Emaar Properties · Emaar Beachfront
Bayview by Address Resorts at Emaar Beachfront Construction Updates
Two Beachfront Towers Over One Podium, Read Across Ten Dated Inspections
Bayview by Address Resorts reached 63.02% on 14 September 2026, its two beachfront towers gaining nearly two thirds of that climb since the 03 October 2025 reading.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Bayview by Address Resorts at Emaar Beachfront at a Glance
Bayview by Address Resorts is the 676-residence branded development Emaar Properties is building on Emaar Beachfront, entered in the DLD register as project 2646, and its Independent Progress Monitoring Report (IPMR) describes two residential towers over a shared podium (Tower 1: Ground + 49 floors; Tower 2: Ground + 34 floors). The register's first reading for the plot, 0% on 08 May 2023, is dated 21 days before the 29 May 2023 registration and 160 days before the 15 October 2023 registered start, so this record opens ahead of both register dates and now runs to 63.02% on 14 September 2026 across ten dated inspections.
2646
Active
15 October 2023
676 residential units
84,972.40 sq m
31 July 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Bayview by Address Resorts at Emaar Beachfront Construction Update Timeline
Ten inspections make up this record, and each one names the reading before it as its previous inspection, so the chain runs without an undated link: 0% on 08 May 2023, when the plot still held another project's site offices, 0.02% on 25 December 2023 as an enabling contractor mobilized, 9.08% on 08 October 2024, 22.08% on 03 October 2025, then 34.62%, 48.92%, and 63.02% on 02 February, 30 June, and 14 September 2026. Each dot on the track is one inspection, each card and table row links that month's full update, and the IPMR Progress Status beside every reading shows the phase the inspection was filed under.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 63.02% | 14 September 2026 | View the September 2026 update |
| June 2026 | 48.92% | 30 June 2026 | View the June 2026 update |
| February 2026 | 34.62% | 02 February 2026 | View the February 2026 update |
| October 2025 | 22.08% | 03 October 2025 | View the October 2025 update |
| June 2025 | 18.01% | 19 June 2025 | View the June 2025 update |
| March 2025 | 14.16% | 09 March 2025 | View the March 2025 update |
| October 2024 | 9.08% | 08 October 2024 | View the October 2024 update |
| April 2024 | 2.86% | 26 April 2024 | View the April 2024 update |
| December 2023 | 0.02% | 25 December 2023 | View the December 2023 update |
| May 2023 | 0% | 08 May 2023 | View the May 2023 update |
Pace Analysis
How Fast Bayview by Address Resorts at Emaar Beachfront Has Been Built
Nine dated pairs sit inside the Bayview record, and their pace falls into three bands rather than one rate: a slow pre-construction and enabling start, a steady run of about one point per month into the main contract, and a step change after October 2025. Each figure below is the point change between two readings divided by the days between them, on a 30-day month:
- May 2023 to Dec 2023: pre-construction, 0% to 0.02%Under 0.01 points per month
- Dec 2023 to Apr 2024: mobilization and enabling works, 0.02% to 2.86%About 0.69 points per month
- Apr 2024 to Oct 2024: enabling works and piling, 2.86% to 9.08%About 1.13 points per month
- Oct 2024 to Mar 2025: piling into the main contract, 9.08% to 14.16%About 1.00 points per month
- Mar 2025 to Jun 2025: ground floor slab to completed substructure, 14.16% to 18.01%About 1.13 points per month
- Jun 2025 to Oct 2025: superstructure with internal works, 18.01% to 22.08%About 1.15 points per month
- Oct 2025 to Feb 2026: superstructure and external envelope, 22.08% to 34.62%About 3.08 points per month
- Feb 2026 to Jun 2026: envelope, finishes, and external works, 34.62% to 48.92%About 2.90 points per month
- Jun 2026 to Sep 2026: advanced superstructure and finishes, 48.92% to 63.02%About 5.57 points per month
Read as a curve, the record bends once. For its first 17 months the register moved from 0% to 9.08%, two thirds of that after the April 2024 reading, while the plot went from another project's site offices to finished enabling works with piling under way. The switch to Main Contract - Progressing on 09 March 2025 left the rate where it was: the pair ending at that reading and the two after it, through 03 October 2025, held between 1.00 and 1.15 points per month. The bend follows that reading, once envelope and internal works joined the superstructure: 40.94 points were logged in the 346 days to 14 September 2026, including the largest single gain, 14.30 points from February to June 2026, and the fastest and shortest interval, 76 days at about 5.57 points per month. For an owner waiting on July 2028 and an investor weighing an entry, what matters is that these are measured intervals between dated readings, each describing a stretch already built, not a rate carried forward.
