350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of residential towers, landscaped podiums and swimming pools from above in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2

350 Riverside Crescent Construction Updates

The DLD Register Record of a 59-Floor Tower in Sobha Hartland 2

350 Riverside Crescent read 57.85% on the DLD register on 18 August 2026, past halfway, with the RERA report placing structure works at an advanced stage.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

57.85%Construction Progress
18 August 2026Latest RERA Inspection
742 residential unitsTotal Units
Project 3083DLD Registration

Construction Snapshot

350 Riverside Crescent at a Glance

350 Riverside Crescent is the Sobha Realty tower of 742 residences registered with the Dubai Land Department as project 3083, one of the six towers the developer sets along a crescent in Sobha Hartland 2. The register dates its construction start to 10 May 2024, three weeks before its 03 June 2024 registration, and recorded 57.85% on 18 August 2026, two years and three months into the build. With 59 floors and a roof stacked over four podium levels, a ground level and two basements in the RERA report, the percentages below follow one tall vertical build rather than a spread of low-rise blocks, so every point gained is measured against a single frame rising floor by floor.

DLD Project Number

3083

Project Status

Active

Construction Start

10 May 2024

Total Units

742 residential units

Total Built-Up Area

62,125.97 sq m

Registered Completion Date

Q4 2027 (developer handover)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

350 Riverside Crescent Construction Update Timeline

This record holds one dated reading so far: 57.85% on 18 August 2026, logged 27 months after the 10 May 2024 construction start. The register also lists an earlier 50.07% without a date, so it sits on the track as an undated marker rather than a table row, and the next dated reading will give this tower its first measurable interval. The row below links the August 2026 update, whose cover image is a Sobha Realty rendering rather than a site photograph.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202657.85%18 August 2026View the August 2026 update

Pace Analysis

How Fast 350 Riverside Crescent Has Been Built

With one dated reading, 350 Riverside Crescent has no inspection-to-inspection velocity yet. What the record does support is two pieces of arithmetic, anchored on the 10 May 2024 start and the Q4 2027 handover quarter, and neither is a forecast:

  • 10 May 2024 to 18 Aug 2026: foundations and structure, start to 57.85%, whole-build averageAbout 2.09 points per month
  • 18 Aug 2026 to end of Q4 2027: structure, envelope and finishes, 57.85% to 100%, rate that would be neededAbout 2.53 points per month

Set side by side, the two numbers show that the remaining 42.15 points would need a higher monthly average than the first 830 days of this build produced. That comparison is arithmetic, not a verdict: the register shows readings rather than a schedule, a tower of 59 floors over four podium levels rarely gains percentage at an even rate, and the late stages of any build are finishes and fit-out, which register differently from structure. The register also lists a previous 50.07% without a date, so the step from that figure to the 57.85% of 18 August 2026 cannot be turned into a monthly pace. For an end user, Q4 2027 remains Sobha Realty's quarter to confirm rather than something this arithmetic settles; for an investor, the next dated reading on project 3083 is the first figure that will show the tower's actual rate between two inspections.

Get the Next Inspection Figure First

Tell me you are tracking 350 Riverside Crescent and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About 350 Riverside Crescent at Sobha Hartland 2

The 57.85% of 18 August 2026 only means something next to what is being built. The project guide covers the tower this record is following toward handover:

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 aerial project rendering of high-rise residential towers with a green arrow identifying one building in Dubai - Presented by Tohid Fetrat

350 Riverside Crescent: 742 Apartments in Sobha Hartland 2

350 Riverside Crescent is one of six Riverside Crescent towers by Sobha Realty, featuring 1, 1.5 and 2 bedroom apartments.

View the 350 Riverside Crescent Project Guide

Considering a Mid-Construction Entry?

Units at 350 Riverside Crescent are released and priced by Sobha Realty, and what remains changes as the tower climbs toward Q4 2027. If this record is what brought you here, ask me what is available today and how much of the construction 60% a new SPA would place on signing.

Ask About Remaining Availability on WhatsApp

Stage Record

350 Riverside Crescent Build Stages, Mapped to the Inspections

Only one dated report exists for this tower so far, so each stage below is placed using the 10 May 2024 start, the RERA report of 18 August 2026 and the 57.85% register reading of the same date, rather than a run of monthly inspections.

From 10 May 2024

Site Activation and Enabling Works

Construction started on 10 May 2024 and the project was registered on 03 June 2024; the 18 August 2026 report lists enabling works as completed.

Completed by 18 Aug 2026

Foundations and Substructure

Foundation and substructure works for a building with two basement levels are recorded as completed in the RERA report dated 18 August 2026.

Current PhaseTo 18 Aug 2026, 57.85% at last reading

Podium and Tower Structure

The RERA report placed structure works for four podium levels and 59 floors at an advanced stage, with the register at 57.85% on 18 August 2026.

Underway in parallel at 18 Aug 2026

Envelope, MEP and Internal Finishes

External envelope, MEP, internal works and finishes were each moving at their own stage when the 57.85% reading was logged on 18 August 2026.

Toward the Q4 2027 handover

Completion and Handover

The remaining 42.15 points run to 100% and handover in Q4 2027, the quarter Sobha Realty states and is to confirm.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on 350 Riverside Crescent's own record.

Buyer Position

Tracking Your Position at 350 Riverside Crescent

This page is one of four project resources that together cover a 350 Riverside Crescent purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of residential towers, landscaped podiums and swimming pools from above in Dubai - Presented by Tohid Fetrat
You Are Here

350 Riverside Crescent Construction Updates

This page: project 3083's DLD register record, from the May 2024 start toward Q4 2027.

350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic showing a gold card above a rendered swimming pool, palm tree and residential towers in Dubai - Presented by Tohid Fetrat

350 Riverside Crescent Golden Visa: Only 2 Bedroom Apartments Qualify

350 Riverside Crescent by Sobha has three apartment layouts, but only 2 bedroom units exceed the AED 2M Golden Visa threshold.

Read the 350 Riverside Crescent Golden Visa Guide
350 Riverside Crescent by Sobha Realty in Sobha Hartland 2 escrow concept graphic featuring a shield and padlock above a rendered outdoor pool with inflatable play structures and residential towers in Dubai - Presented by Tohid Fetrat

350 Riverside Crescent Escrow Account: Emirates NBD, DLD Project 3083

350 Riverside Crescent's 742 residences use an Emirates NBD escrow account under DLD project 3083, inspected at 57.85% in August 2026.

Verify the 350 Riverside Crescent Escrow Account

Approaching Handover

Between 57.85% and Handover: What 350 Riverside Crescent Buyers Should Do Now

At 57.85% on 18 August 2026, 350 Riverside Crescent is in the stretch where the construction 60% of the 80/20 plan is paid while the tower rises, so the useful work now is matching each payment to the record rather than preparing for keys. How much of that 60% falls due at each stage is set in every SPA, which makes the three checks below worth doing before the next payment leaves your account, not after it.

First, make each construction-phase transfer only to the account shown on the 350 Riverside Crescent escrow account page, which explains how to match it to project 3083 in the Dubai Land Department record.

Second, if residency matters to your purchase, read the 350 Riverside Crescent Golden Visa guide now: only the 2 bedroom layout from AED 2.55M ≈ USD 694K is priced above the AED 2M ≈ USD 545K threshold, and the qualifying value is the price recorded on your Oqood.

Third, follow the register reading by reading: the 350 Riverside Crescent August 2026 construction update sets out the 18 August 2026 report in full, and each later reading for project 3083 joins this record as it publishes.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Sobha Hartland 2 Structure

A single tower's register reading reads differently once you see the master community taking shape around it. These three pages place the 57.85% that 350 Riverside Crescent recorded on 18 August 2026 in its market, community and developer context:

Aerial view of Sobha Hartland 2 properties for sale in Dubai showing modern residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments

Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.

See Sobha Hartland 2 Properties for Sale
Aerial night view of Sobha Hartland 2 in Dubai showing illuminated residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra

Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.

Explore the Sobha Hartland 2 Community
Sobha Developer Dubai – luxury skyscraper with rooftop pool and skyline view of Burj Khalifa

Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels

Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.

View the Sobha Realty Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

350 Riverside Crescent Construction Updates Frequently Asked Questions

350 Riverside Crescent is an active Dubai Land Department project, number 3083, recorded at 57.85% construction progress on the register after the inspection of 18 August 2026. The RERA report of that date records enabling works, foundations and the substructure as completed, puts structure works at an advanced stage and shows the external envelope, MEP and internal finishes running alongside them. The dated record is in the inspection timeline above.

The register moved from a previous reading of 50.07% to 57.85% at the inspection of 18 August 2026, a rise of 7.78 points. The earlier reading is shown without a date, so the time between the two readings, and with it a monthly rate for that step, cannot be worked out from the register view used for this page.

Averaged over the whole build, 350 Riverside Crescent has gained about 2.09 points per month: 57.85 points across the 830 days from the 10 May 2024 start to the 18 August 2026 reading. Reaching 100% by the end of the Q4 2027 handover quarter would take about 2.53 points per month. Both figures are arithmetic, not a forecast: the register shows readings rather than a schedule, late stages such as finishes and fit-out rarely move at the same rate as structure, and the handover date is Sobha Realty's to confirm. The working is in the pace analysis above.

The Dubai Land Department register gives a construction start of 10 May 2024 and a registration date of 03 June 2024 for project 3083, so the recorded start comes before the registration. The first reading tracked on this site is 57.85% on 18 August 2026, covered in the August 2026 350 Riverside Crescent construction report.

350 Riverside Crescent holds 742 residences, split between 1 bedroom, 1.5 bedroom and 2 bedroom apartments. In the RERA report of 18 August 2026 the tower is configured 2B+G+4P+59F+R: 59 floors and a roof rising over four podium levels, a ground level and two basements, with the register reading for the whole building at 57.85% on that date.

Each figure on this page is a Dubai Land Department register reading for project 3083, dated to the inspection it belongs to; the latest is 57.85% from 18 August 2026. The RERA progress report filed on that date carries no percentage of its own; it supplies the stage notes and the tower configuration, while the figure itself comes from the register. How readings are gathered across every tracked project is set out on the Dubai Construction Updates hub.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the 350 Riverside Crescent construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.