Six Senses Residences The Palm lagoon pool and landscaped amenities during the May 2026 construction update on Palm Jumeirah Presented by Tohid Fetrat

Six Senses Residences The Palm Construction Update - May 2026

May 2026 Inspection Confirms Six Senses Residences The Palm Reaches 97.86% Construction Progress

The May 2026 RERA inspection confirms Six Senses Residences The Palm has reached 97.86% construction progress, with final hotel building MEP, internal finishes, external envelope, and external works advancing toward completion.

Six Senses Residences The Palm Construction Snapshot

Minimal black line icon representing project name with building symbol in modern UI design Presented by Tohid Fetrat

Project Name

Six Senses Residences The Palm Dubai

Minimal black line icon showing grid with hash symbol representing project number Presented by Tohid Fetrat

Project Number

2350

Minimal black line icon showing checklist with check marks and approval badge representing project status Presented by Tohid Fetrat

Project Status

Active

Minimal black line icon showing construction crane with rising bar chart representing construction progress Presented by Tohid Fetrat

Construction Progress

97.86%

Minimal black line icon showing calendar with check mark representing inspection date Presented by Tohid Fetrat

Inspection Date

05 May 2026

Minimal black line icon showing construction crane with check mark representing construction start Presented by Tohid Fetrat

Construction Start

05 January 2022

Minimal black line icon showing unit grid with question mark representing total units Presented by Tohid Fetrat

Total Units

162 luxury residences

Minimal black line icon showing building surrounded by measuring tape representing total built area Presented by Tohid Fetrat

Total Built Area

112,361.27 sq m

Minimal black line icon showing calendar with clock representing expected completion time Presented by Tohid Fetrat

Expected Completion

Q3 2026

Six Senses Residences The Palm Construction Progress Summary

The latest RERA inspection conducted on 05 May 2026 confirms Six Senses Residences The Palm has advanced from 97.58% to 97.86% construction progress as the ultra-luxury branded development enters its final construction phase.

Current inspection findings confirm that the hotel building continues progressing through MEP installation, internal finishes, external envelope works, and external works, while major construction activities across the residences and villas have been substantially completed.

Six Senses Residences The Palm Final Construction Activities Update

The May 2026 RERA inspection confirms Six Senses Residences The Palm has reached its final stage of construction, with the residences and signature villas substantially completed while remaining work continues within the hotel component.

Current inspection findings confirm ongoing MEP installation, internal finishes, external envelope works, and external works at the hotel building. Building Completion Certificate (BCC), DCD approvals, LPG systems, DEWA utilities, and district cooling connections have already been completed, reflecting the project's advanced delivery stage.

Explore Six Senses Residences The Palm Location on Dubai Map

Six Senses Residences The Palm is located on the West Crescent of Palm Jumeirah, one of Dubai’s most exclusive beachfront destinations, surrounded by luxury resorts, branded residences, private beaches, and panoramic Gulf views.

Interactive Dubai real estate map preview
Click to view Six Senses Residences The Palm on Dubai Map

Investing in Six Senses Residences The Palm During Final Construction

The increase from 97.58% to 97.86% construction progress marks Six Senses Residences The Palm's transition into its final delivery phase, with remaining hotel building works progressing alongside completed residential and infrastructure components.

As the project approaches completion, verified RERA inspections, buyer protection resources, and independent pre-handover inspections help purchasers make well-informed decisions before final acceptance.

Dubai Golden Visa Through Six Senses Residences The Palm

Eligible Six Senses Residences The Palm investments may qualify buyers for long-term UAE residency.

Escrow Protection for Six Senses Residences The Palm

Buyer payments remain protected through a DLD-regulated escrow account linked to construction milestones.

Six Senses Residences The Palm Snagging Inspection

Arrange an independent pre-handover inspection to identify defects before accepting your completed luxury residence.

Six Senses Residences The Palm Project Details

Six Senses Residences The Palm is an ultra-luxury branded beachfront development by Select Group on the West Crescent of Palm Jumeirah, featuring penthouses, sky villas, royal penthouses, signature villas, and private resort-style living.

The project combines wellness-focused residences, Six Senses hospitality, private beach access, and world-class amenities to deliver one of Palm Jumeirah's most exclusive branded residential communities.

Six Senses Residences The Palm by Select Group residential building exterior with contemporary architecture in Dubai - Presented by Tohid Fetrat

Explore Palm Jumeirah Structure

Six Senses Residences The Palm construction updates connect to the luxury beachfront ecosystem of Palm Jumeirah, alongside world-class branded residences, exclusive waterfront communities, and Select Group developments.

Palm Jumeirah Properties for Sale

Browse beachfront residences, luxury villas, penthouses, and branded investment opportunities.

Palm Jumeirah Community Overview

Discover luxury resorts, private beaches, waterfront living, and iconic island communities.

Select Group Developer Profile

Explore Select Group's luxury waterfront developments and branded residential communities.

Six Senses Residences The Palm Construction Update - FAQs

What is the current construction progress of Six Senses Residences The Palm?

The latest RERA inspection on 05 May 2026 confirms the project has reached 97.86% construction progress.

What construction activities are currently underway?

Current works focus on the hotel building, including MEP installation, internal finishes, external envelope, and external works.

Have the residential buildings been completed?

Yes. The latest inspection notes indicate the residential components are substantially complete, with remaining work concentrated on the hotel building.

What is the original project completion date?

The project was originally registered with an expected completion date of 31 December 2024. Based on the latest RERA inspection, the expected completion timeline is now Q3 2026 while final construction activities continue.

How many residences are included in Six Senses Residences The Palm?

The development comprises 162 luxury residences, including penthouses, sky villas, royal penthouses, and signature villas.

Why should buyers follow monthly construction updates?

Monthly updates provide verified RERA inspection progress, helping buyers monitor delivery milestones and project completion status.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments
Message Me

For any questions about your real estate investment, message or call me directly. I’m here to guide you toward the best opportunities in Dubai.

WhatsApp Get more information
×

Loading...