Bay Grove Residences Phase 1 waterfront towers and lagoon-style beachfront community featured on the construction updates page in Dubai Presented by Tohid Fetrat

Nakheel · Dubai Islands

Bay Grove Residences Phase 1 Construction Updates

A Dated Groundwork Record Where Island B Meets Crystal Beach

Bay Grove Residences Phase 1 reached 6.6% in the DLD register on 21 July 2026, a fourth dated reading tracing groundwork on Island B's Crystal Beach plot.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.6%Construction Progress
21 July 2026Latest RERA Inspection
296 residential unitsTotal Units
Project 3293DLD Registration

Construction Snapshot

Bay Grove Residences Phase 1 at a Glance

Bay Grove Residences Phase 1 is Nakheel's 296-residence beachfront phase on Island B of Dubai Islands: four buildings, from B+G+7+R up to B+G+20+R, planned above one shared basement and one shared ground level. Nineteen months separate its 22 December 2024 recorded construction start from the 6.6% register reading of 21 July 2026, and none of the four inspection reports in that span singles out a building; each describes enabling, shoring, piling or foundation works on the site as a whole, which is what a single combined base for four towers of different heights looks like at this point in the record.

DLD Project Number

3293

Project Status

Active

Construction Start

22 December 2024

Total Units

296 residential units

Total Built-Up Area

40,086.68 sq m

Registered Completion Date

15 March 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Bay Grove Residences Phase 1 Construction Update Timeline

Four inspections carry a dated register figure for Phase 1: a 0% baseline on 17 June 2025, the first move off zero to 1.21% on 26 January 2026, 3.7% on 28 April 2026 and 6.6% on 21 July 2026. The longest wait in the record comes first, 223 days between the opening two readings, while both later intervals run under 100 days. Each dot on the track below is one of those readings, and each table row links its full monthly update with the report notes for that date.

Inspection MonthConstruction ProgressInspection DateFull Update
July 20266.6%21 July 2026View the July 2026 update
April 20263.7%28 April 2026View the April 2026 update
January 20261.21%26 January 2026View the January 2026 update
June 20250%17 June 2025View the June 2025 update

Pace Analysis

How Fast Bay Grove Residences Phase 1 Has Been Built

Four dated readings give Phase 1 three measured intervals. Each figure below is simple arithmetic on two register readings, using a 30-day month, and none of it is a forecast:

  • Jun 2025 to Jan 2026: baseline to enabling works, 0% to 1.21% over 223 daysAbout 0.16 points per month
  • Jan 2026 to Apr 2026: enabling and piling, 1.21% to 3.7% over 92 daysAbout 0.81 points per month
  • Apr 2026 to Jul 2026: piling into foundations, 3.7% to 6.6% over 84 daysAbout 1.04 points per month

Read as a curve, the Phase 1 record gets steeper at every step: each interval is shorter than the one before it and adds more points, from 1.21 points across the 223-day opening gap to 2.90 points in the 84 days to 21 July 2026. Counted from the 22 December 2024 recorded start, the whole build averages about 0.34 points a month over 576 days. On 21 July 2026 the register still stood 93.4 points short of 100%, 603 days before its 15 March 2028 registered completion date, with the September 2028 handover beyond it; those figures sit side by side here as recorded arithmetic, not as a projection of either date. For an end user planning a move or an investor weighing exit timing, the useful signal at 6.6% is direction rather than level: three rising intervals, all of them groundwork, with the shared basement and the four superstructures still to enter the reports.

Get the Next Inspection Figure First

Tell me you are tracking Bay Grove Residences Phase 1 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Bay Grove Residences Phase 1 at Island B

A register reading is only half the story without the building it is counting toward. The full project guide describes what Phase 1 buyers are waiting on while this record fills in:

Bay Grove Residences Phase 1 beachfront exterior view of the waterfront apartments on Island B at Dubai Islands Presented by Tohid Fetrat

Bay Grove Residences Phase 1, Four Buildings Behind Crystal Beach

Bay Grove Residences Phase 1 is Nakheel's Island B address of 296 units in four buildings sharing an infinity pool.

View the Bay Grove Residences Phase 1 Project Guide

Considering an Early-Construction Entry?

Availability at Bay Grove Residences Phase 1 moves between inspection cycles, and an entry at this stage is chosen from plans rather than finished floors. If the record on this page is what brought you here, ask me what is currently open before the remaining choice narrows.

Ask About Remaining Availability on WhatsApp

Stage Record

Bay Grove Residences Phase 1 Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates in the Phase 1 record instead of a generic build sequence. Two stages are on record so far; the three after them come from the four-building configuration in the monitoring reports and carry no reading yet.

Oct 2024 to Jun 2025, 0% on 17 Jun 2025

Registration, Recorded Start and Baseline

Project 3293 entered the DLD register on 04 October 2024 with a recorded construction start of 22 December 2024; the first dated inspection, on 17 June 2025, set the baseline at 0%.

Current PhaseJan 2026 onward, 6.6% at last reading

Enabling, Piling and Foundation Works

Enabling, shoring and piling at 1.21% on 26 January 2026, enabling and piling at 3.7% on 28 April 2026, then foundation works added at 6.6% on 21 July 2026.

Not yet in the record

Combined Basement and Ground Level

One basement and one ground level shared by all four buildings, listed in every report's project description but not yet named in any inspection notes through 21 July 2026.

Ahead of handover

Four Superstructures, B+G+7+R to B+G+20+R

Buildings 01 to 04 are configured as B+G+8+R, B+G+13+R, B+G+7+R and B+G+20+R above the shared base; no register reading covers this stage yet.

15 Mar 2028 registered, Sep 2028 handover

Completion and Handover

Two end dates frame this stage: 15 March 2028 as the registered completion date in the DLD record, and September 2028, the month Nakheel's payment plan gives for completion and handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Bay Grove Residences Phase 1's own record.

Buyer Position

Tracking Your Position at Bay Grove Residences Phase 1

This page is one of four project resources that together cover a Bay Grove Residences Phase 1 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Bay Grove Residences Phase 1 waterfront towers and lagoon-style beachfront community featured on the construction updates page in Dubai Presented by Tohid Fetrat
You Are Here

Bay Grove Residences Phase 1 Construction Updates

This page: the Phase 1 register record, 0% in June 2025 to 6.6% in July 2026.

Bay Grove Residences Phase 1 waterfront community with UAE Golden Visa concept featured in Dubai Presented by Tohid Fetrat

Bay Grove Residences Phase 1 Golden Visa: 296 Island B Units

Nakheel's Bay Grove Residences Phase 1 on Island B qualifies at 2 and 3 bedroom apartments and the 4 bedroom penthouse.

Read the Bay Grove Residences Phase 1 Golden Visa Guide
Bay Grove Residences Phase 1 waterfront residence with escrow account security concept in Dubai Presented by Tohid Fetrat

Bay Grove Residences Phase 1 Escrow: Nakheel's Island B Account

Bay Grove Residences Phase 1, DLD project 3293, escrows 296 units at First Abu Dhabi Bank, certified 6.6% in July 2026.

Verify the Bay Grove Residences Phase 1 Escrow Account

Approaching Handover

Between 6.6% and Handover: What Bay Grove Residences Phase 1 Buyers Should Do Now

At 6.6% the Phase 1 record is still groundwork, while the launch payment schedule runs on a calendar of its own: by July 2026 it had called 65% of the price (20% on booking plus five dated instalments), against the 6.6% register reading of 21 July 2026. That is arithmetic on the launch schedule of record, not a statement about any buyer's payments, and your own SPA sets what you owe and when. The schedule's next dated instalment, 5%, falls in November 2026, so the three checks below belong before that month rather than after it.

First, match every instalment to the DLD-registered escrow account that First Abu Dhabi Bank holds for project 3293; the Bay Grove Residences Phase 1 escrow account page shows how to confirm it against the official record before a transfer.

Second, if residency is part of the plan, test your tier against the property threshold now: the one-bedroom entry price sits below it, and the Bay Grove Residences Phase 1 Golden Visa guide sets out which Phase 1 tiers qualify.

Third, read each new register figure against the dates in your SPA rather than the launch calendar alone; the Bay Grove Residences Phase 1 July 2026 construction update is the latest in the record and the first to name foundation works.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island B Structure

A record measured in groundwork reads differently beside what surrounds it. These three pages set the 6.6% reading of 21 July 2026 against the sister Bay Grove phases, Island B and Nakheel's portfolio:

Aerial masterplan view of Island B properties for sale at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island B: Seven Waterfront Projects by Nakheel, Ellington and Beyond

Island B, on the eastern side of Dubai Islands, is a villa and beachfront residence district with seven projects for sale.

See Island B Properties for Sale
Aerial view of Dubai Islands Island B with highlighted arrow showing location of residential district along the waterfront Presented by Tohid Fetrat

Island B Community Overview

Discover Island B within Dubai Islands, featuring waterfront residences, beach access, hospitality destinations, promenades, and planned lifestyle infrastructure by Nakheel.

Explore the Island B Community
Aerial masterplan view of Palm Jebel Ali by Nakheel showing the palm shaped island and the Dubai waterfront skyline at sunset Presented by Tohid Fetrat

Nakheel: The Master Developer of Dubai's Island Living and Reclaimed Coastline

Founded in 2003, Nakheel created Palm Jumeirah and Dubai Islands, adding over 300 kilometers of coastline and building complete waterfront communities.

View the Nakheel Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Bay Grove Residences Phase 1 Construction Updates Frequently Asked Questions

Bay Grove Residences Phase 1 is an active DLD-registered project (number 3293) standing at 6.6% in the Dubai Land Department project register as of the inspection dated 21 July 2026, the newest reading in the record behind this page. Its monitoring report of the same date names three activities under way: enabling, piling and foundation works. Every dated reading is in the inspection timeline above.

Four dated readings are on record for Bay Grove Residences Phase 1: 0% on 17 June 2025, 1.21% on 26 January 2026, 3.7% on 28 April 2026 and 6.6% on 21 July 2026. The July 2026 figure is up 2.90 points on the April 2026 reading, the biggest single move the record has shown. The reading it grew from is covered in the Bay Grove Residences Phase 1 April 2026 construction update.

By simple arithmetic on its dated register readings, Bay Grove Residences Phase 1 has sped up across all three intervals: about 0.16 points per month from June 2025 to January 2026 (1.21 points in 223 days), about 0.81 from January to April 2026 (2.49 points in 92 days) and about 1.04 from April to July 2026 (2.90 points in 84 days). From the 22 December 2024 recorded start to the 6.6% reading of 21 July 2026, the average is about 0.34 points a month. These are measured figures, not a forecast; the working is in the pace analysis above.

No. The DLD register gives Bay Grove Residences Phase 1 a registered completion date of 15 March 2028, which lay 603 days after the 6.6% reading of 21 July 2026 and was still ahead when this page was prepared in September 2026. Handover is scheduled for September 2028, the month Nakheel's payment plan gives for construction completion. The dates that bind an individual buyer are the ones written into that buyer's sale and purchase agreement.

Bay Grove Residences Phase 1 holds 296 residential units, the figure shown in the DLD register and in every monitoring report, across four buildings configured as B+G+8+R, B+G+13+R, B+G+7+R and B+G+20+R above one combined basement and one combined ground level. The mix covers 1, 2 and 3 bedroom apartments and 4 bedroom penthouses, with layouts in the Bay Grove Residences Phase 1 layouts and project details.

The Independent Progress Monitoring Reports filed for Bay Grove Residences Phase 1 print a Progress Status label and inspection notes, not a percentage, so every figure on this page is the DLD project register reading for the same inspection date, listed on Dubai REST as "Bay Grove Residences, Dubai Islands". On 21 July 2026 the two sources read 6.6% in the register and Enabling Works - Progressing in the report, the label also used in January and April 2026.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Bay Grove Residences Phase 1 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status