Luxury residential entrance and landscaped drop-off area at Bay Grove Residences Phase 1 featured on the April 2026 construction update page in Dubai Presented by Tohid Fetrat

Nakheel · Dubai Islands · Construction Update

Bay Grove Residences Phase 1 Construction Update - April 2026

April 2026 Inspection Records Bay Grove Residences Phase 1 at 3.7% as Piling Continues on Dubai Islands

Enabling and piling works were progressing at Bay Grove Residences Phase 1 when the 28 April 2026 inspection placed its Dubai Land Department register reading at 3.7%.

Direct advisor access. Every message answered personally, never by a call center.

3.7%DLD Register Reading
28 April 2026Inspection Date
September 2028Scheduled Handover
3293DLD Project Number

Dated DLD Register Data

Bay Grove Residences Phase 1 Construction Snapshot

A 2.49 point rise from the dated 1.21% reading of 26 January 2026 keeps Phase 1 inside the enabling and foundations band, with piling still recorded as progressing and the register showing its largest single move in the Phase 1 record so far.

Project Name

Bay Grove Residences Phase 1 by Nakheel

Project Number

3293

Project Status

Active

Construction Progress

3.7%

Inspection Date

28 April 2026

Construction Start

22 December 2024

Total Units

296 residential units

Total Built Area

40,086.68 sq m

Expected Completion

15 March 2028

Data source: the Dubai Land Department project register (Dubai REST, listed as "Bay Grove Residences, Dubai Islands"), showing 3.7% current progress and 1.21% at the previous inspection for the entry dated 28 April 2026, read together with the Independent Progress Monitoring Report of that date. This page is a record of that inspection: the reading was 150 days old when the page was prepared in September 2026, and the following reading sits on the July 2026 update. The hero shows developer project imagery, not the site as inspected. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: April 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Bay Grove Residences Phase 1 Construction Progress Summary

From the 26 January 2026 inspection to the 28 April 2026 inspection, Phase 1 went from 1.21% to 3.7% in the Dubai Land Department project register: 2.49 points in 92 days, about 0.81 points per 30-day month by simple arithmetic on the two dated readings, not a forecast. The earlier interval, June 2025 to January 2026, measured about 0.16 points a month, and the monitoring report status held at Enabling Works - Progressing through both of the 2026 inspections.

On Record
  • Construction start in the DLD register: 22 December 2024
  • Dated baseline of 0% on 17 June 2025
  • First reading above zero: 1.21% on 26 January 2026, with shoring and piling listed
In Progress at 3.7%
  • Enabling works progressing, per the 28 April 2026 monitoring report
  • Piling works progressing on site
  • Status unchanged since January: Enabling Works - Progressing
  • Three inspection photographs filed with the 28 April 2026 entry
Ahead of Handover
  • Foundations for the one combined basement beneath all four buildings
  • Superstructures from Building 03 at B+G+7+R to Building 04 at B+G+20+R
  • Registered completion 15 March 2028; handover scheduled for September 2028
Next inspectionEntered in the DLD project register after the next RERA site visit; in this record the following dated reading is covered on the July 2026 update.
Completion targetThe DLD record gives 15 March 2028 as the registered completion date, 687 days after this inspection; Nakheel schedules handover for September 2028.
Remaining distance96.3 percentage points lay between the 28 April 2026 reading and 100%.

Payment Linked Progress

What 3.7% Progress Means for Bay Grove Residences Phase 1 Buyers

The Phase 1 launch schedule of record runs on the calendar: its fourth instalment was set for March 2026, a month before this inspection, and its fifth for July 2026, whatever the register showed in between. At 3.7%, four checks keep payments and paperwork in line with that schedule.

Before the July 2026 Instalment

Verify the escrow account

With the launch schedule placing a 10% instalment in July 2026, each transfer should reach only the DLD regulated escrow account for project 3293 held at First Abu Dhabi Bank. Bay Grove Residences Phase 1 escrow account verification is the step before paying; the lookup takes about two minutes against the official DLD project record.

