Windsor House 2 by Ellington in Dubai South Residential District project rendering used for the August 2026 construction update showing the planned landscaped residential courtyard in Dubai - Presented by Tohid Fetrat

Ellington · Dubai South Residential District · Construction Update

Windsor House 2 Construction Update - August 2026

August 2026 DLD Register Reading Places Windsor House 2 at 0.6% in Dubai South Residential District

RERA found enabling works, piling and foundation progressing at Windsor House 2 on 20 August 2026, the inspection date beside its 0.6 percent DLD register reading.

Direct advisor access. Every message answered personally, never by a call center.

0.6%DLD Register Reading
20 August 2026Inspection Date
Q3 2028Expected Handover
4300DLD Project Number

Verified DLD Inspection Data

Windsor House 2 Construction Snapshot

A 0.6 point move from an undated 0% previous reading places Windsor House 2 in the enabling and foundations band, where the payment plan, not the site, sets most of what a buyer owes next.

Project Name

Windsor House 2 by Ellington

Project Number

4300

Project Status

Active

Construction Progress

0.6%

Inspection Date

20 August 2026

Construction Start

12 February 2026

Total Units

414 Residences

Total Built Area

39,161.66 sq m

Expected Completion

Q3 2028

Data source: the DLD project register reading for project 4300, registered as WINDSOR HOUSE II, recorded on 20 August 2026, read with the RERA Independent Progress Monitoring Report of the same date, which prints no percentage of its own; the building configuration is as described in that report. The main image on this page is a developer rendering of the planned courtyard, not evidence of site works. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Windsor House 2 Construction Progress Summary

The DLD register moved Windsor House 2 from an undated 0% to 0.6% at the 20 August 2026 inspection, about six months after the recorded construction start. The RERA report for that date lists enabling works, piling and foundation as progressing and records nothing as complete, so the basement levels, the podium deck and the ten residential floors of each tower all still lie ahead.

On the Register
  • Registered as DLD project 4300 on 13 February 2026
  • Construction start recorded as 12 February 2026
  • Trust account bank named on the RERA report: Mashreq Bank PSC
In Progress at 0.6%
  • Enabling works on the Dubai South Residential District site
  • Piling, progressing per the 20 August 2026 report
  • Foundation works, progressing per the same report
  • Report progress status: Enabling Works, Progressing
Ahead of Handover
  • Basement, lower ground and upper ground levels (B+LG+UG)
  • Ten residential floors in each of Tower A and Tower B
  • The podium amenity deck between the two towers
  • Handover, expected in Q3 2028
Next inspectionPublished in the DLD project register after the next RERA site visit; no date is announced in advance, and this record adds each new reading.
Expected handoverQ3 2028. Confirm the current construction and handover timetable with the developer in writing.
Registered Completion Date (DLD)31-07-2029, as recorded in the DLD project register at the time of the 20 August 2026 reading.
Remaining distance99.4 percentage points separate the 0.6% reading from 100%.
Pace so farAbout 0.1 points per month (arithmetic over the first six months, not a forecast), counted from the recorded start on 12 February 2026 to the 20 August 2026 reading.

Payment Linked Progress

What 0.6% Progress Means for Windsor House 2 Buyers

Windsor House 2 runs a 70/30 plan that mixes calendar and construction triggers, so a 0.6% reading shows which instalments the site can move and which it cannot. By 20 August 2026 none of the four construction-linked instalments, the first due at 20% construction, had been triggered, while the six reservation-date instalments, 50% of the price, fall due within 360 days of each buyer's own reservation date, independent of construction progress. At this stage, four actions matter most.

Before Every Instalment

Verify the escrow account

Reservation-date instalments keep falling due while the site is at its enabling, piling and foundation stage, so every transfer should go only to the DLD regulated escrow account for project 4300 held with Mashreq. Windsor House 2 escrow account verification sets out the check; the lookup itself takes about two minutes against the official DLD project record.

Before the 20% Construction Milestone

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines the instalments linked to 20%, 30%, 40% and 50% construction and the payment on completion, and map those clauses against the Q3 2028 expected handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Reservation

Confirm your Oqood registration

Off-plan units are recorded with the Dubai Land Department through Oqood, the interim register that comes before a title deed. While Windsor House 2 is still at enabling and foundation stage, confirm that your unit appears in Oqood under your name and that its details match your SPA.

Every Cycle

Track the readings toward 20%

The first construction-linked instalment falls due at 20% construction, so each register reading between 0.6% and 20% shows how close it is. Windsor House 2 construction updates records every dated reading as it publishes.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0.6%?

Entering at the enabling and foundation stage trades a longer wait for a longer runway: you choose from plans across Tower A and Tower B rather than from a finished building, and 30% of the price waits for completion. Every payment goes to the DLD-registered escrow account for project 4300, released against construction progress recorded by RERA inspections.

