorded as completed, and the trades now on site are the internal, external and MEP packages that turn a G+2P+8+R frame into 66 furnished homes.

Completed
  • Enabling works on the Sunset Bay 2 plot
  • Foundation works beneath the single residential building
  • Structural works, recorded as completed in the 4 August 2026 report
In Progress at 70.2%
  • Internal works, with interior fit out shown in the report's inspection photographs
  • External works around the ground, podium and residential levels
  • MEP works: mechanical, electrical and plumbing systems
  • Main contract, with RERA progress status Main Contract, Progressing
Ahead of Handover
  • Remaining DLD register readings between 70.2% and 100%
  • Fully furnished interiors for all 66 residences, per the developer
  • Handover guided for Q1 2027, with a registered completion date of 20-02-2027
Next inspectionPosted in the DLD project register after the next RERA site visit; no date is published in advance, and this page records the 4 August 2026 reading only.
Completion targetHandover guidance Q1 2027; registered completion date 20-02-2027 in the DLD register, 200 days after this reading (project registered 28-02-2025).
Remaining distance29.8 percentage points to 100%: about 4.47 points per month over the 200 days to the registered completion date, against a whole-build average of about 3.97 points per month since the recorded start of 20-02-2025 (arithmetic, not a forecast).

Payment Linked Progress

What 70.2% Progress Means for Sunset Bay 2 Buyers

Sunset Bay 2 runs a date-based 60/40 plan, so instalments follow the calendar rather than the register: at the 4 August 2026 reading, 20 + 5 + 5 + 10 + 10 = 50% of the price had fallen due against 70.2% recorded progress, and the 15 September 2026 instalment that followed brought the dated total to 60%, leaving 40% for completion. From here, four actions matter most.

Before the Completion Payment

Verify the escrow account

The 40% due on completion, like every earlier instalment, belongs only in the DLD regulated escrow account registered for project 3570, listed under the register name Sunset Bay Two By Imtiaz. Sunset Bay 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines the completion payment and the handover notice period, and set those clauses against the Q1 2027 handover guidance and the registered completion date of 20-02-2027. Not sure how your instalments line up with this reading? Send me your SPA schedule and I will map it against the recorded readings.

Window Open Now

Book the snagging window

At 70.2% in the register and with handover guided for Q1 2027, Sunset Bay 2 has entered the usual window for planning a pre handover inspection, and in a fully furnished building that inspection takes in the supplied furniture as well as the finishes. Sunset Bay 2 snagging inspection guide sets out the booking steps before acceptance.

Every Cycle

Track the remaining cycles

29.8 points stand between this reading and 100%, and each later register figure shows how quickly that gap closes. Sunset Bay 2 construction updates hub adds every new reading with its date.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 70.2%?

Entering Sunset Bay 2 at this stage trades payment-plan runway for visibility: the structure is recorded complete, handover is guided for Q1 2027, and the open choice is which of the remaining furnished layouts fits. Every payment goes to the DLD-registered escrow account for project 3570, released against construction progress recorded in the DLD register.

Entering Now at 70.2%
  • Structural works recorded complete in the 4 August 2026 RERA report
  • Handover guided for Q1 2027, a horizon of months rather than years
  • Instalments already due settled at signing and 40% on completion, per the developer's current terms
Typical Launch Entry
  • Construction risk carried through every stage from site enabling onward
  • A delivery horizon usually counted in years
  • More instalments spread out, at launch-level pricing
AED 2.12M ≈ USD 578KStarting Price
60/40 Plan40% Due on Completion
Q1 2027Expected Handover
Ask What Is Available at Sunset Bay 2

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Sunset Bay 2 Project Details

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands residential tower exterior with curved balconies, planted terraces and landscaped surroundings in Dubai - Presented by Tohid Fetrat
Island A, Dubai Islands · Imtiaz

With structural works recorded complete in the 4 August 2026 RERA report, Sunset Bay 2 is one G+2P+8+R building of 66 fully furnished residences: 1 and 2 bedroom apartments above the podium and 3 bedroom duplexes at its base. Starting prices: AED 2.12M ≈ USD 578K.

Entering now means most of the 60/40 plan's dated instalments are settled at signing rather than spread out, with 40% left for completion and handover guided for Q1 2027.

Sunset Bay 2 by Imtiaz Project Guide

Site Context This Cycle

Explore Sunset Bay 2 Location on Dubai Map

Sunset Bay 2 holds its own plot on Island A at Dubai Islands, a plot the developer places steps from the beach and a park. With the structure recorded complete in the 4 August 2026 report, the external works now progressing on that plot are the part of this cycle that decides how the building meets its beach and park setting at street level.

Island A is a new masterplanned island rather than an established district: the developer's materials place six of the nine Dubai Islands marinas and the island's mall on Island A, and the developer's fact sheet puts Infinity Bridge and the Waterfront Market about five minutes away by car. For buyers weighing occupancy or letting from Q1 2027, how far the surrounding plots and amenities have come by then matters as much as this building's own reading. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Sunset Bay 2 by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Sunset Bay 2 as Construction Moves Into Finishing

With the structure recorded complete and the completion payment the largest step left, residency planning, payment protection and handover checks now overlap for Sunset Bay 2 buyers. Each resource below is matched to that point in the build.

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring project renderings of the residential tower with layered balconies and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Sunset Bay 2 Construction Updates

This page: the 4 August 2026 DLD register reading for Sunset Bay 2, with site notes.

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands Golden Visa card graphic over an aerial view of the rooftop pool and landscaped amenity deck in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 by Imtiaz Golden Visa: Every Type Listed Above

Sunset Bay 2, Imtiaz's 66-residence building on Island A, lists all three unit types at or above the threshold.

Read Sunset Bay 2 Golden Visa Guide
Sunset Bay 2 by Imtiaz in Island A at Dubai Islands escrow account protection concept with shield and padlock icons above a landscaped podium garden and pedestrian area in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 Escrow, Past 70% Certified on Island A

First Abu Dhabi Bank holds Sunset Bay 2 escrow as DLD project 3570 for 66 units, certified 70.2% in August 2026.

Verify Sunset Bay 2 Escrow Account
Sunset Bay 2 by Imtiaz in Island A at Dubai Islands snagging inspection concept over a furnished kitchen and dining interior with an inspection checklist icon in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 Snagging: 66 Fully Furnished Residences

Sunset Bay 2 is an Imtiaz building on Island A at Dubai Islands: ground, two podium levels, eight floors, a roof.

Book Sunset Bay 2 Snagging

Update Timeline

Other Sunset Bay 2 Construction Updates

This August 2026 page opens the dated monthly series for Sunset Bay 2; each later DLD register reading joins the hub as it is published.

All Sunset Bay 2 Construction Updates

FAQs

Sunset Bay 2 Construction Progress in August 2026: Frequently Asked Questions

The Dubai Land Department project register showed 70.2% construction progress for Sunset Bay 2, DLD project 3570, against the inspection report dated 4 August 2026. The matching RERA Independent Progress Monitoring Report prints no percentage of its own, so 70.2% is the register figure, and a newer reading may have been posted after this page was prepared.

The register view lists 43.2% as the previous inspection beside the 70.2% August 2026 reading, but shows no date for it. Without that date the interval between the two readings is unknown, so no monthly pace can be measured from the pair; the dated arithmetic on this page runs from the recorded construction start of 20-02-2025 instead.

The record shows no revised date: the DLD register keeps a registered completion date of 20-02-2027, which falls inside the developer's Q1 2027 handover guidance. Closing the remaining 29.8 points by that date works out at about 4.47 points per month, set against a whole-build average of about 3.97 points per month; both are arithmetic, not a forecast. How readings and completion dates are followed over time is covered on the Sunset Bay 2 construction updates hub.

It records enabling, foundation and structural works as completed, with internal, external and MEP works progressing, and gives the RERA progress status as Main Contract, Progressing. The report describes the building as G+2P+8+R and carries inspection photographs of interior works, which remain part of the official record rather than being reproduced on this page.

The DLD register records construction as started on 20-02-2025 and the project as registered on 28-02-2025, with a registered completion date of 20-02-2027. The 4 August 2026 reading came 530 days after the recorded start, and both early dates are shown here exactly as the register lists them.

No. The hero image is a developer rendering of the finished Sunset Bay 2 design, used to identify the project rather than to show site conditions on 4 August 2026. The site evidence for this month is the DLD register reading and the RERA report, whose inspection photographs stay with the official record.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Sunset Bay 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.