The Edge construction update April 2026 by Select Group in Business Bay Dubai featuring luxury tower progress and waterfront skyline views Presented by Tohid Fetrat

Select Group · Business Bay · Construction Update

The Edge Construction Update - April 2026

April 2026 Inspection Confirms The Edge Reaches 88.86% Construction Progress in Business Bay

Facade installation, MEP systems, and interior finishing now dominate site activity at The Edge, verified at 88.86 percent in the April 2026 RERA inspection cycle.

Direct advisor access. Every message answered personally, never by a call center.

88.86%Construction Progress
23 April 2026Inspection Date
11 October 2026Expected Completion
2611DLD Project Number

Verified DLD Inspection Data

The Edge Construction Snapshot

An 11.84 point rise since June 2025 places The Edge firmly in the finishing band, the stage where inspection data matters most for payment and handover decisions.

Project Name

The Edge by Select Group

Project Number

2611

Project Status

Active

Construction Progress

88.86%

Inspection Date

23 April 2026

Construction Start

09 June 2023

Total Units

1,030 residential units

Total Built Area

65,564.27 sq m

Expected Completion

11 October 2026

Data source: RERA inspection conducted on 23 April 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.

This Inspection Cycle

The Edge Construction Progress Summary

Between the June 2025 and April 2026 inspections, The Edge moved from 77.02% to 88.86%, an 11.84 point gain concentrated in the exterior envelope and interior fit out of both Business Bay towers. At this pace of recorded progress, site activity has shifted from building the towers to completing them.

Completed
  • Enabling and foundation works across the full plot
  • Structural works on both residential towers
  • Podium superstructure connecting the two towers
In Progress at 88.86%
  • Facade installation across tower and podium levels
  • MEP systems: mechanical, electrical, and plumbing fit out
  • Interior finishes across the 1,030 residential units
  • External works around the canal facing plot
Ahead of Handover
  • Remaining RERA inspection cycles toward 100%
  • Building completion certificate procedures
  • Handover from the expected completion date of 11 October 2026
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion target11 October 2026 per the current DLD record, roughly six months from this inspection date.
Remaining distance11.14 percentage points separate the April 2026 reading from handover readiness.

Payment Linked Progress

What 88.86% Progress Means for Edge Buyers

Most Dubai off plan payment plans tie installments to construction milestones or to handover itself, so a verified reading of 88.86% is not just a status update: it signals which obligations and protections apply next. At this stage of The Edge, four actions matter most.

Before Remaining Installments

Verify the escrow account

Any payment still ahead of handover should go only to the DLD regulated escrow account registered for project 2611. The Edge escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines completion linked installments and the handover notice period, and map those clauses against the 11 October 2026 completion date. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Window Open Now

Book the snagging window

At 88.86% and inside nine months of expected handover, The Edge is in the standard booking window for a pre handover inspection. The Edge snagging inspection guide covers the booking window before acceptance.

Every Cycle

Track the remaining cycles

One or two inspection readings typically remain before completion certification. The Edge construction updates hub keeps the final stretch free of surprises.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 88.86%?

Entering a project this close to completion trades payment-plan runway for certainty: the structure is verified, the delivery window is short, and the remaining choice is between the units still available. Every payment goes to the DLD-registered escrow account for project 2611, released against certified construction progress.

Entering Now at 88.86%
  • Certified structure: the inspection record above is the risk picture
  • Roughly six months to the expected handover date
  • 70% of the 30/70 plan due at completion, not spread over years
Typical Launch Entry
  • Construction risk carried from excavation to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 1.25M ≈ USD 340KStarting Price
30/70 Plan70% Due on Completion
From 11 October 2026Expected Handover
Ask What Is Available at The Edge

12 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

The Edge Project Details

The Edge by Select Group residential towers with Burj Khalifa skyline view in Dubai - Presented by Tohid Fetrat
Business Bay · Select Group

With structural works complete across both towers, The Edge is now a finishing stage development of 1,030 contemporary 1 and 2 bedroom apartments on the Business Bay canal front. Starting prices: AED 1.25M ≈ USD 340K.

For buyers entering at this stage, the trade off is shorter waiting time against a later position in the payment plan, with handover expected from 11 October 2026 per the current DLD record.

The Edge by Select Group Project Guide

Site Context This Cycle

Explore The Edge Location on Dubai Map

The Edge rises on a canal facing plot in Business Bay, its two towers oriented toward the Downtown Dubai skyline, which shapes how finishing works are sequenced: facade and external packages on the exposed canal frontage are among the most visible items in the current inspection cycle.

Because Business Bay is an established district with completed roads, canal promenade, and utility infrastructure, The Edge is finishing into a functioning neighborhood rather than an emerging one, which matters for buyers weighing immediate occupancy or rental plans against the October 2026 completion target. See the project's position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view The Edge by Select Group on Dubai Map

Buyer Resources for This Project

Investing in The Edge During Final Construction Progress

The finishing band is where residency planning, payment protection, and handover preparation converge. Each resource below is matched to where The Edge stands right now.

The Edge by Select Group construction update May 2026 showing tower progress in Business Bay Dubai Captured by Tohid Fetrat
You Are Here

The Edge Construction Updates

This page: the verified April 2026 inspection record for The Edge, from enabling works to handover.

The Edge by Select Group Golden Visa opportunity in Business Bay Dubai with luxury residential tower and UAE Golden Visa card Presented by Tohid Fetrat

The Edge Golden Visa

Check whether a qualifying Edge purchase still supports 10-year UAE Golden Visa residency eligibility.

Read The Edge Golden Visa Guide
The Edge by Select Group escrow account security in Business Bay Dubai with protection shield and secure property investment concept Presented by Tohid Fetrat

The Edge Escrow Account

Confirm the DLD-registered escrow account for project 2611 before releasing installments ahead of handover.

Verify The Edge Escrow Account
The Edge by Select Group twin residential towers with Burj Khalifa view in Dubai - Presented by Tohid Fetrat

The Edge Snagging Inspection

At 88.86% recorded progress, arrange independent defect documentation before you accept your Edge residence.

Book The Edge Snagging

Update Timeline

Other The Edge Construction Updates

Follow the full inspection history to see how The Edge has moved through each construction phase, reading by reading.

All The Edge Construction Updates

FAQs

The Edge Construction Progress in April 2026: Frequently Asked Questions

As of the RERA inspection conducted on 23 April 2026, The Edge stands at 88.86% construction progress in the DLD project register.

The Edge moved from 77.02% recorded in June 2025 to 88.86% on 23 April 2026, a gain of 11.84 points concentrated in facade installation, MEP fit out, and interior finishes across both Business Bay towers.

The April 2026 record shows no slippage: expected completion remains 11 October 2026 in the DLD register as of this update, with 11.14 percentage points between the 23 April 2026 reading and full certification, roughly six months before the registered date. How inspection cycles and completion certification work is covered on The Edge construction updates hub.

Yes. Expected completion dates in the DLD project register can be revised between inspection cycles. The date shown here reflects the record as of April 2026; any revision would appear in a later update on this cluster.

With structural works complete on both towers as of the 23 April 2026 inspection, site activity centers on facade installation across tower and podium levels, mechanical, electrical, and plumbing fit out, interior finishes across the 1,030 residential units, and external works on the canal facing plot.

Yes, the window is open now. The practical booking window opens once a project passes roughly 70% or comes within nine months of expected handover, and as of the April 2026 reading The Edge meets both conditions, so arranging the inspection ahead of the handover notice avoids compressed timelines later.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for The Edge correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts