Violet 2 Construction Update - April 2026

April 2026 Inspection Confirms Violet 2 Reaches 45.08% Construction Progress in DAMAC Hills 2

Enabling, structure, MEP, and external envelope works now run in parallel across the Violet 2 townhouse rows, verified at 45.08 percent in April 2026.

Direct advisor access. Every message answered personally, never by a call center.

45.08%Construction Progress
10 April 2026Inspection Date
Q1 2027Expected Handover
3199DLD Project Number

Verified DLD Inspection Data

Violet 2 Construction Snapshot

A 28.31 point rise since the previous recorded inspection puts Violet 2 just under the halfway mark, in the band where progress stops being something you can read from the street and starts being measured inside the shells.

Project Name

Violet 2 at DAMAC Hills 2

Project Number

3199

Project Status

Active

Construction Progress

45.08%

Inspection Date

10 April 2026

Construction Start

18 October 2024

Total Units

223 townhouses

Total Built Area

Expected Completion

Q1 2027

Data source: RERA inspection conducted on 10 April 2026, tracked against DLD inspection records for project 3199. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Violet 2 Construction Progress Summary

Between the previous recorded reading and the 10 April 2026 inspection, Violet 2 moved from 16.77% to 45.08% across its 223 townhouses, a gain of 28.31 points. The register carries no date against that earlier reading, so the pace behind the gain is not something the record supports stating. What the April file does establish is that four separate work packages are now running concurrently rather than one after another.

Completed
  • Construction start registered on 18 October 2024
  • Escrow account opened with Dubai Islamic Bank for project 3199
  • Two audited RERA readings on record, the latest 10 April 2026
In Progress at 45.08%
  • Enabling, foundation, and structure works at advanced stages
  • Internal and MEP works progressing across the townhouse rows
  • External envelope and finishes works at differing stages by row
  • Infrastructure works progressing across the Madinat Hind 4 site
Ahead of Handover
  • The RERA readings still standing between 45.08% and 100%
  • Completion certificate procedures once the works are certified
  • Handover from the expected window of Q1 2027
Next inspectionThe register receives its next reading after RERA's following site visit, and this page carries that reading in the same cycle.
Completion targetQ1 2027, which is under a year from this inspection date rather than the multi year horizon a launch entry carries.
Remaining distance54.92 percentage points remain to full certification, and almost all of that scope is internal rather than structural.

Payment Linked Progress

What 45.08% Progress Means for Violet 2 Buyers

Off plan installments in Dubai are released against certified construction stages rather than against dates in a calendar, which makes a verified reading of 45.08% a scheduling document as much as a progress figure. Four actions follow from where Violet 2 sits today.

Before Your Next Installment

Verify the escrow account

Every installment still owing on a Violet 2 townhouse belongs in the DLD regulated escrow account registered to project 3199, which the inspection file names as held with Dubai Islamic Bank. Violet 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Milestone Tranche

Read your SPA against the certified stages

Your agreement, not a sales floor summary, decides which tranche the 45.08% reading triggers and how much notice reaches you before the Q1 2027 window opens. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

At Mid Construction

Confirm your Oqood interim registration

Your purchase should be recorded in the DLD interim property register through Oqood, which registers your interest in the townhouse while it is still being built. Confirm the entry exists and that the unit reference on it matches the one written into your agreement.

Every Cycle

Track the remaining cycles

Several inspection readings still separate 45.08% from completion certification. The Violet 2 construction updates hub keeps the second half of the build free of surprises.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 45.08%?

Entering a townhouse cluster at the midpoint buys a different thing than entering at launch: the structures exist and have been audited, the delivery window is measured in months rather than years, and a meaningful share of the payment schedule already sits behind the project. Every payment goes to the DLD-registered escrow account for project 3199, released against certified construction progress.

Entering Now at 45.08%
  • Structure, MEP, and envelope works already audited to 45.08%
  • Under a year to the Q1 2027 handover window
  • Early construction tranches of the 70/30 plan already behind the project
Typical Launch Entry
  • Construction risk carried from excavation to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 1.87M ≈ USD 509KStarting Price
70/30 Plan30% Due on Completion
From Q1 2027Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Violet 2 Project Details

Violet 2 by DAMAC in DAMAC Hills 2 modern villa exterior at dusk with landscaped flowering gardens driveway and parked cars in Dubai - Presented by Tohid Fetrat
DAMAC Hills 2 · DAMAC Properties

With structure, envelope, and internal packages running at once, Violet 2 is a mid construction release of 223 four bedroom townhouses on the DAMAC Hills 2 side that faces Water Town. Starting prices: AED 1.87M ≈ USD 509K.

