Violet 2 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with a landscaped garden and pool in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Hills 2

Violet 2 at DAMAC Hills 2 Construction Updates

The Verified Build Record for 223 Townhouses Opposite Water Town

Violet 2 recorded 45.08% construction at its 10 April 2026 RERA inspection, with structure, MEP, and envelope packages now running together across the townhouse rows.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

45.08%Construction Progress
10 April 2026Latest RERA Inspection
223 townhousesTotal Units
Project 3199DLD Registration

Construction Snapshot

Violet 2 at DAMAC Hills 2 at a Glance

Violet 2 is the 223-townhouse follow-on to DAMAC's first Violet cluster, registered as project 3199 and building since 18 October 2024. The April 2026 file puts it at 45.08%, which on a cluster built as rows rather than as one structure means the percentage is now driven by work happening inside the shells. That geometry also explains why a single figure here is an average across packages that are deliberately out of step with one another, not a snapshot of one building rising floor by floor.

DLD Project Number

3199

Project Status

Active

Construction Start

18 October 2024

Total Units

223 townhouses

Total Built-Up Area

Registered Completion Date

Q1 2027

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Violet 2 at DAMAC Hills 2 Construction Update Timeline

The register holds two Violet 2 readings. Only one of the pair carries a date. The audited inspection of 10 April 2026 put the cluster at 45.08%, some 28.31 points above an earlier figure of 16.77% that the register logs without any inspection date attached. That missing date is why the track below plots a single point rather than a climb: an undated reading cannot be placed on a timeline, and it cannot be used to derive a rate.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202645.08%10 April 2026View the April 2026 update
!

Reading the record: the DLD register also carries an earlier Violet 2 figure of 16.77% with no inspection date recorded against it. It is stated here for completeness and then deliberately excluded from the track above, from the table, and from every pace figure on this page. An undated reading cannot support a date-based calculation, and inventing one to fill the gap would put a number on this page that the register does not hold.

Pace Analysis

How Fast Violet 2 at DAMAC Hills 2 Has Been Built

With one dated inspection on file, Violet 2 has no measured velocity between readings yet. What the record does support is two different rates, and it matters which is which:

  • 18 Oct 2024 to 10 Apr 2026: whole-build average across 17.7 months to reach 45.08%About 2.5 points per month, derived
  • 10 Apr 2026 to the close of Q1 2027: rate needed to clear the remaining 54.92 pointsAbout 4.7 points per month, schedule-implied

The distance between those two numbers is the honest state of this page. The derived figure carries the slow enabling and foundation months at the front of the programme, so it understates what the site is capable of today; the schedule-implied figure is simply what the remaining months would have to deliver to land inside the stated window. On a townhouse cluster that gap reads differently than it would on a tower, because the outstanding 54.92 points are fit-out, systems, and finishes repeated across 223 near-identical homes rather than 223 new structures, and repeated work speeds up once the leading rows fix the sequence. It is still the figure to watch. For a buyer holding a construction-linked schedule, the next dated reading is what turns an implied rate into a measured one, and recording that is exactly what this page exists to do.

Get the Next Inspection Figure First

Tell me you are tracking Violet 2 at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Violet 2 at DAMAC Hills 2

A percentage only means something measured against what it is building. The project guide covers what the 45.08% is delivering:

Violet 2 by DAMAC in DAMAC Hills 2 modern villa exterior at dusk with landscaped flowering gardens driveway and parked cars in Dubai - Presented by Tohid Fetrat

Violet 2 at DAMAC Hills 2: The Second TH12 Townhouse Release

Violet 2 at DAMAC Hills 2 is the second Violet release, 223 four bedroom townhouses built to the TH12 prototypes.

View the Violet 2 at DAMAC Hills 2 Project Guide

Considering an Entry at Mid Construction?

Availability across the 223 townhouses shifts between inspection cycles, and in a release this size the end plots are the thinnest part of the list. If the record on this page is what brought you here, ask me what is actually open before the next cycle publishes.

Ask About Remaining Availability on WhatsApp

Stage Record

Violet 2 at DAMAC Hills 2 Build Stages, Mapped to the Inspections

Each stage below is tied to where it actually falls in Violet 2's own register entries rather than to a generic construction sequence, which means the gap in the record shows up as a gap instead of being smoothed over.

Oct 2024 to the first recorded reading

Site Activation and Enabling Works

From the 18 October 2024 registered start: mobilisation, enabling works, and plot preparation across the Violet 2 land within Madinat Hind 4.

Recorded at 16.77%, no date registered

Foundations and Early Structure

The register's earlier Violet 2 figure of 16.77% covers foundations and the first structural work on the rows. No inspection date accompanies it, so it anchors a stage but never a moment.

Current Phase10 Apr 2026 at 45.08%

Structure, MEP, and Envelope in Parallel

The April 2026 file puts the foundation and structure packages at an advanced stage, with internal, MEP, envelope, and finishing crews working at the same time and each row standing at a different point in that sequence.

From 45.08% toward certification

Internal Finishing Across 223 Townhouses

The 54.92 points still outstanding sit almost entirely inside the shells: fit-out, building systems, and finishes repeated across every row until each one is signed off.

Toward the Q1 2027 window

Certification and Handover

Sign-off of the finished works, the completion certificate that follows it, and then handover to buyers from the expected Q1 2027 window.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Violet 2 at DAMAC Hills 2's own record.

Buyer Position

Tracking Your Position at Violet 2 at DAMAC Hills 2

This page is one of four project resources that together cover a Violet 2 at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Violet 2 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of a modern villa with a landscaped garden and pool in Dubai - Presented by Tohid Fetrat
You Are Here

Violet 2 at DAMAC Hills 2 Construction Updates

This page: every recorded Violet 2 percentage, the pace it implies, and what remains outstanding.

Violet 2 by DAMAC in DAMAC Hills 2 Golden Visa card graphic above a balcony overlooking landscaped villas and community grounds in Dubai - Presented by Tohid Fetrat

Violet 2 at DAMAC Hills 2 Golden Visa: Every TH12-4E Clears Alone

Violet 2 at DAMAC Hills 2: every TH12-4E end townhouse qualifies, a middle townhouse only at the top of its range.

Read the Violet 2 at DAMAC Hills 2 Golden Visa Guide
Violet 2 by DAMAC in DAMAC Hills 2 escrow account concept with shield and padlock icons above a modern villa exterior and landscaped garden in Dubai - Presented by Tohid Fetrat

Violet 2 at DAMAC Hills 2 Escrow: DAMAC's Townhouse Payments on Record

Violet 2 at DAMAC Hills 2 pays Dubai Islamic Bank escrow as DLD project 3199, 223 units certified 45.08% April 2026.

Verify the Violet 2 at DAMAC Hills 2 Escrow Account

Approaching Handover

Between 45.08% and Handover: What Violet 2 at DAMAC Hills 2 Buyers Should Do Now

Just under half the certified work now sits behind the project and the Q1 2027 window has moved inside twelve months, which puts a Violet 2 buyer in the part of the schedule where the remaining decisions are administrative rather than structural. Notice windows on construction-linked tranches are short by design, so the three checks below belong in this cycle rather than in the one where a payment request arrives.

First, confirm that each installment still outstanding is routed into the escrow account the DLD holds against project 3199; the Violet 2 escrow account verification page names the account carried in the inspection file and shows the lookup that confirms it.

Second, settle residency eligibility now rather than at handover, since title deed timing shapes which application path is open to you; the Violet 2 Golden Visa eligibility guide covers how the property threshold is read against a townhouse purchase.

Third, read each inspection as it publishes instead of waiting for a handover notice to arrive; the April 2026 Violet 2 inspection record is the first published cycle, and every reading after it lands in the same timeline.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Hills 2 Structure

A build record answers half the question. What already stands and trades around the plot answers the rest, so these three pages set Violet 2's progress against its community, its competition, and its developer:

Community view of DAMAC Hills 2 showcasing properties for sale including villas, townhouses, and apartments in Dubai. Presented by Tohid Fetrat

DAMAC Hills 2 Properties for Sale

Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.

See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 by DAMAC Properties community park with football field tennis courts basketball courts landscaped pathways and residential villas in Dubai - Presented by Tohid Fetrat

DAMAC Hills 2 Community Overview

Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.

Explore the DAMAC Hills 2 Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Violet 2 at DAMAC Hills 2 Construction Updates Frequently Asked Questions

Project 3199 holds an Active status on the DLD register, and its most recent audited reading is 45.08%, taken at the RERA inspection dated 10 April 2026. The whole record sits in the inspection timeline above.

The 10 April 2026 inspection recorded 45.08%, which stands 28.31 points above the earlier register reading of 16.77%. Because no date is filed against that earlier figure, the point gain cannot be converted into a rate. The site report for the cycle is published in the April 2026 construction update.

The DLD register holds the 16.77% figure for project 3199 without an accompanying inspection date. This page states the figure for completeness but keeps it off the progress track, out of the timeline table, and out of every pace calculation, because a reading with no date cannot anchor either a point in time or a velocity.

Across the 17.7 months between the 18 October 2024 construction start and the 10 April 2026 inspection, Violet 2 averaged about 2.5 percentage points per month. That is a derived whole-build average, not a measured rate between two dated readings. Clearing the remaining 54.92 points by the close of the Q1 2027 window would require roughly 4.7 points per month. Both figures are set out in the pace analysis above.

Handover is expected in Q1 2027. At the 10 April 2026 inspection, 54.92 percentage points remained between the recorded reading and full certification, and the record here is refreshed as each further inspection reaches the register.

Construction on project 3199 was registered as starting on 18 October 2024. The first reading published on this site is the 10 April 2026 inspection at 45.08%, which is 539 days after that registered start date.

The release comprises 223 four bedroom townhouses built to two prototypes, TH12-4M and TH12-4E, laid out over ground, first, and roof floors with saleable areas of roughly 2,352 to 2,415 sq ft. Layouts and prototype detail are covered in the Violet 2 at DAMAC Hills 2 project guide.

The inspection file for project 3199 names Dubai Islamic Bank as the escrow account holder. Installments on an off plan townhouse leave that account only after a construction stage has been certified, never on a calendar date alone, a mechanism covered on the Violet 2 escrow account page.

The cluster occupies plot 18187 within Madinat Hind 4, on the side of DAMAC Hills 2 that faces Water Town. Its townhouses are built as long rows that progress independently of one another, which is why a single reading can show structure, envelope, and finishing work at different stages at the same moment.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Violet 2 at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status