Get the Next Inspection Figure First
Tell me you are tracking Bayview by Address Resorts at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Bayview by Address Resorts at Emaar Beachfront
A 63.02% reading on 14 September 2026 only means something next to what it is building toward: branded, fully furnished homes in two towers on Emaar Beachfront. The project guide covers that side of the purchase:

Bayview by Address Resorts at Emaar Beachfront: Furnished Twin Towers
Bayview by Address Resorts at Emaar Beachfront holds 676 fully furnished residences in two towers, with a private beach.
View the Bayview by Address Resorts at Emaar Beachfront Project GuideConsidering an Entry Before the July 2028 Handover?
Availability at Bayview by Address Resorts changes between inspection cycles, and the current count lives on the project page rather than here. If the ten-reading record on this page is what brought you here, ask me what is available now and on which payment terms before you compare other Emaar Beachfront towers.
Ask About Remaining Availability on WhatsAppStage Record
Bayview by Address Resorts at Emaar Beachfront Build Stages, Mapped to the Inspections
Each stage below is pinned to the inspections that recorded it and to the IPMR Progress Status filed with them, so the sequence reads from this plot's own paperwork: four status labels across ten readings, with the fifth stage still ahead of the 63.02% reading of 14 September 2026.
Pre-Construction and Mobilization
The 08 May 2023 inspection logged no building activity, with the plot holding site offices and stored materials for a different project; the register then dated registration to 29 May 2023 and the start to 15 October 2023, and by 25 December 2023 Bayview's own enabling contractor was appointed and mobilizing.
Enabling Works, Piling, and Foundations
Both 2024 inspections carried the status Enabling Works - Progressing: foundation work was moving by 26 April 2024 at 2.86%, and by 08 October 2024, at 9.08%, the enabling package was finished while piling and foundations went on.
Main Contract: Substructure to Superstructure
Main Contract - Progressing first appeared on 09 March 2025 at 14.16%, with the ground floor slab being reinforced; the substructure was logged as completed by 19 June 2025 at 18.01%, internal works joined on 03 October 2025 at 22.08%, and envelope works on 02 February 2026 at 34.62%.
Advanced Superstructure, Finishes, and External Works
External works entered the notes on 30 June 2026 at 48.92%, and on 14 September 2026, at 63.02%, the superstructure was progressing at advanced stages, substructure work was substantially completed, and internal, envelope, MEP, finishing, and external works were all running.
Completion and Handover
After the 14 September 2026 reading, 36.98 points separated Bayview from 100%, with a registered completion date of 31 July 2028 and handover set for July 2028; every reading logged between now and then is added to this record as a dated row.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Bayview by Address Resorts at Emaar Beachfront's own record.
Buyer Position
Tracking Your Position at Bayview by Address Resorts at Emaar Beachfront
This page is one of four project resources that together cover a Bayview by Address Resorts at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Bayview by Address Resorts at Emaar Beachfront Construction Updates
This page: ten dated Bayview readings, 0% in May 2023 to 63.02% in September 2026.

Bayview by Address Resorts at Emaar Beachfront Golden Visa: Six Tiers
Emaar's 676-residence Bayview by Address Resorts at Emaar Beachfront qualifies at every tier from the 1 bedroom to 6 bedroom penthouse.
Read the Bayview by Address Resorts at Emaar Beachfront Golden Visa Guide
Bayview by Address Resorts at Emaar Beachfront: Its Escrow Account
Bayview by Address Resorts at Emaar Beachfront, DLD project 2646: Abu Dhabi Commercial Bank escrow, 63.02% certified September 2026.
Verify the Bayview by Address Resorts at Emaar Beachfront Escrow Account
Bayview by Address Resorts at Emaar Beachfront Snagging for Furnished Homes
Bayview by Address Resorts at Emaar Beachfront is Emaar Properties' fully furnished, branded development: 676 residences in two towers.
Book Bayview by Address Resorts at Emaar Beachfront SnaggingApproaching Handover
Between 63.02% and Handover: What Bayview by Address Resorts at Emaar Beachfront Buyers Should Do Now
At the 14 September 2026 inspection Bayview by Address Resorts stood at 63.02%, 3.02 points past the 60% level that the 2023 launch schedule pairs with its 8th instalment (estimated for March 2027) and 16.98 points short of the 80% level paired with the 9th (estimated for September 2027). Each construction-linked instalment on that schedule carries a completion level as well as an estimated month, so the three habits below matter at every reading from here, not only once a payment notice arrives.
First, match every construction-linked payment to a dated reading and send it only to the project's trust account, which the Bayview escrow account page helps you verify before any transfer leaves your bank.
Second, read your own sale and purchase agreement and Oqood entry for how the 60% and 80% instalments are triggered, whether by recorded level, by estimated date, or by developer notice, since the 2023 schedule of record is not a live offer and later buyers enter on the developer's current terms.
Third, follow the record one inspection at a time: the Bayview September 2026 construction update sets out the latest IPMR notes in full, and each later reading is added as a dated update of its own and a new row in the timeline above.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar Beachfront Structure
Bayview's 63.02% of 14 September 2026 is one build among several on the Emaar Beachfront island; these three pages set its progress against the listings, the master community, and the developer behind it:

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Bayview by Address Resorts at Emaar Beachfront Construction Updates Frequently Asked Questions
Bayview by Address Resorts is an active DLD-registered project (number 2646) recorded at 63.02% construction progress at the inspection of 14 September 2026, filed under the IPMR Progress Status Main Contract - Progressing with its superstructure progressing at advanced stages. As of 24 September 2026 that reading is 10 days old and the latest in the register; the full record is in the Bayview inspection timeline above.
The most recent reading is 63.02%, recorded on 14 September 2026, up 14.10 points from 48.92% on 30 June 2026 over 76 days, the shortest interval between any two inspections in the Bayview record. The IPMR notes and the RERA photographs for that visit are described in the full September 2026 update for Bayview by Address Resorts.
Across nine dated pairs, Bayview by Address Resorts moved at under 0.01 points per month between May and December 2023, at about 0.69 to 1.15 points per month from December 2023 to October 2025, and faster after that: about 3.08 points per month to 02 February 2026, 2.90 to 30 June 2026, and 5.57 to 14 September 2026, the fastest pair in the record. Each rate describes a finished interval on a 30-day month; the full breakdown is in the Bayview pace analysis above.
The DLD register gives Bayview by Address Resorts (project 2646) a registered completion date of 31 July 2028, and handover is set for July 2028, so the two point to the same month. At the 14 September 2026 reading of 63.02%, that registered date lay 686 days ahead with 36.98 points still to be recorded; spread evenly, that is about 1.62 points per month, an arithmetic benchmark only, not a forecast. This record is updated whenever the register logs a new reading or a revised date.
Bayview by Address Resorts comprises 676 residential units, branded and fully furnished, from 1 bedroom apartments to 6 bedroom penthouses, in two residential towers over a shared podium that the IPMR describes as Tower 1: Ground + 49 floors and Tower 2: Ground + 34 floors. The construction record on this page covers both towers and the podium as one DLD project, number 2646, recorded at 63.02% on 14 September 2026.
The DLD register lists Bayview by Address Resorts as registered on 29 May 2023 with a registered construction start of 15 October 2023, while its first inspection is dated earlier, 08 May 2023, at 0%: 21 days before registration and 160 days before the registered start. The IPMR for that visit found no building activity, with the plot holding another project's site offices and materials; the Bayview May 2023 construction update covers that opening reading.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Bayview by Address Resorts at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.