Before Your Next Due Date

Reread your SPA payment schedule

Set the dates in your sale and purchase agreement beside the launch schedule of record, which runs from its March 2026 instalment to one set for July 2026, and confirm how the agreement defines the September 2028 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.

After Booking

Confirm your Oqood entry

Oqood is the DLD's interim register entry for an off plan unit. A launch-period purchase should already appear under project 3293; on a new booking, ask when the entry will be issued, then match its unit number and price to your SPA before the next dated instalment.

Every Cycle

Watch for the move to foundations

Enabling and piling were listed in both the January and April 2026 reports; later readings will show whether foundation works enter the record. Bay Grove Residences Phase 1 construction updates hub lines up every dated reading with its measured pace.

General framework, not legal advice: instalment dates, registration steps, and handover notice terms are fixed by your own SPA and the DLD record, and both should be read directly.

Buying at 3.7%?

At 3.7%, the works on record at Phase 1 are enabling and piling, the groundwork beneath the future buildings, which leaves the full superstructure ahead and the widest spread of layouts, levels and outlooks across the four buildings. Every payment goes to the DLD-registered escrow account for project 3293, released against inspected construction progress.

Entering at 3.7%
  • Register reading of 3.7% on 28 April 2026, enabling and piling progressing
  • Registered completion date 687 days after this inspection; handover in September 2028
  • The final 30% of the launch schedule falls due at handover
Typical Late Stage Entry
  • Frame and facade standing and inspected before you commit
  • Months, not years, between purchase and keys
  • A thinner choice of remaining layouts and floors
AED 1.85M ≈ USD 504KStarting Price
70/30 Launch Schedule30% Due on Handover
September 2028Scheduled Handover
Ask What Is Available at Bay Grove Residences Phase 1

Availability is not part of the DLD record and changes between cycles; the units still open and the terms for a new booking are confirmed at reservation and set in the SPA.

About the Development

Bay Grove Residences Phase 1 Project Details

Bay Grove Residences Phase 1 beachfront exterior view of the waterfront apartments on Island B at Dubai Islands Presented by Tohid Fetrat
Dubai Islands · Nakheel

At the April 2026 inspection, Phase 1 was a piling-stage site: enabling and piling works were progressing beneath what will become one combined basement and four buildings holding 296 residential units, from 1 bedroom apartments to 4 bedroom penthouses. Starting prices: AED 1.85M ≈ USD 504K.

Buying at this point means waiting through every superstructure, from Building 03 at B+G+7+R to Building 04 at B+G+20+R, in return for an early pick of floors and orientation, with handover scheduled by Nakheel for September 2028.

Bay Grove Residences Phase 1 by Nakheel Project Guide

Site Context This Cycle

Explore Bay Grove Residences Phase 1 Location on Dubai Map

Phase 1 stands on plot 3031, the first plot reached on arrival at Island B, in the island's Marina district facing Crystal Beach, which the developer fact sheet gives a length of 500 m. The four buildings are planned at angles that open their views to the water, with a promenade between them and the sand, so the piling recorded in April 2026 is the groundwork beneath those orientations and the single shared basement.

Island B is among the Dubai Islands closest to the mainland, and the developer brochure links the islands to the city through the new access bridge and Infinity Bridge; the fact sheet times Dubai International Airport at 18 minutes and Downtown Dubai at 26. For a buyer reading the April 2026 record, the location can be judged on those links now, while the homes themselves remain a September 2028 handover. Locate the plot on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Bay Grove Residences Phase 1 on Dubai Map

Buyer Resources for This Project

Investing in Bay Grove Residences Phase 1 While Piling Progresses

At 3.7% the questions worth settling are the ones a long build raises: which account receives each dated instalment, and which Phase 1 tiers support residency. Each card below is set against the April 2026 record.

Bay Grove Residences Phase 1 waterfront towers and lagoon-style beachfront community featured on the construction updates page in Dubai Presented by Tohid Fetrat
You Are Here

Bay Grove Residences Phase 1 Construction Updates

This page: the 28 April 2026 register entry, recording Phase 1 at 3.7% during piling.

Bay Grove Residences Phase 1 waterfront community with UAE Golden Visa concept featured in Dubai Presented by Tohid Fetrat

Bay Grove Residences Phase 1 Golden Visa: 296 Island B Units

Nakheel's Bay Grove Residences Phase 1 on Island B qualifies at 2 and 3 bedroom apartments and the 4 bedroom penthouse.

Read Bay Grove Residences Phase 1 Golden Visa Guide
Bay Grove Residences Phase 1 waterfront residence with escrow account security concept in Dubai Presented by Tohid Fetrat

Bay Grove Residences Phase 1 Escrow: Nakheel's Island B Account

Bay Grove Residences Phase 1, DLD project 3293, escrows 296 units at First Abu Dhabi Bank, certified 6.6% in July 2026.

Verify Bay Grove Residences Phase 1 Escrow Account

Update Timeline

Other Bay Grove Residences Phase 1 Construction Updates

April 2026 is the third dated entry in the Phase 1 record, following the January 2026 reading and preceding the July 2026 inspection.

All Bay Grove Residences Phase 1 Construction Updates

FAQs

Bay Grove Residences Phase 1 Construction Progress in April 2026: Frequently Asked Questions

The Dubai Land Department project register recorded 3.7% for Bay Grove Residences Phase 1 (project 3293) at the inspection dated 28 April 2026, and it shows 1.21% as the previous inspection, the reading dated 26 January 2026. The change is 2.49 points over 92 days, the largest step between dated readings in the Phase 1 record up to that date.

The register record supplied with this entry lists a registered completion date of 15 March 2028, 687 days after the 28 April 2026 inspection, and Nakheel's payment schedule estimates construction completion for September 2028, the scheduled handover. That register view was captured in September 2026, so the date shown on 28 April 2026 itself should be confirmed on Dubai REST. A registered date can change from one inspection cycle to the next, and a buyer's binding handover terms are set by the individual sales and purchase agreement.

The Independent Progress Monitoring Report dated 28 April 2026 records that enabling and piling works were progressing, while the 26 January 2026 report had also listed shoring. The April report gives no reason for the difference and does not say whether shoring was finished, paused or simply not noted, so no conclusion is drawn here. Both reports carry the same status, Enabling Works - Progressing.

From 26 January to 28 April 2026 the register moved 2.49 points in 92 days, about 0.81 points per 30-day month. From 17 June 2025 to 26 January 2026 it moved 1.21 points in 223 days, about 0.16 points a month, a stretch that opened with the June 2025 report showing Pre-Construction - On Hold. Both figures are simple arithmetic on dated readings, not forecasts, and every dated interval is set out on the Bay Grove Residences Phase 1 construction updates hub.

On a piled site the usual order is to finish and test the piles, excavate to formation level, trim the pile heads, and then cast pile caps or a raft slab that ties them together; where a combined basement is planned, basement excavation and waterproofing also fall in this stretch. The April 2026 report does not describe any of these steps at Phase 1, so this is the general sequence of work, not a record of the site. The next dated reading is covered on the Bay Grove Residences Phase 1 July 2026 construction update.

Nakheel's launch payment schedule of record set a 10% fourth instalment for March 2026, a month before the 28 April 2026 inspection, and a 10% fifth instalment for July 2026. Those dates are calendar-based rather than tied to register readings, so the 3.7% figure did not move them. The schedule is the launch record, not a current offer: the dates and amounts that bind a buyer are those in the individual sales and purchase agreement.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Bay Grove Residences Phase 1 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.