Beach Walk Grand 2 by Imtiaz in Island A Dubai Islands project rendering used for the September 2026 construction update showing exterior views of the planned residential building in Dubai - Presented by Tohid Fetrat

Imtiaz · Island A, Dubai Islands · Construction Update

Beach Walk Grand 2 Construction Update - September 2026

September 2026 Inspection Record Places Beach Walk Grand 2 at 23.53% in the DLD Project Register

RERA found piling complete and structure and internal works progressing at Beach Walk Grand 2 on 14 September 2026; the background image is a developer rendering.

Direct advisor access. Every message answered personally, never by a call center.

23.53%DLD Register Reading
14 September 2026Inspection Date
Q4 2027Expected Handover
3724DLD Project Number

DLD Register Data

Beach Walk Grand 2 Construction Snapshot

23.53% at the 14 September 2026 inspection puts Beach Walk Grand 2 in the superstructure band, the stage where the building rises above its piles while the dated instalments of its 60/40 plan keep falling due regardless of the reading.

Project Name

Beach Walk Grand 2 by Imtiaz

Project Number

3724

Project Status

Active

Construction Progress

23.53%

Inspection Date

14 September 2026

Construction Start

01 July 2025

Total Units

108 residences

Total Built Area

12,906.30 sq m

Expected Completion

15 December 2027

Data source: the Dubai Land Department project register for project 3724, inspection dated 14 September 2026 (project registered 11 July 2025), read with the RERA Independent Progress Monitoring Report for the same visit, which prints no percentage. The hero image is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Beach Walk Grand 2 Construction Progress Summary

The register lists 17.48% as the previous inspection for project 3724 without a date, so the 6.05 point difference to the 14 September 2026 reading of 23.53% cannot be read as a monthly pace. What the RERA monitoring report for the same visit does show is the sequence on site: enabling and piling completed, mobilisation still ongoing, and structure and internal works progressing on the G+2P+12+R building.

Completed
  • Enabling works, recorded as completed on 14 September 2026
  • Piling works beneath the residential building
In Progress at 23.53%
  • Structure works on the G+2P+12+R residential building
  • Internal works, recorded as progressing at the site
  • Mobilisation works, still ongoing at the time of inspection
Ahead of Handover
  • Structure through the 12 residential floors and the roof level
  • Fit out and furnishing of all 108 residences
  • First-floor amenity deck with pools, clubhouse and gym
  • Handover expected in Q4 2027
Next inspectionPublished in the DLD project register after the next RERA site visit; no date is announced in advance.
Completion targetHandover expected in Q4 2027; the DLD record shows a registered completion date of 15 December 2027, 457 days after this inspection.
Remaining distance76.47 percentage points separate the 14 September 2026 reading from 100%.
Arithmetic, not a forecast23.53 points over the 440 days since the recorded 01 July 2025 start average about 1.60 points per month; reaching 100% by 15 December 2027 needs about 5.02 points per month over the remaining 457 days.

Payments and Progress

What 23.53% Progress Means for Beach Walk Grand 2 Buyers

Beach Walk Grand 2 is sold on a date-based 60/40 plan, so instalments fall due on calendar dates rather than at construction stages. The 23.53% reading shows how far the building has moved while those dates pass, and at this stage four actions matter most.

Before Every Dated Instalment

Verify the escrow account

Every instalment, including the 10% dated 15 October 2026, should go only to the DLD regulated escrow account registered for project 3724 with First Abu Dhabi Bank (FAB). Beach Walk Grand 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing or Paying

Reread your SPA payment schedule

By the 14 September 2026 reading, the 20% booking share and the instalments dated October 2025, February 2026 and June 2026 had fallen due, 40% of the price in all, against 23.53% registered progress: the plan follows the calendar, not the reading. Check how your sale and purchase agreement sets the remaining dates and the 40% due on completion in Q4 2027. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Off plan purchases at Beach Walk Grand 2 are registered with the Dubai Land Department through Oqood under project 3724. Check that your registration names the correct unit and matches your SPA before the next dated instalment, since it is the DLD record of your interest in the unit until handover.

Every Cycle

Track the readings to 100%

With 76.47 points still to be recorded after 14 September 2026, many register readings remain before completion. Beach Walk Grand 2 construction updates collects each one as it publishes, so every dated instalment can be checked against current progress.

General framework, not legal advice: payment dates, registration steps, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 23.53%?

Entering Beach Walk Grand 2 at the structure stage trades some certainty for payment runway: piling is done and the structure is under way, handover is expected in Q4 2027, and 40% of the price stays due until completion. Every payment goes to the DLD-registered escrow account for project 3724, released against construction progress recorded by the DLD.

Entering Now at 23.53%
  • Piling recorded complete and structure works progressing at 14 September 2026
  • Instalments dated before signing settled at entry, per the developer's current terms
  • 40% of the 60/40 plan due on completion in Q4 2027
Typical Launch Entry
  • Construction risk carried from bare plot to handover
  • Every dated instalment still ahead of the buyer
  • Launch-level pricing, before any structure is visible
AED 2.60M ≈ USD 708KStarting Price
60/40 Plan40% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at Beach Walk Grand 2

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Beach Walk Grand 2 Project Details

Beach Walk Grand 2 by Imtiaz in Island A Dubai Islands aerial view of the residential building with curved balconies rooftop pool landscaped podium and waterfront surroundings in Dubai - Presented by Tohid Fetrat
Island A, Dubai Islands · Imtiaz Developments

With enabling and piling recorded as completed and structure works progressing at 14 September 2026, Beach Walk Grand 2 is a single G+2P+12+R building of 108 fully furnished residences, from 1 bedroom apartments to upper-floor duplexes. Starting prices: AED 2.60M ≈ USD 708K.

For buyers entering at this stage, the trade off is a longer wait to handover in Q4 2027 against 40% of the price held until completion, with any instalments dated before signing settled at entry per the developer's current terms.

Beach Walk Grand 2 by Imtiaz Project Guide

Site Context This Cycle

Explore Beach Walk Grand 2 Location on Dubai Map

Beach Walk Grand 2 stands on a coastal plot on Island A at Dubai Islands, off the Deira coast, where the building's foundations had to be piled before any structure could rise. With piling recorded as completed at the 14 September 2026 inspection, this cycle's work moves to the frame of the single G+2P+12+R building and to its internal works.

Dubai Islands is a newer coastal destination than the city's established districts, so buyers planning to move in or rent out from Q4 2027 are judging a neighbourhood that may still be maturing at handover, a context the Dubai Islands destination guide follows. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Beach Walk Grand 2 by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Beach Walk Grand 2 During the Structure Stage

With dated instalments still falling due while the structure rises, payment protection and residency planning matter as much as the reading itself. Each resource below is matched to Beach Walk Grand 2 as of September 2026.

Beach Walk Grand 2 by Imtiaz in Island A Dubai Islands construction updates cover image featuring a project rendering of the residential building with rooftop amenities and waterfront surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Beach Walk Grand 2 Construction Updates

This page: the 14 September 2026 register reading for Beach Walk Grand 2, with piling complete.

Beach Walk Grand 2 by Imtiaz in Island A Dubai Islands Golden Visa card graphic beside a waterfront residential building rendering in Dubai - Presented by Tohid Fetrat

Beach Walk Grand 2 Golden Visa: Every Unit Type on Its Own

Imtiaz's Beach Walk Grand 2, 108 residences on Island A, meets the threshold at all four unit types individually.

Read Beach Walk Grand 2 Golden Visa Guide
Beach Walk Grand 2 by Imtiaz in Island A Dubai Islands escrow account protection graphic with shield and padlock icons beside a waterfront residential building rendering in Dubai - Presented by Tohid Fetrat

Beach Walk Grand 2 Escrow: Imtiaz's Second Beach Walk Account

Imtiaz's Beach Walk Grand 2 escrows 108 units at First Abu Dhabi Bank, DLD project 3724, 23.53% certified September 2026.

Verify Beach Walk Grand 2 Escrow Account

Update Timeline

Other Beach Walk Grand 2 Construction Updates

This September 2026 record is the first monthly update published for Beach Walk Grand 2; each later reading joins the construction updates hub as it publishes.

All Beach Walk Grand 2 Construction Updates

FAQs

Beach Walk Grand 2 Construction Progress in September 2026: Frequently Asked Questions

The Dubai Land Department project register shows Beach Walk Grand 2 (project 3724) at 23.53% for the inspection dated 14 September 2026. That figure is a DLD register reading: the RERA Independent Progress Monitoring Report for the same visit describes the works on site but prints no percentage of its own. At 23.53% the building is in its early structure stage, with piling recorded as completed and structure works progressing.

No. As of the 14 September 2026 reading, the DLD record for project 3724 still listed a registered completion date of 15 December 2027, and handover for buyers is expected in Q4 2027. Registered dates can be revised between inspection cycles, so any change would appear in a later reading rather than in this record.

The DLD record that carries the 14 September 2026 reading lists 17.48% as the previous inspection but does not show when that inspection took place. Without a date, the move to 23.53% cannot be converted into a monthly rate, so this page plots 17.48% as an undated marker on the progress bar and draws no pace from the pair.

The RERA Independent Progress Monitoring Report records that mobilisation works were still ongoing at the time of inspection, that enabling and piling works were completed, and that structure works and internal works were progressing. It describes the building as G+2P+12+R, meaning a ground floor, two podium parking levels, 12 residential floors and a roof level, and gives the progress status as Main Contract, Progressing. The report carries inspection photographs, which are not reproduced on this page.

The DLD record lists construction as started on 01 July 2025 and the project as registered on 11 July 2025, ten days later. Both dates are printed here exactly as the register shows them, and the record gives no reason for the order. Counted from the recorded start, the 14 September 2026 reading came 440 days into the build.

No. The hero image is a developer rendering composite of the planned building, used to illustrate this update. It does not show the state of the site on 14 September 2026; the evidence for this month is the DLD register reading of 23.53% and the RERA report's notes on piling, structure and internal works.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2026 inspection record for Beach Walk Grand 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts