Imtiaz · Island A, Dubai Islands
Sunset Bay 4 Construction Updates
The Register Record of One G+2P+8+R Building on Island A
Sunset Bay 4 by Imtiaz read 53% on the DLD register on 29 September 2026, past halfway about sixteen months after its 15 May 2025 start.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Sunset Bay 4 at a Glance
Sunset Bay 4 by Imtiaz is a single 63-residence building on Island A at Dubai Islands, entered in the Dubai Land Department register as project 3714, with construction recorded as started on 15 May 2025 and registration dated 27 May 2025. Its latest register reading is 53% on 29 September 2026, against a handover expected in Q2 2027. Because the whole project is one G+2P+8+R structure (a ground floor, two podium parking levels, eight residential floors and a roof level), every reading on this page measures one frame rather than an average across several buildings.
3714
Active
15 May 2025
63 residences
7,492.15 sq m
15 May 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Sunset Bay 4 Construction Update Timeline
The Sunset Bay 4 record holds one dated register reading so far: 53% on the inspection report dated 29 September 2026, the first reading this site has published for project 3714. The register also lists 37.22% as the previous inspection but prints no date beside it, so that figure sits on the track below as an undated marker with no table row of its own. The table row links the September 2026 update, which sets out the RERA report notes that accompany the 53% figure.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 53% | 29 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Sunset Bay 4 Has Been Built
With one dated register reading on file, the pace of Sunset Bay 4 is read from two pieces of arithmetic rather than a measured curve between inspections:
- 15 May 2025 to 29 Sep 2026: whole-build average up to 53%About 3.17 points per month
- 29 Sep 2026 to 15 May 2027: 53% to 100% by the registered completion dateAbout 6.18 points per month needed
Those two figures read the same record from opposite ends, and both are arithmetic, not a forecast. The first spreads 53 points across the 502 days since the 15 May 2025 start, a span in which, per the RERA report of 29 September 2026, enabling and foundation works reached completion and the G+2P+8+R frame reached an advanced stage. The second is what the remaining 47 points would need over the 228 days to the 15 May 2027 registered completion date, close to double the average so far. The same report already shows internal works, finishes, the external envelope and MEP running alongside the frame of this one building, which is why the next dated reading, not the long average, is the useful test. Until it posts, the 37.22% figure stays undated and no measured pace is drawn from it; for an end user planning a Q2 2027 move or an investor judging delivery consistency, that next reading is the figure to watch.
Get the Next Inspection Figure First
Tell me you are tracking Sunset Bay 4 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Sunset Bay 4 at Island A
The 53% reading of 29 September 2026 only means something next to what is being delivered. The project guide covers the building this record tracks toward its Q2 2027 handover:

Sunset Bay 4: An Eight-Floor Imtiaz Building on Island A
Sunset Bay 4 by Imtiaz holds 63 fully furnished one, two and three bedroom apartments over eight floors at Dubai Islands.
View the Sunset Bay 4 Project GuideConsidering a Mid-Construction Entry?
Limited units remain available at Sunset Bay 4, and the open mix shifts as the building moves from its frame toward the Q2 2027 handover. If the register record on this page is what brought you here, ask me what is open now, before the 15 December 2026 instalment date.
Ask About Remaining Availability on WhatsAppStage Record
Sunset Bay 4 Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates the Sunset Bay 4 record actually supplies, the 15 May 2025 start, the 27 May 2025 registration and the 29 September 2026 report at 53%, so a stage without its own dated reading says so instead of borrowing one.
Site Activation and Enabling Works
Construction is recorded as started on 15 May 2025, with DLD registration following on 27 May 2025; the RERA report of 29 September 2026 lists the enabling works as completed.
Foundations for the Single Building
Foundation works for the one residential building are recorded as completed in the 29 September 2026 report; the register gives no separate date for that milestone.
The G+2P+8+R Structure
Ground, two podium parking levels, eight residential floors and the roof level: structure works stood at an advanced stage, not yet completed, in the RERA report of 29 September 2026, when the register read 53%.
Envelope, MEP, and Interior Works
Internal works, internal finishes, the external envelope and MEP were all recorded as ongoing on 29 September 2026, overlapping the frame rather than waiting for it to finish.
