350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 project rendering used for the August 2026 construction update showing the planned swimming pool, landscaped deck and surrounding residential towers in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2 · Construction Update

350 Riverside Crescent Construction Update - August 2026

August 2026 Inspection Records 350 Riverside Crescent at 57.85% Construction Progress in Sobha Hartland 2

The RERA report describes structure works at an advanced stage, with envelope, MEP and finishes progressing, as the DLD register records 350 Riverside Crescent at 57.85 percent.

Direct advisor access. Every message answered personally, never by a call center.

57.85%DLD Register Reading
18 August 2026Inspection Date
Q4 2027Expected Completion
3083DLD Project Number

Verified DLD Inspection Data

350 Riverside Crescent Construction Snapshot

A 7.78 point rise over the previous register reading of 50.07%, which the register shows without a date, takes 350 Riverside Crescent past the halfway mark and into the envelope and MEP band, where checking the build against your payment schedule matters most.

Project Name

350 Riverside Crescent by Sobha Realty

Project Number

3083

Project Status

Active

Construction Progress

57.85%

Inspection Date

18 August 2026

Construction Start

10 May 2024

Total Units

742 residential units

Total Built Area

62,125.97 sq m

Expected Completion

Q4 2027

Data source: DLD project register reading for inspection dated 18 August 2026 (project registered 03 June 2024), with the RERA Independent Progress Monitoring Report of the same date for the works description and tower configuration; that report prints no percentage. Q4 2027 is the handover quarter stated by Sobha Realty. The hero image is a Sobha Realty project rendering, not a site photograph, and shows no construction progress. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

350 Riverside Crescent Construction Progress Summary

The RERA report dated 18 August 2026 describes project 3083 working on two fronts at once: structure works progressing at an advanced stage, while internal works, the external envelope, internal finishes and MEP move forward at different stages. The register reading of 57.85% sits against a previous reading of 50.07% that carries no date, and the main contract is listed as progressing.

Completed
  • Enabling works for the tower and podium
  • Foundation works
  • Substructure works, as recorded in the RERA report
In Progress at 57.85%
  • Structure works at an advanced stage per the RERA report
  • External envelope, progressing at different stages
  • Internal works and internal finishes
  • MEP systems: mechanical, electrical and plumbing
Ahead of Handover
  • Remaining structure works up to the 59 floors and roof
  • Envelope, MEP and finishes across the 742 residences
  • Further RERA inspection cycles toward 100% and the Q4 2027 handover
Next inspectionPublished in the DLD project register after the next RERA site visit; the register shows readings, not a schedule, so no date is given here.
Completion targetQ4 2027 handover as stated by Sobha Realty. Arithmetic, not a forecast: the build has averaged about 2.09 points per month since the 10 May 2024 start, and about 2.53 points per month would reach 100% by the end of Q4 2027. Build pace is rarely linear, since late stages are finishes and fit out, and the handover date is Sobha's to confirm.
Remaining distance42.15 percentage points separate the 18 August 2026 reading from 100%.

Payment Linked Progress

What 57.85% Progress Means for 350 Riverside Crescent Buyers

Sobha Realty's 80/20 plan places 60% of the price in the construction phase, so the 57.85% register reading is a payment question as much as a progress one: how much of that 60% is already due at today's stage is set in each SPA. Past the halfway mark, four actions matter most.

Before Any Transfer

Verify the escrow account

Every construction payment should go only to the DLD regulated escrow account registered for project 3083. 350 Riverside Crescent escrow account verification comes before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing

Map your SPA against the 60%

Ask Sobha Realty for the schedule showing how much of the construction 60% falls due on signing at this stage and how the rest is triggered, read alongside the Q4 2027 handover quarter. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Off plan units are recorded on the DLD interim register, Oqood, after booking; check that your unit sits under project 3083 before construction payments continue. The purchase price recorded there is also the value a Golden Visa application is measured against, as the 350 Riverside Crescent Golden Visa guide explains.

Every Cycle

Track the remaining cycles

With 42.15 points still to be recorded before Q4 2027, several more register readings will land before handover. 350 Riverside Crescent construction updates hub logs each one as it publishes.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 57.85%?

Entering at this stage trades part of the launch-era installment runway for evidence: enabling, foundation and substructure works are recorded as completed, the RERA report puts the structure at an advanced stage, and the handover quarter is a little over a year away. Every payment goes to the DLD-registered escrow account for project 3083, released against recorded construction progress.

Entering Now at 57.85%
  • Recorded build: the register reading and RERA notes above set the risk picture
  • Handover quarter Q4 2027, a little over a year after this reading
  • Part of the construction 60% may already be due; your SPA sets how much
Typical Launch Entry
  • Construction risk carried from excavation through to handover
  • A delivery horizon usually measured in years, not quarters
  • Longer installment runway at launch-stage pricing
AED 1.09M ≈ USD 297KStarting Price
80/20 Plan20% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at 350 Riverside Crescent

9 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

350 Riverside Crescent Project Details

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 aerial project rendering of high-rise residential towers with a green arrow identifying one building in Dubai - Presented by Tohid Fetrat
Sobha Hartland 2 · Sobha Realty

With substructure works completed and the structure at an advanced stage in the 18 August 2026 RERA report, 350 Riverside Crescent is a mid-construction Sobha Realty tower of 742 residences in 1, 1.5 and 2 bedroom layouts. Starting prices: AED 1.09M ≈ USD 297K.

For buyers entering at this stage, the trade off is a shorter wait to the Q4 2027 handover against a larger share of the 80/20 plan falling due on or soon after signing.

350 Riverside Crescent by Sobha Realty Project Guide

Site Context This Cycle

Explore 350 Riverside Crescent Location on Dubai Map

350 Riverside Crescent is one of the six towers Sobha Realty arranges in a tapered crescent in Sobha Hartland 2, a single tower of two basements, a ground level, four podium levels and 59 floors plus roof according to the RERA report. In a building of that height, an advanced structure stage running alongside envelope, MEP and finishes usually means the trades are stacked by level, with later packages following the frame upward through this cycle.

Sobha Realty plans Sobha Hartland 2 as a master community of about 8 million sq ft with an international school, offices, a mall, clubhouses and retail, so buyers weighing a Q4 2027 move-in or rental plan should check which of those facilities will be open by handover rather than assume a finished district. The developer's brochure places Downtown Dubai and Meydan Racecourse about 10 minutes from Sobha Hartland 2 and Dubai International Airport about 12. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view 350 Riverside Crescent by Sobha Realty on Dubai Map

Buyer Resources for This Project

Investing in 350 Riverside Crescent During Mid-Construction Progress

Past the halfway mark, payment protection and residency eligibility are the two checks that cannot wait for handover. Each resource below is matched to where 350 Riverside Crescent stands right now.

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of residential towers, landscaped podiums and swimming pools from above in Dubai - Presented by Tohid Fetrat
You Are Here

350 Riverside Crescent Construction Updates

This page: the August 2026 register reading of 57.85% and RERA notes for 350 Riverside Crescent.

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic showing a gold card above a rendered swimming pool, palm tree and residential towers in Dubai - Presented by Tohid Fetrat

350 Riverside Crescent Golden Visa: Only 2 Bedroom Apartments Qualify

350 Riverside Crescent by Sobha has three apartment layouts, but only 2 bedroom units exceed the AED 2M Golden Visa threshold.

Read 350 Riverside Crescent Golden Visa Guide
350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 escrow concept graphic featuring a shield and padlock above a rendered outdoor pool with inflatable play structures and residential towers in Dubai - Presented by Tohid Fetrat

350 Riverside Crescent Escrow Account: Emirates NBD, DLD Project 3083

350 Riverside Crescent's 742 residences use an Emirates NBD escrow account under DLD project 3083, inspected at 57.85% in August 2026.

Verify 350 Riverside Crescent Escrow Account

Update Timeline

Other 350 Riverside Crescent Construction Updates

August 2026 opens the monthly record for 350 Riverside Crescent on this site; each later register reading joins the hub as it publishes, so the tower can be followed reading by reading.

All 350 Riverside Crescent Construction Updates

FAQs

350 Riverside Crescent Construction Progress in August 2026: Frequently Asked Questions

As of the inspection dated 18 August 2026, the Dubai Land Department project register records 350 Riverside Crescent, project 3083, at 57.85% construction progress, up from a previous register reading of 50.07% that is shown without a date. The RERA progress report issued for the same inspection describes the works but prints no percentage of its own, so the register figure is the one to quote.

No change is stated: Q4 2027 remains the handover quarter Sobha Realty gives for 350 Riverside Crescent as of this update, and the 18 August 2026 RERA report records the state of the works, not a revised date. A handover quarter can still move between inspection cycles; any revision would come from Sobha Realty and the DLD project record and would be reflected on the 350 Riverside Crescent construction updates hub.

The Independent Progress Monitoring Report for project 3083 records enabling, foundation and substructure works as completed, and structure works progressing at an advanced stage, with internal works, the external envelope, internal finishes and MEP progressing at different stages. It describes the building as two basements, a ground level, four podium levels, 59 floors and a roof, and the register record carries inspection photographs that are not published here.

The register view used for this update shows 50.07% as the previous inspection beside the 18 August 2026 reading but does not display when that earlier inspection took place. This page therefore gives it no month and calculates no pace between the two readings; the only dated figures are the 10 May 2024 construction start, the 03 June 2024 registration and the August 2026 reading.

No. The hero image is a Sobha Realty project rendering of the planned pool deck and surrounding towers, used to illustrate the August 2026 update, and it shows no actual construction progress. The progress evidence for this month is the DLD register reading and the written RERA report, not the image.

Under the 80/20 plan, 20% is paid at booking, 60% during construction and 20% on completion, and the 57.85% reading of 18 August 2026 places the tower past the halfway mark of construction. How much of the construction 60% is already due at this stage is set in each SPA, so a buyer entering after this reading should ask Sobha Realty for the unit's schedule before signing.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for 350 Riverside Crescent correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts