Sunset Bay 2 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring project renderings of the residential tower with layered balconies and landscaped podium in Dubai - Presented by Tohid Fetrat

Imtiaz · Island A, Dubai Islands

Sunset Bay 2 Construction Updates

The Register Record of One Furnished Building on Island A

Sunset Bay 2 by Imtiaz reached a 70.2% DLD register reading on 4 August 2026, with 29.8 points of internal, external and MEP works left before handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

70.2%Construction Progress
04-08-2026Latest RERA Inspection
66 residencesTotal Units
Project 3570DLD Registration

Construction Snapshot

Sunset Bay 2 at a Glance

Sunset Bay 2 by Imtiaz is one G+2P+8+R residential building of 66 furnished residences on Island A at Dubai Islands, and its construction record is compact: 530 days separate the recorded start of 20-02-2025 from the 70.2% register reading of 4 August 2026, with the project registered on 28-02-2025. With eight residential floors above a ground floor and two podium levels, this is a short building, and the RERA report of 4 August 2026 records its structural works as completed, so the points still to come belong to work inside and around that frame. The six register anchors below sit behind every figure on this page.

DLD Project Number

3570

Project Status

Active

Construction Start

20-02-2025

Total Units

66 residences

Total Built-Up Area

7,875.74 sq m

Registered Completion Date

20-02-2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Sunset Bay 2 Construction Update Timeline

The Sunset Bay 2 record holds one dated reading so far: 70.2%, shown in the register against the inspection report of 4 August 2026. Beside it the register lists a previous figure of 43.2% with no date attached, which puts the August reading 27.0 points higher; because that earlier figure is undated, it sits on the track below as a dot only, with no table row and no pace measured from it. The single row links the full August 2026 update.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202670.2%04-08-2026View the August 2026 update

Pace Analysis

How Fast Sunset Bay 2 Has Been Built

With only one dated reading, Sunset Bay 2 has no inspection-to-inspection pace yet. What its register dates do support is two pieces of arithmetic, neither of them a forecast:

  • 20-02-2025 to 04-08-2026: recorded start to 70.2%, whole-build average over 530 daysAbout 3.97 points per month
  • 04-08-2026 to 20-02-2027: remaining 29.8 points to the registered completion date, over 200 daysAbout 4.47 points per month needed

The first figure spreads 70.2 points evenly across every month since the recorded start, which no real build does; the second is simply what the remaining 29.8 points would require for the register to reach 100% by the registered completion date of 20-02-2027. The two sit about half a point per month apart. The RERA report of 4 August 2026 shows where those remaining points lie: enabling, foundation and structural works are recorded as completed, and the internal, external and MEP packages are the ones still progressing across the ground floor, two podium levels and eight residential floors. For an end user, the date that matters stays the Q1 2027 handover; for an investor, it is the next dated register reading that will turn these two averages into a measured pace for this building.

Get the Next Inspection Figure First

Tell me you are tracking Sunset Bay 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Sunset Bay 2 at Island A

A register percentage reads differently once you know what the 66 residences behind it are. The full project guide covers what Sunset Bay 2 buyers are waiting on:

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands residential tower exterior with curved balconies, planted terraces and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Sunset Bay 2, a Compact Single Building on Island A

Sunset Bay 2 is a single Imtiaz building of 66 residences over eight floors, steps from a beach and a park.

View the Sunset Bay 2 Project Guide

Considering a Late-Stage Entry?

Sunset Bay 2 shows Limited Units Available, and with the register at 70.2% and handover set for Q1 2027, the furnished layouts still on offer tend to narrow as completion approaches. If the record on this page is what brought you here, ask me for current availability before the layout you want is taken.

Ask About Remaining Availability on WhatsApp

Stage Record

Sunset Bay 2 Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Sunset Bay 2 record actually shows: three stages closed by the RERA report of 4 August 2026, one running at the 70.2% register reading, and one still ahead of the 20-02-2027 registered completion date.

From 20-02-2025

Site Activation and Enabling Works

Construction is recorded as started on 20-02-2025 and the project as registered on 28-02-2025; the enabling works on the Island A plot are listed as completed in the 4 August 2026 report.

Completed by 04-08-2026

Foundations for One Building

Foundation works beneath the single G+2P+8+R building are recorded as completed in the RERA report of 4 August 2026; no dated register reading falls inside this window.

Completed by 04-08-2026

Podium and Eight Residential Floors

Structural works for the ground floor, two podium levels, eight residential floors and roof level are recorded as completed in that report; the undated 43.2% figure cannot be placed within this window.

Current Phase04-08-2026, 70.2% at last reading

Internal, External, and MEP Works

Internal, external and MEP works were progressing at the 4 August 2026 inspection, which the register reads as 70.2%; the report carries inspection photographs of interior works.

To 20-02-2027 registered completion

Furnished Finish and Handover

The remaining 29.8 points to 100%, ending with 66 fully furnished residences, per the developer, and handover scheduled for Q1 2027, when the 40% completion payment falls due.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sunset Bay 2's own record.

Buyer Position

Tracking Your Position at Sunset Bay 2

This page is one of four project resources that together cover a Sunset Bay 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring project renderings of the residential tower with layered balconies and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Sunset Bay 2 Construction Updates

This page: the Sunset Bay 2 register record, from the 20-02-2025 start toward Q1 2027 handover.

Sunset Bay 2 by Imtiaz in Island A at Dubai Islands Golden Visa card graphic over an aerial view of the rooftop pool and landscaped amenity deck in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 by Imtiaz Golden Visa: Every Type Listed Above

Sunset Bay 2, Imtiaz's 66-residence building on Island A, lists all three unit types at or above the threshold.

Read the Sunset Bay 2 Golden Visa Guide
Sunset Bay 2 by Imtiaz in Island A at Dubai Islands escrow account protection concept with shield and padlock icons above a landscaped podium garden and pedestrian area in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 Escrow, Past 70% Certified on Island A

First Abu Dhabi Bank holds Sunset Bay 2 escrow as DLD project 3570 for 66 units, certified 70.2% in August 2026.

Verify the Sunset Bay 2 Escrow Account
Sunset Bay 2 by Imtiaz in Island A at Dubai Islands snagging inspection concept over a furnished kitchen and dining interior with an inspection checklist icon in Dubai - Presented by Tohid Fetrat

Sunset Bay 2 Snagging: 66 Fully Furnished Residences

Sunset Bay 2 is an Imtiaz building on Island A at Dubai Islands: ground, two podium levels, eight floors, a roof.

Book Sunset Bay 2 Snagging

Approaching Handover

Between 70.2% and Handover: What Sunset Bay 2 Buyers Should Do Now

With the RERA report of 4 August 2026 recording the structure as completed, what separates Sunset Bay 2 from 100% is the internal, external and MEP work still progressing, and in a building delivered fully furnished that work ends at a handover with more to check than finishes alone. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.

First, arrange independent snagging so that defects in your residence, supplied furniture included, are documented before you accept it; the Sunset Bay 2 snagging page covers timing around the Q1 2027 handover and what gets inspected.

Second, before the 40% completion payment, confirm the receiving account on the Sunset Bay 2 escrow account page; every dated instalment in the 60/40 plan has fallen due, so this is the largest single transfer still ahead.

Third, if residency is part of the plan, check eligibility before handover in the Sunset Bay 2 Golden Visa guide, since the title deed timing affects which application route applies.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island A Structure

One building's record is only part of the picture; the rest is what is taking shape around it. These three pages set the Sunset Bay 2 build against its island market, its community and its developer:

Aerial masterplan view of Island A properties for sale with waterfront residences, marinas, green spaces, and connected roadways in Dubai. Presented by Tohid Fetrat

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses

Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.

See Island A Properties for Sale
Aerial masterplan view highlighting Island A at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island A Community Overview

Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.

Explore the Island A Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Sunset Bay 2 Construction Updates Frequently Asked Questions

Sunset Bay 2 by Imtiaz, DLD project 3570, is an active project at 70.2% construction progress in the Dubai Land Department register, a reading shown against the inspection report of 4 August 2026. The RERA report of that date records enabling, foundation and structural works as completed, with internal, external and MEP works progressing. The reading was 61 days old when this page was prepared, so a newer one may have been posted since; the dated record is in the inspection timeline above, and the site notes are in the August 2026 construction update for Sunset Bay 2.

Each percentage on this page is a Dubai Land Department register reading for project 3570, listed on Dubai REST under the register name Sunset Bay Two By Imtiaz; the RERA Independent Progress Monitoring Report adds site notes but prints no percentage of its own. A reading becomes a timeline row only when the register gives it a date, which is why 70.2% on 4 August 2026 is the single row, while the earlier 43.2% figure, shown by the register without a date, appears on the track as a dot.

The two dates answer different questions. 20-02-2027 is the registered completion date in the DLD record for project 3570, while Q1 2027 is the handover timing for Sunset Bay 2 buyers; the registered date falls inside that quarter and had not passed when this page was prepared, with 70.2% recorded on 4 August 2026. Actual handover is confirmed by Imtiaz Developments as final inspections complete, and this page's record is updated when the closing inspection is recorded.

Averaged over the whole build, Sunset Bay 2 gained 70.2 points in the 530 days from the recorded start of 20-02-2025 to the 4 August 2026 reading, about 3.97 points per month. Reaching 100% by the registered completion date of 20-02-2027 needs the remaining 29.8 points over 200 days, about 4.47 points per month. Both figures are arithmetic, not a forecast, and no measured pace exists yet because only one reading carries a date; the working is in the pace analysis above.

G+2P+8+R is the building description in the RERA report of 4 August 2026: a ground floor, two podium levels, eight residential floors and a roof level, all in one residential building. The developer's floor plans place the 3 bedroom duplexes at the base, the club house and gym on the second podium floor, the 1 and 2 bedroom apartments on residential floors 1 to 8 and the rooftop pool on the roof level; the same report records the structural works for that configuration as completed.

Sunset Bay 2 by Imtiaz will deliver 66 residences, the same total as the DLD register entry for project 3570, across 1 Bedroom Apartments, 2 Bedroom Apartments and 3 Bedroom Duplexes, all fully furnished with bespoke interiors per the developer. With 70.2% recorded on 4 August 2026, handover of those 66 homes is set for Q1 2027; layouts and prices are covered in the Sunset Bay 2 by Imtiaz project guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sunset Bay 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status