Select Group · Palm Jumeirah
Six Senses Residences The Palm Construction Updates
The Dated Build Record of a Branded Beachfront Address on the West Crescent
Six Senses Residences The Palm read 100% at its 01 September 2026 RERA inspection, leaving snagging, common-area painting and deep cleaning on the West Crescent before handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Six Senses Residences The Palm at a Glance
Six Senses Residences The Palm is Select Group's 162-residence branded development on plot 2023 of Palm Jumeirah's West Crescent, where two penthouse buildings, two sky villa towers and nine signature beachfront villas share the site with a 61-key Six Senses hotel. Its record runs from a 05 January 2022 construction start, with DLD registration dated 04 February 2022, to 100% and a Completed status at the 01 September 2026 inspection. Because a hotel shares the plot with three residential formats, this record has to be read building by building: the last packages listed as open in May 2026 sat at the hotel building, not the residential blocks.
2350
Finished (DLD register)
05 January 2022
162 Luxury Residences
112,361.27 sq m
31 December 2024
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Six Senses Residences The Palm Construction Update Timeline
Two dated inspections make up this record: 97.86% on 05 May 2026, while the Progress Status still read Main Contract - Progressing, and 100% on 01 September 2026, when it changed to Completed. The May entry also carries an earlier reading of 97.58% with no date attached, so it sits on the track below as a dot but has no table row. Each row links the full monthly update for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 100% | 01 September 2026 | View the September 2026 update |
| May 2026 | 97.86% | 05 May 2026 | View the May 2026 update |
Reading the dates: the DLD-registered completion date for project 2350 is 31 December 2024, which had lapsed 609 days before the 01 September 2026 inspection recorded 100% and a Completed status. The Building Completion Certificate, issued by TKS on 14 January 2026, is also on record. The register still showed the 31 December 2024 date at that reading; handover is scheduled for Q3 2026, and each buyer's unit date is confirmed by Select Group.
Pace Analysis
How Fast Six Senses Residences The Palm Has Been Built
Six Senses Residences The Palm carries one measured pace and one whole-build average, and each answers a different question:
- May 2026 to Sep 2026: finishing and close-out, 97.86% to 100%About 0.54 points per 30-day month
- Jan 2022 to Sep 2026: whole build, 05 January 2022 start to 100% on 01 September 2026 (arithmetic average, not a forecast)About 1.76 points per 30-day month
The measured figure is narrow by design: 2.14 points across the 119 days between the two dated inspections, the stretch in which the hotel building's envelope, MEP, internal finishes and external works dropped out of the inspection notes. The whole-build figure is plain arithmetic, 100 points spread over 1,700 days from the January 2022 start; with no dated reading before May 2026 in this record, it cannot show where the build sped up or slowed, and it predicts nothing. What the record does show is unusual in its order: DCD, LPG and the Building Completion Certificate were all issued between November 2025 and January 2026, months before the last 2.14 points closed. For an end user, construction risk is off the table and the open items are the handover date and the condition of the unit; for an investor, the completed record moves the timing question from the build to the Q3 2026 handover.
Get the Next Inspection Figure First
Tell me you are tracking Six Senses Residences The Palm and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Six Senses Residences The Palm at Palm Jumeirah Dubai
With construction recorded at 100% on 01 September 2026, the question moves from the build to what buyers receive at handover. The full project guide covers it:

Six Senses Residences The Palm, Beside a Six Senses Hotel
Six Senses Residences The Palm holds 162 branded Select Group homes on the West Crescent, beside a 61-key hotel.
View the Six Senses Residences The Palm Project GuideConsidering a Pre-Handover Entry?
Limited units remain at Six Senses Residences The Palm, and the building now reads Completed ahead of the Q3 2026 handover. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Six Senses Residences The Palm Build Stages, Mapped to the Inspections
Only two dated inspections exist for Six Senses Residences The Palm, so the windows below also lean on the register's January 2022 start and the three completion approvals of late 2025 and early 2026 to place each stage in time.
Site Start and Registration
Construction on plot 2023 started on 05 January 2022, and the DLD registered project 2350 on 04 February 2022.
Hotel, Penthouse Blocks, Sky Villas, and Villas
The B+G+10+R hotel and penthouse buildings, two B+G+7+R sky villa towers and nine B+G+2+R signature villas were built out before the late 2025 approvals; no dated inspection from this window is held in the record.
Completion Approvals Issued
DCD on 05 November 2025, LPG on 11 December 2025 and the Building Completion Certificate from TKS on 14 January 2026 were all on record before the first dated reading.
Hotel Building Close-Out
The 05 May 2026 inspection recorded 97.86%, 0.28 points above an undated 97.58%, with envelope, MEP, finishes and external works still open at the hotel building and Empower cooling connected.
Completed, Snagging, and Handover Preparation
The 01 September 2026 inspection put the build at 100% with a Completed status, leaving snagging, common-area painting and deep cleaning under way ahead of the Q3 2026 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Six Senses Residences The Palm's own record.
Buyer Position
Tracking Your Position at Six Senses Residences The Palm
This page is one of four project resources that together cover a Six Senses Residences The Palm purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Six Senses Residences The Palm Construction Updates
This page: Six Senses Residences The Palm's record, 97.86% in May to 100% in September 2026.

Six Senses Residences The Palm Golden Visa: Five Residence Types
Select Group's Six Senses Residences The Palm, 162 branded residences on the West Crescent, qualifies at all five types.
Read the Six Senses Residences The Palm Golden Visa Guide
Six Senses Residences The Palm: Select Group's Escrow at 100%
Select Group's Six Senses Residences The Palm, DLD project 2350, read 100% certified September 2026, 173 units escrowed at Emirates NBD.
Verify the Six Senses Residences The Palm Escrow Account
Six Senses Residences The Palm Snagging: Penthouses, Sky Villas and Beachfront Villas
Six Senses Residences The Palm is Select Group's collection of 162 branded residences on the West Crescent of Palm Jumeirah.
Book Six Senses Residences The Palm SnaggingApproaching Handover
Between 100% and Handover: What Six Senses Residences The Palm Buyers Should Do Now
At Six Senses Residences The Palm the remaining gap is no longer measured in points: construction has read 100% since 01 September 2026 and the Building Completion Certificate dates from 14 January 2026, so what stands between buyers and their keys is the site close-out and the handover notice for the Q3 2026 handover. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.
First, have your residence inspected independently before you sign acceptance; the September 2026 notes list snagging among the works under way on site, but that close-out is the contractor's, and the Six Senses Residences The Palm snagging page covers what an owner's inspection checks in penthouses, sky villa balcony pools and villa basements.
Second, confirm how your completion balance is scheduled against the DLD record for project 2350 on the Six Senses Residences The Palm escrow account page, so the final payment follows recorded completion, not a request.
Third, every residence type offered here is priced above the Golden Visa property threshold, so plan the application around the Q3 2026 handover and title deed timing with the Six Senses Residences The Palm Golden Visa guide.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Palm Jumeirah Dubai Structure
A finished build is judged against what surrounds it. These three pages put the completed Six Senses Residences The Palm record in its market, island and developer context:

Palm Jumeirah Dubai Properties for Sale
Browse beachfront apartments, penthouses, sky mansions and signature villas for sale across Palm Jumeirah.
See Palm Jumeirah Dubai Properties for Sale
Palm Jumeirah Dubai Community Overview
Read the Palm Jumeirah guide: Nakheel's island of signature villas, branded residences, private beaches and five-star resorts.
Explore the Palm Jumeirah Dubai Community
Select Group: Premium Waterfront Residences From Marina Gate to Peninsula
Select Group delivers waterfront developments in Palm Jumeirah, Business Bay and Dubai Marina: founded in 2002, with over 7,000 units delivered.
View the Select Group Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Six Senses Residences The Palm Construction Updates Frequently Asked Questions
Six Senses Residences The Palm, DLD project 2350, is recorded at 100% in the DLD project register following the RERA inspection of 01 September 2026, with its Progress Status marked Completed and the DLD app listing the project as Finished. Snagging, common-area painting and deep cleaning were still under way on site that day, and handover is scheduled for Q3 2026. The full record is in the inspection timeline above.
The 01 September 2026 inspection recorded 100% construction progress, up 2.14 points from the 97.86% reading of 05 May 2026, and moved the Progress Status from Main Contract - Progressing to Completed. The site notes for that visit are covered in the September 2026 construction update.
Read side by side, 97.86% on 05 May 2026 and 100% on 01 September 2026 show the final 2.14 points closing in 119 days. In May the open packages were the external envelope, MEP, internal finishes and external works at the hotel building; by September the notes named only snagging, common-area painting and deep cleaning. The May visit is documented in the May 2026 construction update.
Measured on its two dated inspections, Six Senses Residences The Palm advanced 2.14 points in 119 days between 05 May 2026 and 01 September 2026, about 0.54 points per 30-day month. Across the whole build, 100 points over the 1,700 days from the 05 January 2022 construction start to 01 September 2026 averages about 1.76 points per 30-day month; that figure is arithmetic, not a measured phase and not a forecast. The comparison is set out in the pace analysis above.
The DLD register records a completion date of 31 December 2024 for project 2350, which had lapsed 609 days before the 01 September 2026 inspection recorded 100% and a Completed status. Construction itself is complete, with the Building Completion Certificate issued by TKS on 14 January 2026, while handover is scheduled for Q3 2026 and each unit's date is set by Select Group. The register still showed the 31 December 2024 date at the latest reading, and this page's record is updated when the register changes.
Three approvals are on record for Six Senses Residences The Palm: DCD on 05 November 2025, LPG on 11 December 2025, and the Building Completion Certificate issued by TKS (Ports, Customs and Free Zone Corporation) on 14 January 2026. All three predate the first dated reading in this record, 97.86% on 05 May 2026, so the completion certificate was already held while the hotel building packages were being closed out.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Six Senses Residences The Palm construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.