Rooftop, Amenities, and Handover
Still ahead after the 29 September 2026 reading: the rooftop infinity pool deck, the clubhouse and gym on the second podium floor, furnishing of the 63 residences, and the 47 points left before handover expected in Q2 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sunset Bay 4's own record.
Buyer Position
Tracking Your Position at Sunset Bay 4
This page is one of four project resources that together cover a Sunset Bay 4 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sunset Bay 4 Construction Updates
This page: the DLD register record for Sunset Bay 4, from start to Q2 2027 handover.

Sunset Bay 4 by Imtiaz Golden Visa: Two Types Reach the Line
Sunset Bay 4, Imtiaz's 63 apartments on Island A, qualifies at 2 and 3 bedrooms; the 1 bedroom apartments do not.
Read the Sunset Bay 4 Golden Visa Guide
Sunset Bay 4: Imtiaz's Fourth Sunset Bay Escrow Record
Sunset Bay 4 pays First Abu Dhabi Bank escrow under DLD project 3714, 63 units, 53% certified at September 2026's inspection.
Verify the Sunset Bay 4 Escrow AccountApproaching Handover
Between 53% and Handover: What Sunset Bay 4 Buyers Should Do Now
Payments at Sunset Bay 4 follow dates, not readings: by 29 September 2026 the 60/40 schedule had reached 50% of the price, set against 53% on the register, with a further 10% dated 15 December 2026 and 40% due on completion. That next date, rather than the next reading, sets the clock for buyers, so the three steps below belong before 15 December 2026, not after it.
First, confirm that the 15 December 2026 instalment goes to the First Abu Dhabi Bank trust account registered for project 3714; the Sunset Bay 4 escrow account page walks through checking it on Dubai REST.
Second, if residency is part of the plan, settle eligibility early through the Sunset Bay 4 Golden Visa eligibility guide, since only the 2 and 3 bedroom tiers are priced above the AED 2M ≈ USD 545K threshold.
Third, recheck the 40% completion payment, the furnishing and your layout on the Sunset Bay 4 by Imtiaz project guide, so the balance is planned well before the Q2 2027 handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
A build record is only half the picture; the other half is the island filling in around it. These three pages set the Sunset Bay 4 register record against Island A listings, its community plan and its developer:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Sunset Bay 4 Construction Updates Frequently Asked Questions
Sunset Bay 4 by Imtiaz, DLD project 3714 with Active status, read 53% on the Dubai Land Department register on 29 September 2026. The RERA report of the same date places structure works at an advanced stage, not yet completed, after enabling and foundation works; the full record is in the inspection timeline above.
The register reading of 29 September 2026 stands at 53%, which is 15.78 points above the previous inspection figure of 37.22%. That earlier figure carries no date in the DLD record, so the gap cannot be turned into a monthly pace; the RERA notes for the 53% reading are in the Sunset Bay 4 construction update for September 2026.
The DLD register lists 15 May 2027 as the registered completion date for project 3714, a date inside the Q2 2027 window in which Sunset Bay 4 handover is expected. At the 29 September 2026 reading of 53%, that date was 228 days away and had not lapsed; actual handover is confirmed by Imtiaz Developments as final inspections complete, and this page's record is updated as each new reading posts.
Sunset Bay 4 holds 63 residences, the same total the DLD register shows for project 3714, all fully furnished 1, 2 and 3 bedroom apartments. The single building is configured G+2P+8+R: a ground floor, two podium parking levels, eight residential floors and a roof level with the infinity pool, and the building as a whole read 53% on 29 September 2026.
As arithmetic, not a forecast, 53 points over the 502 days from the 15 May 2025 start to the 29 September 2026 reading average about 3.17 points per month. Reaching 100% by the 15 May 2027 registered completion date would need about 6.18 points per month over the remaining 228 days; the working is in the pace analysis above.
Four register dates anchor the Sunset Bay 4 record: construction started on 15 May 2025, DLD registration followed on 27 May 2025, the register read 53% on 29 September 2026, and the registered completion date is 15 May 2027, with handover expected in Q2 2027. Each later dated reading is added as a new row of the timeline table.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sunset Bay 4 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.