
Beyond Developments · Dubai Maritime City
The Mural by Beyond in Dubai Maritime City Construction Updates
The Certified Record of a Seafront Tower Rising on Plot 530
The Mural recorded 8.2% construction progress at its 07 May 2026 RERA inspection, the certified record so far covering piling and foundations on plot 530.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
The Mural by Beyond in Dubai Maritime City at a Glance
The Mural is Beyond Developments' 268-residence tower on plot 530, registered with the Dubai Land Department as project 3650 and under construction since 10 October 2025. Just under seven months separate that start from the 8.2% carried at the May 2026 inspection, and every certified point in between belongs to work at or below ground level. For a 36-level tower on the outer rim of a peninsula that is still being built around it, a first file weighted entirely toward substructure is the expected shape rather than a warning inside it.
3650
Active
10 October 2025
268 residences
Q4 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
The Mural by Beyond in Dubai Maritime City Construction Update Timeline
One dated inspection anchors this record: 07 May 2026, at 8.2%. The register also holds 6.43% as the preceding figure but publishes no date against it, so that number stays off the track and out of the table below and appears here only as context for how the substructure has accumulated. What the visual therefore shows is a single certified point standing 91.8 percentage points short of completion, and each new cycle is added to it as RERA returns to plot 530.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 8.2% | 07 May 2026 | View the May 2026 update |
Pace Analysis
How Fast The Mural by Beyond in Dubai Maritime City Has Been Built
With one dated reading on file, pace at The Mural is a derived figure rather than a velocity measured between two inspections. Two calculations frame where the project stands:
- Oct 2025 start to May 2026 inspection: 0% to 8.2%, substructureAbout 1.2 points per month, derived
- May 2026 to the Q4 2028 window: 91.8 points still to certifyAbout 3 points per month, schedule-implied
The distance between those two numbers is the whole character of this stage. Substructure consumes months and capital while returning very little to the percentage, because piling and foundations on a reclaimed seafront plot are measured in volume placed below the surface rather than in visible floors. The required rate roughly triples once the tower begins rising, and that is normal arithmetic rather than a red flag: a repeating floor plate is the fastest thing any contractor builds. For an investor weighing runway and for an end user counting toward Q4 2028, the reading that carries real information is not this one but the first cycle certifying work above the podium, where a derived average finally becomes a measurable trend.
Get the Next Inspection Figure First
Tell me you are tracking The Mural by Beyond in Dubai Maritime City and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About The Mural by Beyond in Dubai Maritime City at Maritime City
A percentage only means something beside the thing it is counting up to. That side of The Mural is set out in the project guide:

The Mural by Beyond in Dubai Maritime City: Sea and Forest Views
The Mural by Beyond in Dubai Maritime City rises 36 levels, its 268 residences looking out to the open sea.
View the The Mural by Beyond in Dubai Maritime City Project GuideConsidering an Early-Stage Entry?
Buying while the record still reads in single digits means the widest choice of floor and aspect inside the tower, and that choice narrows with every certified cycle. Tell me the scale and aspect you have in mind and I will send back what is still unsold before the next reading lands.
Ask About Remaining Availability on WhatsAppStage Record
The Mural by Beyond in Dubai Maritime City Build Stages, Mapped to the Inspections
Each stage below is tied to where it sits in The Mural's own file rather than to a textbook build sequence, so 8.2% reads as a position in the programme rather than as a bare number.
Site Activation on Plot 530
From the 10 October 2025 start date: mobilisation, hoarding and site enabling on plot 530 in Madinat Dubai Almelaheyah, all of it ahead of the first tracked inspection.
Piling and Foundations
At the May 2026 inspection the certified picture was entirely below ground: piles going in to carry the tower, foundation activity beneath the future podium, and enabling still running. The main contract carried a progressing status.
Basement, Ground and Podium
The base this tower stands on runs from the basement and lower ground up through the ground floor and a pair of podium levels. Certifying it is what lifts the record out of pure substructure.
32 Residential Floors
The repeating floor plates carrying all 268 residences, plus the amenities terrace and the sky amenities levels. This is the band where recorded percentages typically move fastest.
Facade, Fit-Out and Delivery
Envelope, building services, interior fit-out across the tower, and the closing inspections that carry The Mural into its anticipated Q4 2028 handover window.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Mural by Beyond in Dubai Maritime City's own record.
Buyer Position
Tracking Your Position at The Mural by Beyond in Dubai Maritime City
This page is one of four project resources that together cover a The Mural by Beyond in Dubai Maritime City purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Mural by Beyond in Dubai Maritime City Construction Updates
This page: the certified inspection record for The Mural, from its October 2025 construction start onward.

