Windsor House 2 by Ellington in Dubai South Residential District construction updates cover image featuring a project rendering of midrise buildings and landscaped frontage in Dubai - Presented by Tohid Fetrat

Ellington · Dubai South Residential District

Windsor House 2 Construction Updates

Tower A and Tower B, Followed Reading by Reading from the Piling Stage in Dubai South

Windsor House 2 read 0.6% on 20 August 2026, its first dated DLD register reading, taken while enabling, piling and foundation works progressed at both towers.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0.6%Construction Progress
20 August 2026Latest RERA Inspection
414 residential unitsTotal Units
Project 4300DLD Registration

Construction Snapshot

Windsor House 2 at a Glance

Windsor House 2 is Ellington's 414-residence pair of towers in Dubai South Residential District, and its construction record is still in its opening months: the register logs a construction start on 12 February 2026, registration of project 4300 one day after that on 13 February 2026, and a single dated reading of 0.6% recorded on 20 August 2026. Because Tower A and Tower B share one plot, one register line and one reading, every figure below describes both buildings at once, with handover expected in Q3 2028.

DLD Project Number

4300

Project Status

Active, registered 13 February 2026

Construction Start

12 February 2026

Total Units

414 residential units

Total Built-Up Area

39,161.66 sq m

Registered Completion Date

31-07-2029

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Windsor House 2 Construction Update Timeline

This record holds one dated reading so far: 0.6% recorded on 20 August 2026, 189 days after the 12 February 2026 construction start. The register pairs it with a previous value of 0% that carries no date, so that earlier value sits on the track as an unlabelled dot at the start line rather than as a table row. The August 2026 entry is the only row below, and it links the full monthly update for that inspection.

Inspection MonthConstruction ProgressInspection DateFull Update
August 20260.6%20 August 2026View the August 2026 update

Pace Analysis

How Fast Windsor House 2 Has Been Built

With a single dated reading, Windsor House 2 has no inspection-to-inspection velocity yet. The only arithmetic the record supports runs from the registered construction start to the August 2026 reading:

  • 12 Feb 2026 to 20 Aug 2026: enabling works, piling and foundation, 0.6% recorded over 189 daysAbout 0.1 points per month
  • Previous register value of 0%, shown without a date, so no pace can be measured from itNo measured pace yet

That works out at about 0.1 points per month (arithmetic over the first six months, not a forecast). A curve needs two dated points, and Windsor House 2 has one, so the shape of this build cannot be read yet. What the single point does show is where the work sits: below ground, across a plot that has to carry basement, lower ground and upper ground levels under two ten-floor towers, which is work that moves a whole-project percentage very little per month. For an end user, the practical consequence is that reservation-date instalments, not the 0.6% recorded on 20 August 2026, set the near-term payment calendar. For an investor, the next dated reading is the one to watch, because it will be the first that allows a measured pace between two inspections.

Get the Next Inspection Figure First

Tell me you are tracking Windsor House 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Windsor House 2 at Dubai South Residential District

A 0.6% reading only means something next to what it is building toward. The full project guide covers the two towers this record is tracking:

Windsor House 2 by Ellington in Dubai South Residential District project rendering of midrise residential buildings with balconies and planted frontage at dusk in Dubai - Presented by Tohid Fetrat

Windsor House 2: Ellington's Courtyard Apartments in Dubai South

Windsor House 2 by Ellington features 414 residences across two towers in Dubai South, with landscaped courtyards and 70/30 payment plan.

View the Windsor House 2 Project Guide

Considering an Early-Stage Entry?

Windsor House 2 is listed with limited units available, and entering while the foundations are still being laid means choosing from plans across both towers rather than from a finished building. If the record on this page is what brought you here, ask me what is available today before the choice narrows.

Ask About Remaining Availability on WhatsApp

Stage Record

Windsor House 2 Build Stages, Mapped to the Inspections

Only the first two stages below have dates on this record yet. The rest are the work the RERA report's B+LG+UG+10 description still leaves ahead, listed in order so each new reading can be placed against them.

12 to 13 Feb 2026

Construction Start and Registration

The register shows construction starting on 12 February 2026 and project 4300 registered on 13 February 2026, one day apart, both as recorded.

Current PhaseFeb 2026 onward, 0.6% on 20 Aug 2026

Enabling Works, Piling and Foundation

The 20 August 2026 RERA report found enabling works, piling and foundation progressing on the Tower A and Tower B plot, with the register at 0.6% and nothing yet recorded as complete.

Not yet reached

Basement, Lower Ground and Upper Ground

The B+LG+UG levels the RERA report places beneath the residential floors, where Ellington's plans show parking, lobbies and retail and F&B units.

Not yet reached

Ten Residential Floors per Tower

Ten floors of studio to 3 bedroom apartments in each tower; the plan's four construction-linked instalments fall at 20%, 30%, 40% and 50% construction.

