The Mural Construction Update - May 2026

May 2026 Inspection Records The Mural at 8.2% Construction Progress in Dubai Maritime City

Enabling, piling, and foundation works dominate site activity at The Mural, recorded at 8.2 percent in the RERA inspection carried out on 07 May 2026.

Direct advisor access. Every message answered personally, never by a call center.

8.2%Construction Progress
07 May 2026Inspection Date
Q4 2028Expected Completion
3650DLD Project Number

Verified DLD Inspection Data

The Mural Construction Snapshot

A 1.77 point gain over the previous recorded reading puts The Mural at 8.2%, deep inside the groundworks band, where the questions that decide a buyer's outcome are about payment protection rather than build quality.

Project Name

The Mural by Beyond

Project Number

3650

Project Status

Active

Construction Progress

8.2%

Inspection Date

07 May 2026

Construction Start

10 October 2025

Total Units

268 residences

Total Built Area

Expected Completion

Q4 2028

Data source: RERA inspection conducted on 07 May 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

The Mural Construction Progress Summary

The 07 May 2026 reading of 8.2% sits 1.77 points above the 6.43% previously recorded, and every certified point so far belongs to work below ground: enabling, piling, and foundations on plot 530. The register attaches no date to that earlier figure, so the gain is best read as the pace of substructure formation rather than as a monthly rate.

Completed
  • Project registration recorded on 11 April 2025
  • Escrow trust account opened with Commercial Bank of Dubai
  • Construction start logged on 10 October 2025
In Progress at 8.2%
  • Enabling works across the plot 530 site
  • Piling to carry the 36 level tower
  • Foundation works beneath the future podium
  • Main contract logged as progressing in the May 2026 report
Ahead of Handover
  • Basement, lower ground, ground, and two podium levels
  • 32 residential floors with the amenities terrace and sky amenities
  • Facade, services, and interior fit out across 268 residences
  • Remaining RERA cycles up to the Q4 2028 window
Next inspectionThe DLD register publishes the following reading once RERA returns to plot 530; every cycle is filed here as it lands.
Completion targetQ4 2028, the anticipated handover window carried on the developer payment schedule, roughly two and a half years beyond this inspection.
Remaining distance91.8 percentage points separate the 07 May 2026 reading from handover readiness.

Payment Linked Progress

What 8.2% Progress Means for The Mural Buyers

At this depth in the build, almost the entire purchase price is still ahead of you, and the certified record is what stands between your installments and an unbuilt tower. Four actions carry the most weight at The Mural right now.

Before Every Installment

Verify the escrow account

Every payment ahead of handover belongs in the DLD regulated escrow account registered for project 3650, held with Commercial Bank of Dubai. Anything you release while the tower is still below ground belongs there, and The Mural escrow account verification shows how to confirm it: the lookup itself takes about two minutes against the official DLD project record.

Before the 01 August 2026 Date

Map your SPA to the installment calendar

The 50/50 plan runs on fixed calendar dates rather than construction milestones, so your exposure depends on when you signed. Not sure which dates you still face? Send me your SPA schedule and I will mark which dates fall before the tower goes vertical.

Within Days of Booking

Confirm your Oqood registration

Oqood is the interim registration that records an off plan unit against your name at the Dubai Land Department. At this stage of The Mural it is the document that proves what you bought, so confirm the certificate exists and the unit details on it match your SPA.

Every Cycle

Track the vertical milestone

The reading that matters next is the one showing progress above the podium, since substructure work absorbs points slowly. The Mural construction updates hub records each cycle as it is certified.

General framework, not legal advice: milestone definitions, payment dates, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 8.2%?

Entering while the foundations are still being formed trades certainty for runway: the tower is unproven on site, but the payment schedule and the choice of unit are both still wide open. Every payment goes to the DLD-registered escrow account for project 3650, released against certified construction progress.

Entering Now at 8.2%
  • The full 50/50 plan still ahead, with half the price held to completion
  • Five dated construction installments from 01 August 2026 to 01 March 2028
  • Floor, orientation, and layout still open across 268 residences
Typical Late Stage Entry
  • Structure already certified, so less construction risk to carry
  • Most of the purchase price payable within months of signing
  • Selection limited to whatever remains unsold near handover
AED 2.90M ≈ USD 790KStarting Price
50/50 Plan50% Due on Completion
From Q4 2028Expected Handover

The project page lists limited availability as of this update; availability shifts between cycles.

About the Development

The Mural Project Details

The Mural by Beyond Developments in Dubai Maritime City penthouse terrace and glazed facade overlooking the sea at sunset in Dubai - Presented by Tohid Fetrat
Dubai Maritime City · Beyond Developments

With the substructure still being formed, The Mural is a groundworks stage development of 268 residences over 36 levels, running from one bedroom apartments to a single level 35 penthouse. Starting prices: AED 2.90M ≈ USD 790K.

For buyers entering here, the trade off is the longest wait against the lightest committed capital, with half the price held back until the Q4 2028 handover window.

Site Context This Cycle

Explore The Mural Location on Dubai Map

The Mural is being built on plot 530 in Madinat Dubai Almelaheyah, the seaward edge of the Dubai Maritime City peninsula, with the district's landscaped spine behind the site and open water in front of it. That position explains why this cycle reads entirely as piling and foundations: a 36 level tower on made ground carries its hardest engineering below the surface, and the May 2026 inspection captured the site in exactly that phase.

The peninsula itself is still filling in around the plot, so The Mural is being delivered into a district that matures on roughly the same timetable as the tower rather than one already complete, which is the honest frame for anyone weighing rental or occupancy plans against the Q4 2028 window. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in The Mural During Early Construction Progress

The groundworks band is where payment protection and residency planning do the real work, long before finishes matter. Each resource below is matched to where The Mural stands right now.

The Mural by Beyond Developments in Dubai Maritime City construction updates cover image featuring a project rendering of the curved residential tower framed by palm trees in Dubai - Presented by Tohid Fetrat
You Are Here

The Mural Construction Updates

This page: the verified May 2026 inspection record for The Mural, from enabling works onward.

The Mural by Beyond Developments in Dubai Maritime City Golden Visa graphic with a gold card over an aerial project rendering beside the waterfront in Dubai - Presented by Tohid Fetrat

The Mural by Beyond in Dubai Maritime City Golden Visa, Any Level

Every tier at The Mural by Beyond in Dubai Maritime City, from 1 bedroom to 4 bedroom penthouse, qualifies individually.

Read The Mural Golden Visa Guide
The Mural by Beyond Developments in Dubai Maritime City escrow account protection graphic with shield and padlock icons above a landscaped residential terrace in Dubai - Presented by Tohid Fetrat

The Mural by Beyond in Dubai Maritime City: Escrow Record

The Mural by Beyond in Dubai Maritime City, DLD project 3650, banks with Commercial Bank of Dubai, 8.2% certified May 2026.

Verify The Mural Escrow Account

Update Timeline

Other The Mural Construction Updates

This is the first inspection record published for The Mural on this site. Every cycle that follows is filed on the hub below, reading by reading.

All UpdatesThe Mural Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All The Mural Construction Updates

FAQs

The Mural Construction Progress in May 2026: Frequently Asked Questions

The RERA inspection carried out on 07 May 2026 records The Mural at 8.2% construction progress in the DLD project register, with the main contract logged as progressing.

The register shows 6.43% at the previous reading and 8.2% on 07 May 2026, a gain of 1.77 points. No date is attached to that earlier figure in the register, so the interval the gain covers cannot be stated precisely, and this page shows only the dated 07 May 2026 reading on its progress track.

The 07 May 2026 report records enabling, piling, and foundation works ongoing on plot 530 in Madinat Dubai Almelaheyah. Nothing above ground was certified at that reading: the basement, lower ground, ground, two podium levels, and 32 residential floors all sit ahead of the project.

At the 07 May 2026 reading the project is listed as active with 91.8 percentage points still to certify, and the anticipated handover window remains Q4 2028. Substructure cycles like this one carry little schedule signal on their own, so the readings through late 2026 are the ones that will show whether the vertical programme is holding. Each cycle is added to The Mural construction updates hub.

On the published 50/50 schedule the third installment fell on 01 April 2026, just before this inspection, and the fourth falls on 01 August 2026. Five dated construction installments run from that date through to 01 March 2028, with the remaining 50% due on completion. Your own dates depend on your booking date and your signed SPA.

Yes. Completion timing recorded against a project in the DLD register can be revised between inspection cycles, and at 8.2% recorded progress The Mural is early enough that any revision would most likely surface once the tower starts rising. The window shown here reflects the position as of the May 2026 cycle.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for The Mural by Beyond in Dubai Maritime City correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts