Emaar Properties · Emaar Beachfront · Construction Update
Bayview by Address Resorts Construction Update - October 2024
October 2024 Inspection Records Bayview by Address Resorts at 9.08% with Enabling Works Completed and Piling Under Way at Emaar Beachfront
Enabling works were complete and piling and foundation works under way at Bayview by Address Resorts when the 08 October 2024 inspection recorded 9.08%, up from 2.86%.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Bayview by Address Resorts Construction Snapshot
A 6.22 point rise since the 26 April 2024 reading is the largest gain in the Bayview by Address Resorts record so far, and it leaves the project 0.92 points below 10%, the construction completion level that the 2023 schedule ties to its first progress-linked instalment.
Bayview by Address Resorts
2646
Active
9.08%
08 October 2024
15 October 2023
676 residential units
84,972.40 sq m
July 2028
Data source: RERA inspection conducted on 08 October 2024, tracked against DLD inspection records and the Independent Progress Monitoring Report filed for that visit; the reading before it was 2.86% on 26 April 2024. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. As of 24 September 2026 this reading is 716 days old, and every later reading is listed on the Bayview by Address Resorts construction updates record. The kiteboarding scene at the top of this page is a project rendering, not a site photograph. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Bayview by Address Resorts Construction Progress Summary
Between the 26 April 2024 and 08 October 2024 inspections, Bayview by Address Resorts moved from 2.86% to 9.08%, a 6.22 point gain over 165 days, or about 1.13 points per month, against about 0.69 points per month across the pair before it. The IPMR Progress Status held at "Enabling Works - Progressing", yet its notes changed in substance: enabling works are now recorded as completed, and piling and foundation works are named as ongoing while mobilization continues on plot 3648.
- DLD project registration, dated 29 May 2023
- Registered construction start of 15 October 2023, 359 days before this inspection
- Enabling works, recorded as completed in the October 2024 IPMR
- Piling and foundation works, recorded as ongoing in the October 2024 IPMR
- Mobilization, which the same report records as still going on
- RERA photographs of clustered steel reinforcement rising from a wide excavation, a shored retaining wall, and block-walled pits braced with yellow scaffolding
- 10% construction completion, 0.92 points above this reading and the trigger for the 5th instalment on the 2023 schedule
- Above-ground works for the two towers over a shared podium (Tower 1: Ground + 49 floors; Tower 2: Ground + 34 floors), per the IPMR
- Handover in July 2028, set against a registered completion date of 31 July 2028
Payment Linked Progress
What 9.08% Progress Means for Bayview by Address Resorts Buyers
At 9.08% Bayview by Address Resorts sat just under the 10% construction completion that the 2023 schedule links to its 5th instalment, the first payment set by construction rather than by a calendar date, while the dated February 2025 instalment was the next one due. With piling and foundations under way, four actions matter most.
Verify the escrow account
The 5% 3rd instalment, dated August 2024, fell two months before this inspection, which left the 5% 4th instalment of February 2025 as the next calendar payment; it goes only to the DLD regulated escrow account registered for project 2646, which the October 2024 IPMR places with Abu Dhabi Commercial Bank. Bayview by Address Resorts escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Confirm how the 10% trigger is evidenced
With the record 0.92 points short of 10%, find the clause in your sale and purchase agreement and Oqood entry that says whose figure confirms the trigger and what notice follows it, since the 2023 schedule dates that instalment only as an estimate. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Note the furnished handover scope
The piles going in now will carry homes that are to arrive fully furnished under the Address Resorts brand, so the eventual handover inspection reaches furniture and fitted furnishings as well as finishes, joinery, and glazing. Bayview by Address Resorts snagging inspection guide sets out that scope well ahead of the handover date.
Watch for the 10% crossing
The reading after this one shows whether piling and foundation works carried the record past the 10% mark where construction-linked instalments begin. Bayview by Address Resorts construction updates keeps every dated reading in order.
General framework, not legal advice: the wording of each construction trigger, the dates of the calendar instalments, and the 4% DLD registration fee all sit in your own SPA and in the DLD record, so read both directly.
Buying After the October 2024 Reading?
The 9.08% reading of 08 October 2024 is 716 days old today, so a purchase now enters at the latest DLD reading rather than just below the 10% trigger, and any instalment dated before your purchase is settled on the developer's current terms. Every payment goes to the DLD-registered escrow account for project 2646, released against construction progress recorded in the DLD register.
- 9.08% recorded on 08 October 2024, with enabling works completed and piling ongoing
- One calendar instalment left ahead, February 2025, before the construction-linked run
- 0.92 points short of the 10% trigger for the first construction-linked instalment
- More dated readings on record to weigh before signing
- Instalments already dated in the past settled on the developer's current terms
- Less time between signing and the July 2028 handover
3+ Units Available listed on the project page as of September 2026; availability shifts between cycles.
About the Development
Bayview by Address Resorts Project Details

At 9.08% on 08 October 2024, with enabling works completed and piling under way, Bayview by Address Resorts was still a below-ground project of 676 branded, fully furnished residences, from 1 bedroom apartments to 6 bedroom penthouses, on two towers sharing one podium. Starting prices: AED 3.30M ≈ USD 899K.
A buyer entering at this reading faced about three years and ten months to handover in July 2028, with the February 2025 calendar instalment and all six construction-linked instalments of the 2023 schedule still ahead, the first of them at 10%.
Bayview by Address Resorts Project GuideSite Context This Cycle
Explore Bayview by Address Resorts Location on Dubai Map
On plot 3648, listed by the IPMR under the Marsa Dubai location inside Emaar Beachfront, the 08 October 2024 photographs show one long excavation running the length of the site, edged on one side by a shored concrete retaining wall under orange safety mesh and overlooked by finished residential towers just past the boundary, so piling and foundations for both towers and the shared podium were being carried out below grade in a confined waterfront footprint.
Beyond the hoarding, the project brochure describes about 2 km of beach across Emaar Beachfront and drive times of about 15 minutes to Downtown Dubai, 20 minutes to Al Fahidi District, and 30 minutes to Al Maktoum International (DWC), so a buyer at the piling stage was waiting on the towers themselves, not on the district's roads or services. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Bayview by Address Resorts During Piling and Foundation Works
At 9.08% the construction record sat just below the point where it starts to set payment dates on the 2023 schedule, which makes residency, escrow protection, and the furnished handover scope worth settling. Each resource below is matched to Bayview by Address Resorts at that reading.

Bayview by Address Resorts Construction Updates
This page: Bayview by Address Resorts at 9.08% on 08 October 2024, with piling under way.

Bayview by Address Resorts at Emaar Beachfront Golden Visa: Six Tiers
Emaar's 676-residence Bayview by Address Resorts at Emaar Beachfront qualifies at every tier from the 1 bedroom to 6 bedroom penthouse.
Read Bayview by Address Resorts Golden Visa Guide
Bayview by Address Resorts at Emaar Beachfront: Its Escrow Account
Bayview by Address Resorts at Emaar Beachfront, DLD project 2646: Abu Dhabi Commercial Bank escrow, 63.02% certified September 2026.
Verify Bayview by Address Resorts Escrow Account
Bayview by Address Resorts at Emaar Beachfront Snagging for Furnished Homes
Bayview by Address Resorts at Emaar Beachfront is Emaar Properties' fully furnished, branded development: 676 residences in two towers.
Read Bayview by Address Resorts Snagging GuideUpdate Timeline
Other Bayview by Address Resorts Construction Updates
October 2024 is the fourth dated reading for Bayview by Address Resorts; the April 2024 update before it records 2.86% as foundation works began, and the hub keeps every reading in date order.
Where This Update Fits
Explore Bayview by Address Resorts Structure
The October 2024 visit found piling under way on a single plot; the cards below widen the view to the Emaar Beachfront community, the developer running the works, and the listings a buyer would compare.

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Bayview by Address Resorts Construction Progress in October 2024: Frequently Asked Questions
The RERA inspection of 08 October 2024 recorded 9.08% construction progress for Bayview by Address Resorts, DLD project 2646, and the Independent Progress Monitoring Report (IPMR) filed for that visit keeps the Progress Status at "Enabling Works - Progressing". It is the fourth dated reading in the project's record and, as of 24 September 2026, it is 716 days old; every reading after it is listed by date on the Bayview by Address Resorts construction updates record.
Handover is July 2028, and the DLD register gives 31 July 2028 as the registered completion date, 1,392 days or about three years and ten months after the 08 October 2024 inspection. At that point 90.92 percentage points were still to be recorded, about 1.96 points per month if spread evenly, which is an arithmetic benchmark only and not a forecast. The register may revise the completion date between inspection cycles, so the entry current on the day of any payment decision is the one that counts.
The DLD register rose from 2.86% on 26 April 2024 to 9.08% on 08 October 2024, a 6.22 point gain over 165 days, about 1.13 points per month, compared with about 0.69 points per month between December 2023 and April 2024. The Progress Status stayed "Enabling Works - Progressing" across both visits, but the IPMR notes moved from enabling and foundation works progressing to enabling works completed, with piling and foundation works ongoing.
The October 2024 IPMR notes read: "At the time of inspection found: mobilization are on going, enabling works are completed and piling & foundations works are ongoing." The four inspection photographs filed with it show a long excavation dotted with clusters of upright steel reinforcement, a shored concrete retaining wall topped with orange safety mesh, block-walled pits braced with yellow scaffolding beside circular reinforcement cages, and crews in high-visibility vests, with finished towers standing beyond the site.
On 08 October 2024 the 9.08% figure marked the first IPMR in which Bayview's enabling works are described as completed, with the site's effort moved to piling and foundations, still entirely below ground level. It kept the project inside the 0 to 20% enabling and foundations band and 0.92 points below the 10% construction completion mark that the 2023 schedule attaches to its 5th instalment, the first one linked to construction.
On the 2023 launch schedule of record, the 5% 3rd instalment is dated August 2024, two months before the 08 October 2024 inspection, and the 5% 4th instalment dated February 2025 was the next by date. The 10% 5th instalment falls due upon 10% construction completion, with an estimated date of August 2025, and the 9.08% reading sat just below that trigger. Buyers entering today do so on the developer's current terms, and the 4% DLD registration fee is separate from the ten instalments.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the October 2024 inspection record for Bayview by Address Resorts at Emaar Beachfront correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.