Handover expected Q3 2028

Facades, Fit-Out, Amenity Deck and Handover

Enclosure, apartment fit-out and the podium amenity deck between the towers, closing with handover, when the plan's final 30% falls due.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Windsor House 2's own record.

Buyer Position

Tracking Your Position at Windsor House 2

This page is one of four project resources that together cover a Windsor House 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Windsor House 2 by Ellington in Dubai South Residential District construction updates cover image featuring a project rendering of midrise buildings and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Windsor House 2 Construction Updates

This page: every dated register reading for Windsor House 2, from the 2026 start to handover.

Windsor House 2 by Ellington in Dubai South Residential District Golden Visa concept graphic with a gold card above a rendered landscaped courtyard in Dubai - Presented by Tohid Fetrat

Windsor House 2 Golden Visa: Only 3 Bedroom Apartments Qualify

At Windsor House 2 by Ellington in Dubai South, only 3 bedroom apartments meet the Golden Visa threshold.

Read the Windsor House 2 Golden Visa Guide
Windsor House 2 by Ellington in Dubai South Residential District escrow account concept graphic featuring a shield and padlock above an aerial project rendering in Dubai - Presented by Tohid Fetrat

Windsor House 2 Escrow Account at Mashreq Bank, DLD Project 4300

Windsor House 2 by Ellington escrows 414 residences at Mashreq Bank under DLD project 4300 in Dubai South.

Verify the Windsor House 2 Escrow Account

Approaching Handover

Between 0.6% and Handover: What Windsor House 2 Buyers Should Do Now

At the 0.6% recorded on 20 August 2026, the Windsor House 2 site was still 19.4 points short of the 20% construction milestone that triggers the first construction-linked instalment. The calendar does not wait for it: the six reservation-date instalments, 50% of the price, fall due within 360 days of each buyer's own reservation date, whatever the site reads, so the three steps below belong in the months before the first milestone, not after it.

First, before each reservation-date transfer, check the account details against the Windsor House 2 escrow account page, so every payment lands in the DLD-registered account for project 4300 held with Mashreq Bank PSC.

Second, settle residency planning by unit type before you reserve: the Windsor House 2 Golden Visa guide shows why the 3 bedroom apartments, from AED 2.33M ≈ USD 635K, are the one type that reaches the threshold on starting price.

Third, read each new register reading against the 20%, 30%, 40% and 50% construction milestones in your plan; every dated reading joins the inspection timeline on this page as it publishes.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai South Residential District Structure

A build record at the foundation stage is easier to judge against what already stands around it. These three pages put the Windsor House 2 site in its market, community and developer context:

Aerial view of Dubai South Residential District properties for sale showing landscaped community spaces and a large central pool, Presented by Tohid Fetrat

Dubai South Residential District: Inara Residence in the Freehold Core

Dubai South Residential District, the established freehold core of Dubai South, lists Inara Residence apartments on a 60/40 payment plan.

See Dubai South Residential District Properties for Sale
Aerial view of Dubai South Residential District showing villas, residential buildings, landscaped areas and a central lake, Presented by Tohid Fetrat

Dubai South Residential District: A Freehold Zone Beside Expo City Dubai

Dubai South Residential District has gated villa, townhouse and apartment communities, a lagoon beachfront and freehold title for all nationalities.

Explore the Dubai South Residential District Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Windsor House 2 Construction Updates Frequently Asked Questions

Windsor House 2 is an active DLD-registered project, number 4300, at its enabling, piling and foundation stage, with a register reading of 0.6% recorded on 20 August 2026, the latest dated reading on this record. No part of the build is recorded as complete, and the full record is in the inspection timeline above.

Each percentage here is a Dubai Land Department register reading published after a RERA site inspection. The latest, 0.6% recorded on 20 August 2026, is 0.6 points above the register's previous value of 0%, which carries no date and is therefore shown as a dot rather than a timeline row. Every dated reading gets its own row and its own monthly page, starting with the August 2026 construction update for Windsor House 2.

Handover at Windsor House 2 is expected in Q3 2028, while the DLD project register records a completion date of 31-07-2029 for project 4300. The registered date has not lapsed, and this page prints both dates exactly as recorded without interpreting the difference between them. Buyers should confirm the current construction and handover timetable with Ellington in writing, and this page's record is updated when each new reading is recorded.

Windsor House 2 includes 414 residences, studio to 3 bedroom apartments, split across two towers, Tower A and Tower B, around a landscaped central courtyard. Unit types, sizes and prices from AED 716K ≈ USD 195K are set out in the full Windsor House 2 project profile.

The DLD register records the Windsor House 2 construction start as 12 February 2026 and the registration of project 4300 as 13 February 2026, one day apart; both dates are shown as recorded. The first dated reading followed 189 days after the start, at 0.6% on 20 August 2026.

Measured from the 12 February 2026 start to the 0.6% recorded on 20 August 2026, Windsor House 2 averaged about 0.1 points per month (arithmetic over the first six months, not a forecast). No pace between two inspections exists yet, because the only earlier value, 0%, is undated; the working is in the pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Windsor House 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status