Entering Now at 0.6%
  • Enabling works, piling and foundation progressing: the record above is the risk picture
  • Four 5% instalments wait for construction milestones from 20%
  • 30% held until completion, with handover expected in Q3 2028
Typical Entry Close to Handover
  • Much of the construction risk resolved before you commit
  • A shorter wait between purchase and keys
  • A smaller remaining choice of units, floors and views
AED 716K ≈ USD 195KStarting Price
70/30 Plan30% Due on Completion
Q3 2028Expected Handover
Ask What Is Available at Windsor House 2

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Windsor House 2 Project Details

Windsor House 2 by Ellington in Dubai South Residential District project rendering of midrise residential buildings with balconies and planted frontage at dusk in Dubai - Presented by Tohid Fetrat
Dubai South Residential District · Ellington

With enabling works, piling and foundation progressing at the 20 August 2026 inspection, Windsor House 2 is an early-stage development of 414 studio to 3 bedroom apartments in two towers around a landscaped courtyard. Starting prices: AED 716K ≈ USD 195K.

For buyers entering at this stage, the trade off is the longest wait to the keys against the earliest position in the payment plan, with handover expected in Q3 2028.

Windsor House 2 by Ellington Project Guide

Site Context This Cycle

Explore Windsor House 2 Location on Dubai Map

On the developer's location aerial, Windsor House 2 fronts Community Road and Boulevard Road, with Tower A and Tower B set on either side of a central courtyard. In August the work recorded on that site was enabling, piling and foundation, so the basement and ground levels that the RERA report describes as B+LG+UG come before any of the ten residential floors.

Dubai South is a master development anchored by Al Maktoum International Airport (DWC), about 10 minutes' drive away per the developer's location guide, with Expo City Dubai about 16 minutes' drive. The district around the site already holds homes and roads in use, so buyers are following one building site rather than an unbuilt district, and the developer's brief ties the area's longer-term story to the planned expansion of DWC. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Windsor House 2 on Dubai Map

Buyer Resources for This Project

Investing in Windsor House 2 During Early Construction Progress

The enabling and foundations band is when payment protection, unit registration and residency planning are settled, long before handover. Each resource below is matched to where Windsor House 2 stands right now.

Windsor House 2 by Ellington in Dubai South Residential District construction updates cover image featuring a project rendering of midrise buildings and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Windsor House 2 Construction Updates

This page: the August 2026 inspection record for Windsor House 2, read against its 70/30 plan.

Windsor House 2 by Ellington in Dubai South Residential District Golden Visa concept graphic with a gold card above a rendered landscaped courtyard in Dubai - Presented by Tohid Fetrat

Windsor House 2 Golden Visa: Only 3 Bedroom Apartments Qualify

At Windsor House 2 by Ellington in Dubai South, only 3 bedroom apartments meet the Golden Visa threshold.

Read Windsor House 2 Golden Visa Guide
Windsor House 2 by Ellington in Dubai South Residential District escrow account concept graphic featuring a shield and padlock above an aerial project rendering in Dubai - Presented by Tohid Fetrat

Windsor House 2 Escrow Account at Mashreq Bank, DLD Project 4300

Windsor House 2 by Ellington escrows 414 residences at Mashreq Bank under DLD project 4300 in Dubai South.

Verify Windsor House 2 Escrow Account

Update Timeline

Other Windsor House 2 Construction Updates

August 2026 is the first dated reading published for Windsor House 2; each new inspection joins the record on the construction updates hub, reading by reading.

All Windsor House 2 Construction Updates

FAQs

Windsor House 2 Construction Progress in August 2026: Frequently Asked Questions

The Dubai Land Department project register shows Windsor House 2, project 4300, at 0.6% construction progress, recorded on 20 August 2026, against a previous inspection value of 0% that carries no date. The RERA report of the same date prints no percentage of its own and gives the site status as Enabling Works, Progressing.

Handover is expected in Q3 2028. At the time of the 20 August 2026 reading, the DLD project register recorded a completion date of 31-07-2029. Both dates can be revised between inspection cycles, so buyers should confirm the current construction and handover timetable with the developer in writing; how readings and register dates are followed over time is set out in the Windsor House 2 construction updates record.

The Independent Progress Monitoring Report dated 20 August 2026 found enabling works, piling and foundation progressing at the time of inspection, for a project described as B+LG+UG+10 Floors, 2 Buildings (Tower A and Tower B). No element of the build is recorded as complete, and the report carries inspection photographs.

The register pairs the 0.6% reading of 20 August 2026 with a previous inspection value of 0% but shows no date for that earlier value, so no measured pace between the two readings can be calculated. Counted instead from the recorded construction start of 12 February 2026, the average is about 0.1 points per month (arithmetic over the first six months, not a forecast).

No. The 70/30 plan ties four 5% instalments to completion of 20%, 30%, 40% and 50% construction, and the 0.6% reading of 20 August 2026 had not reached the first of them. Instalments paid up to that point followed the reservation-date schedule in each buyer's SPA, and the final 30% is paid on completion.

No. The main image is a developer rendering of the planned landscaped residential courtyard, used to illustrate this update, and it is not evidence of site works or construction progress. The RERA report for 20 August 2026 carries its own inspection photographs, which are not reproduced on this page.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Windsor House 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.