The Mural by Beyond in Dubai Maritime City Golden Visa, Any Level
Every tier at The Mural by Beyond in Dubai Maritime City, from 1 bedroom to 4 bedroom penthouse, qualifies individually.
Read the The Mural by Beyond in Dubai Maritime City Golden Visa Guide
The Mural by Beyond in Dubai Maritime City: Escrow Record
The Mural by Beyond in Dubai Maritime City, DLD project 3650, banks with Commercial Bank of Dubai, 8.2% certified May 2026.
Verify the The Mural by Beyond in Dubai Maritime City Escrow AccountApproaching Handover
Between 8.2% and Handover: What The Mural by Beyond in Dubai Maritime City Buyers Should Do Now
An early record puts a buyer in an unusual position: the tower is barely out of the ground, yet most of the money and most of the decisions are still ahead. Substructure cycles also move the percentage slowly, so waiting for a dramatic reading before organising anything wastes the one window where these three items are easy to settle.
First, treat the escrow record as the check you run before releasing any installment; the escrow account page for project 3650 sets out the registered trust account and how to verify it against the DLD record in a couple of minutes.
Second, read your own payment dates against this record rather than against the site. Installments here fall on fixed calendar dates, so a slow substructure cycle postpones nothing you owe, and knowing which dates sit before the tower goes vertical changes how you plan the funds.
Third, if residency forms part of the reason for buying, settle eligibility early through the residency guide written for this project, because the application path turns on title timing at completion rather than on the booking date.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Maritime City Structure
A percentage measures the tower and says nothing about the district being assembled around it. These three pages put The Mural's progress inside its peninsula, community and developer context:

Dubai Maritime City: Waterfront Apartments and Branded Residences on the Northern Coastline
Dubai Maritime City lists 7 projects of waterfront apartments and branded residences in DP World's district, freehold for all nationalities.
See Maritime City Properties for Sale
Maritime City Community Overview
Read the Dubai Maritime City guide: a waterfront district between Port Rashid and Dubai Drydocks with high-rise coastal living.
Explore the Maritime City Community
Beyond Developments: Omniyat's Design DNA on the Dubai Maritime City Waterfront
Beyond brings Omniyat's design DNA to waterfront communities in Dubai Maritime City and Palm Jumeirah, with every project along the coast.
View the Beyond Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
The Mural by Beyond in Dubai Maritime City Construction Updates Frequently Asked Questions
The Mural by Beyond is an active DLD-registered project (number 3650) in its substructure phase, recorded at 8.2% at the RERA inspection of 07 May 2026, with enabling, piling and foundation works logged as ongoing on plot 530. The dated record sits in the inspection timeline above.
The 07 May 2026 inspection recorded 8.2% construction progress, 1.77 points above the 6.43% carried as the preceding entry. The register publishes no date against that earlier number, so it is not plotted on the progress track. The site report for the dated cycle is published in the May 2026 construction update.
The anticipated handover window for The Mural is Q4 2028. Measured from the 07 May 2026 reading of 8.2%, that leaves 91.8 percentage points to certify across roughly thirty months of remaining programme, and this page records each RERA cycle as it is published.
DLD registration records show 268 residences for project 3650. The RERA record describes the building as 32 floors sitting over two podium levels, a ground floor, a lower ground floor and a basement, which puts all 268 homes inside one 36-level tower rather than spread across phases.
Construction on plot 530 started on 10 October 2025, six months after the project was registered with the Dubai Land Department on 11 April 2025. The first dated inspection in this record, on 07 May 2026, put the tower at 8.2%.
Only one dated reading exists so far, so pace here is derived rather than measured between inspections. Averaged from the 10 October 2025 start to the 8.2% recorded on 07 May 2026, the certified rate works out at roughly 1.2 percentage points per month; holding the Q4 2028 window would require about three points per month from that reading onward. The arithmetic is set out in the pace analysis above.
Everything certified by 07 May 2026 sits at or below ground level: the plot has been enabled, piles are being driven for a 36-level tower, and foundation work is underway beneath the future podium. No structure above ground had been certified at 8.2%, which is why the stage record on this page opens at site activation rather than at frame.
The RERA record places The Mural on plot 530 in Madinat Dubai Almelaheyah, on the outer sea-facing rim of the Dubai Maritime City peninsula. That position is why the tower is planned with water on one aspect and planted parkland on the other, and the layouts and floor bands built around those two views are set out in the The Mural by Beyond project guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Mural by Beyond in Dubai Maritime City construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.