Both prototypes, TH12-4M and TH12-4E, are delivered over ground, first, and roof floors at roughly 2,352 to 2,415 sq ft, so for buyers entering now the choice is less about layout than about which row reaches finishing first ahead of Q1 2027.

Site Context This Cycle

Explore Violet 2 Location on Dubai Map

Violet 2 occupies plot 18187 in Madinat Hind 4, laid out as long townhouse rows rather than a single building, and that geometry is exactly why the April 2026 record reads the way it does: structure, envelope, and finishes are recorded at different stages simultaneously, because the rows were never going to advance in step with one another.

Because DAMAC Hills 2 already operates its three amenity districts while residential terraces continue to be delivered around them, Violet 2 is finishing into a community with a working lagoon, sports facilities, and retail rather than an empty masterplan, which matters for anyone weighing occupancy or rental plans against the Q1 2027 window. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Violet 2 at 45.08% Construction Progress

The middle of a build is where payment protection and residency planning are actually decided, because both are settled long before the handover notice arrives. Each resource below is matched to where Violet 2 stands right now.

Violet 2 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with a landscaped garden and pool in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 2 Construction Updates

This page: Violet 2 read against the 10 April 2026 RERA inspection, reading by reading.

Violet 2 by DAMAC in DAMAC Hills 2 Golden Visa card graphic above a balcony overlooking landscaped villas and community grounds in Dubai - Presented by Tohid Fetrat

Violet 2 at DAMAC Hills 2 Golden Visa: Every TH12-4E Clears Alone

Violet 2 at DAMAC Hills 2: every TH12-4E end townhouse qualifies, a middle townhouse only at the top of its range.

Read the Violet 2 Golden Visa Guide
Violet 2 by DAMAC in DAMAC Hills 2 escrow account concept with shield and padlock icons above a modern villa exterior and landscaped garden in Dubai - Presented by Tohid Fetrat

Violet 2 at DAMAC Hills 2 Escrow: DAMAC's Townhouse Payments on Record

Violet 2 at DAMAC Hills 2 pays Dubai Islamic Bank escrow as DLD project 3199, 223 units certified 45.08% April 2026.

Verify the Violet 2 Escrow Account

Update Timeline

Other Violet 2 Construction Updates

April 2026 is the first published reading for Violet 2. Every cycle from here is added to the same timeline, so the full inspection history stays in one place.

All UpdatesViolet 2 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Violet 2 Construction Updates

FAQs

Violet 2 Construction Progress in April 2026: Frequently Asked Questions

The DLD project register records Violet 2 at 45.08% construction progress under project number 3199, audited at the RERA site inspection of 10 April 2026.

Violet 2 moved from 16.77% at the previous recorded inspection to 45.08% on 10 April 2026, a gain of 28.31 points. The DLD register carries no date against that earlier reading, so the time elapsed behind the gain cannot be stated from the record itself.

Not yet. The 10 April 2026 reading of 45.08% sits just under the halfway mark and leaves 54.92 percentage points to full certification. The second half of a townhouse program carries the internal, MEP, and finishing scope, so from here the reading rises against work happening inside the shells rather than against new structures appearing on the plot.

The April 2026 record shows no revision to the schedule: handover remains set for Q1 2027 as of this update, with 54.92 percentage points between the 10 April 2026 reading and full certification. The mechanics of inspection cycles and completion certification are set out on the Violet 2 construction updates hub.

Yes. A registered completion date is a schedule entry rather than a guarantee, and RERA can record a revision at any cycle. Q1 2027 is what the record supports as of the 10 April 2026 reading, and each subsequent cycle is published here as it lands.

The 10 April 2026 inspection records enabling, foundation, and structure works progressing at advanced stages, with internal, MEP, external envelope, and finishes works progressing at different stages across the 223 townhouses, alongside infrastructure works running on site.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Violet 2 at DAMAC Hills 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts