Amazonia at Al Jaddaf Waterfront by Palladium Developments in Al Jaddaf Waterfront construction updates cover image featuring project renderings of the residential tower from front and angled exterior views in Dubai - Presented by Tohid Fetrat

Palladium Developments · Al Jaddaf Waterfront

Amazonia at Al Jaddaf Waterfront Construction Updates

The Register Record of a 12-Storey Waterfall Tower Beside Dubai Creek

Amazonia at Al Jaddaf Waterfront stood at 0.02% in the DLD register on 29 June 2026, opening the dated record for a 12-storey creekside tower at mobilization.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0.02%Construction Progress
29 June 2026Latest RERA Inspection
75 residencesTotal Units
Project 3595DLD Registration

Construction Snapshot

Amazonia at Al Jaddaf Waterfront at a Glance

Amazonia at Al Jaddaf Waterfront is a single tower of 75 residences by Palladium Developments facing Dubai Creek in Al Jaddaf, with handover expected in Q3 2027. DLD project 3595 was registered and its construction start dated on the same day, 20 October 2025, and the first dated register reading arrived 252 days later: 0.02% on 29 June 2026, with the site recorded at mobilization. Because the whole build is one 12-storey structure crowned by a waterfall the developer sets at the 12th floor, every reading from here measures that one tower climbing, not a spread of phases or plots, which is what makes this record straightforward to follow.

DLD Project Number

3595

Project Status

Active

Construction Start

20 October 2025

Total Units

75 residences

Total Built-Up Area

6,335.94 sq m

Registered Completion Date

30 October 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Amazonia at Al Jaddaf Waterfront Construction Update Timeline

So far the Amazonia record holds one dated reading: 0.02% in the DLD register on 29 June 2026, logged against an earlier inspection that the register view lists at 0% without a date. That places the single labelled dot on the track below almost on the start line, 252 days after the 20 October 2025 registered start, and gives the table one row, linked to the full June 2026 update.

Inspection MonthConstruction ProgressInspection DateFull Update
June 20260.02%29 June 2026View the June 2026 update

Pace Analysis

How Fast Amazonia at Al Jaddaf Waterfront Has Been Built

With one dated reading and one undated baseline, Amazonia has no measured pace yet. What its record does support is a position and a distance:

  • Previous inspection (undated) to 29 Jun 2026: 0% to 0.02%No measured pace: the earlier reading carries no date
  • 29 Jun 2026 to the registered completion date of 30 Oct 2027: 99.98 points over 488 daysAbout 6.15 points per 30-day month (arithmetic, not a forecast)

A pace curve for Amazonia will eventually trace one 12-storey tower moving out of mobilization into excavation, structure, and its waterfall facade, and that curve cannot be drawn from a single point. The 0.02% of 29 June 2026 is a position rather than a rate, and the move off the undated 0% has no time span to divide by. The 6.15 figure is plain arithmetic across the 488 days from that reading to the registered completion date of 30 October 2027, a scale marker for the distance still to be logged on the register, not a forecast of any schedule. For an end user, the signal worth watching is the date of the next dated reading; for an investor weighing an early entry, it is the first pair of dated readings, because that is where a measured pace for this tower begins.

Get the Next Inspection Figure First

Tell me you are tracking Amazonia at Al Jaddaf Waterfront and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Amazonia at Al Jaddaf Waterfront at Al Jaddaf

The 0.02% reading of 29 June 2026 only means something next to what is planned for the plot. The full project guide sets out what this record is tracking toward:

Amazonia at Al Jaddaf Waterfront rooftop terrace with lounge seating, palm trees, and waterfall feature in Dubai Presented by Tohid Fetrat

Amazonia at Al Jaddaf Waterfront: A Tower with a Facade Waterfall

Amazonia at Al Jaddaf Waterfront is a 12-storey Palladium tower of 75 apartments, with greenery on the facade and a waterfall.

View the Amazonia at Al Jaddaf Waterfront Project Guide

Considering a Pre-Construction Entry?

With a time-linked 60/40 plan behind every Amazonia purchase, entering now starts your instalment calendar while the register still shows the 0.02% of 29 June 2026. Availability moves as units sell, so ask me for the current picture rather than relying on any figure published earlier.

Ask About Remaining Availability on WhatsApp

Stage Record

Amazonia at Al Jaddaf Waterfront Build Stages, Mapped to the Inspections

Each stage below is tied to what the Amazonia record actually shows: two stages carry dates from registration and the 29 June 2026 inspection, and the three after them stay marked as not yet recorded until a dated reading reaches them.

20 Oct 2025

Registration and Construction Start

DLD project 3595 was registered and its construction start recorded on the same date, 20 October 2025, opening the Amazonia record at Al Jaddaf Waterfront.

Current PhaseTo 29 Jun 2026, 0.02% at last reading

Site Mobilization

The 29 June 2026 inspection found mobilization progressing on site, with a Progress Status of Pre-Construction - Progressing and 0.02% in the DLD register.

Not yet recorded

Excavation and Foundations

No dated reading has yet recorded excavation or foundation works for the single Amazonia tower; the next register entries will show when this stage opens.

Not yet recorded

Twelve-Storey Structure, Facade, and Waterfall

The frame of all 12 storeys, then the planted facade and the waterfall the brochure places at the 12th floor, followed by fit-out of the 75 residences.

Expected handover Q3 2027

Completion and Handover

Commissioning, final inspections, and handover of the 75 residences, expected in Q3 2027; this stage opens only as the register approaches 100%.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Amazonia at Al Jaddaf Waterfront's own record.

Buyer Position

Tracking Your Position at Amazonia at Al Jaddaf Waterfront

This page is one of four project resources that together cover a Amazonia at Al Jaddaf Waterfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Amazonia at Al Jaddaf Waterfront by Palladium Developments in Al Jaddaf Waterfront construction updates cover image featuring project renderings of the residential tower from front and angled exterior views in Dubai - Presented by Tohid Fetrat
You Are Here

Amazonia at Al Jaddaf Waterfront Construction Updates

This page: the DLD register record for Amazonia, from its 20 October 2025 start toward handover.

Amazonia at Al Jaddaf Waterfront by Palladium Developments in Al Jaddaf Waterfront Golden Visa graphic with a gold visa card beside a project rendering of the residential tower in Dubai - Presented by Tohid Fetrat

Amazonia at Al Jaddaf Waterfront Golden Visa: One Creekside Tier

Palladium's Amazonia at Al Jaddaf Waterfront, 75 residences on Dubai Creek, qualifies only at the 3 bedroom apartment.

Read the Amazonia at Al Jaddaf Waterfront Golden Visa Guide
Amazonia at Al Jaddaf Waterfront by Palladium Developments in Al Jaddaf Waterfront escrow account protection graphic with shield and padlock icons above the project building entrance rendering in Dubai - Presented by Tohid Fetrat

Amazonia at Al Jaddaf Waterfront: Palladium's Abu Dhabi Islamic Bank Escrow

Amazonia at Al Jaddaf Waterfront, DLD project 3595, escrows 76 units at Abu Dhabi Islamic Bank, 0.02% certified June 2026.

Verify the Amazonia at Al Jaddaf Waterfront Escrow Account

Approaching Handover

Between 0.02% and Handover: What Amazonia at Al Jaddaf Waterfront Buyers Should Do Now

At 0.02% on 29 June 2026, the Amazonia record shows a site at mobilization, with excavation, foundations, and the 12-storey frame all still ahead. Because the plan is time-linked, the 10% instalments due one and two months after purchase and the recurring 5% every second month arrive on your calendar whatever the next reading says, so the three steps below belong before your next transfer, not after it.

First, confirm that every instalment lands in the project's trust account with Abu Dhabi Islamic Bank by checking project 3595 on the Amazonia escrow account page before you transfer anything further.

Second, if residency is part of the plan, check whether your unit type reaches the threshold in the Amazonia Golden Visa guide; at Amazonia only the three bedroom tier does, which shapes the unit you commit to now.

Third, follow the dated record rather than marketing timelines: the Amazonia June 2026 construction update holds the first dated reading, and each later inspection will add a row to the timeline above.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

A tower at its first dated reading is best judged against what already stands around it. These three pages set the Amazonia record in its market, community, and developer context:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Palladium Development Dubai waterfront modern architecture with curved balcony and serene sunset water view Presented by Tohid Fetrat

Palladium Development: A Boutique Developer From Grandala to Amazonia

Palladium, founded in 2022, focuses on design driven residential and hospitality projects from Jumeirah Garden City to Al Jaddaf.

View the Palladium Development Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Amazonia at Al Jaddaf Waterfront Construction Updates Frequently Asked Questions

Amazonia at Al Jaddaf Waterfront is an active DLD-registered project (number 3595) at the pre-construction stage, with a DLD register reading of 0.02% on 29 June 2026, when the inspection recorded mobilization progressing on site. The full record is in the Amazonia inspection timeline above.

The DLD register reading of 29 June 2026 put Amazonia at 0.02%, up 0.02 of a point from the previous inspection shown at 0% (undated in the register view). The Independent Progress Monitoring Report issued for that inspection gave a Progress Status of Pre-Construction - Progressing; the reading is set out in full in the Amazonia June 2026 inspection record.

The DLD record for project 3595 shows a registered completion date of 30 October 2027, and the expected handover for Amazonia is Q3 2027. Both dates are shown here as recorded; the latest register reading behind them is 0.02% on 29 June 2026, and this page is updated when each new dated reading appears.

Amazonia is planned as 75 residences, from studios to three bedroom apartments, in a single 12-storey Palladium Developments tower in Al Jaddaf Waterfront. At the DLD register reading of 0.02% on 29 June 2026, none of that structure had yet been recorded; the site was at mobilization.

The DLD register dates the Amazonia construction start to 20 October 2025, the same day project 3595 was registered. The first dated register reading followed 252 days later, at 0.02% on 29 June 2026.

From the 0.02% DLD register reading of 29 June 2026, 99.98 percentage points remain. Spread across the 488 days to the registered completion date of 30 October 2027, that is about 6.15 points per 30-day month, which is arithmetic, not a forecast; the Amazonia pace analysis above shows the working.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Amazonia at Al Jaddaf Waterfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.