Imtiaz · Island A, Dubai Islands
Beach Walk Grand 2 Construction Updates
One G+2P+12+R Building on Island A, Tracked Reading by Reading in the DLD Register
Beach Walk Grand 2 read 23.53% in the DLD register on 14 September 2026, this record's first dated reading and its post-piling baseline on Island A.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Beach Walk Grand 2 at a Glance
Beach Walk Grand 2 is a single residential building by Imtiaz Developments on Island A at Dubai Islands, holding 108 residences in a G+2P+12+R frame: a ground floor, two podium parking levels, 12 residential floors and a roof level. The register dates construction from 01 July 2025, ten days before the 11 July 2025 registration, and shows 23.53% on 14 September 2026, 440 days into the build. Because every residence sits in that one building, each reading on this page measures the whole project at once, with no second tower or later phase folded into the figure.
3724
Active
01 July 2025
108 residential units
12,906.30 sq m
15 December 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Beach Walk Grand 2 Construction Update Timeline
The Beach Walk Grand 2 record holds one dated register reading so far: 23.53% on 14 September 2026, published for project 3724 after the RERA visit that found enabling and piling completed. The same register entry lists 17.48% as the previous inspection without printing its date, so the 6.05 points between the two cannot be placed on a calendar or turned into a monthly rate; that earlier figure sits on the track below as an unlabelled marker and stays out of the table. The single row links the September 2026 update, which carries the full notes from that visit.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 23.53% | 14 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Beach Walk Grand 2 Has Been Built
Beach Walk Grand 2 has one dated reading, so there is no pace between inspections to measure yet. What the register dates do support is two pieces of arithmetic, not a forecast:
- 01 Jul 2025 to 14 Sep 2026: whole-build average, recorded start to 23.53% over 440 daysAbout 1.60 points per month
- 14 Sep 2026 to 15 Dec 2027: needed to reach 100% by the registered completion date, 76.47 points over 457 daysAbout 5.02 points per month
The two figures sit far apart because they describe different work. The 440 days since 01 July 2025 cover mobilisation, enabling works and piling for the building, which the RERA visit of 14 September 2026 recorded as completed apart from mobilisation, while the 457 days to 15 December 2027 have to carry the frame through 12 residential floors and the roof level, the fit-out of 108 furnished residences and the first-floor amenity deck. Neither number predicts the Q4 2027 handover or says it will move; the first becomes a measured pace only when a second dated reading is published. For an end user, the figure to watch is how each new reading closes the 76.47 points still to go; for an investor, it is whether successive dated readings, once structure replaces groundworks, climb faster than the 1.60 points per month averaged so far.
Get the Next Inspection Figure First
Tell me you are tracking Beach Walk Grand 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Beach Walk Grand 2 at Island A
A 23.53% register reading on 14 September 2026 is progress toward a specific building: 108 fully furnished residences over 12 residential floors, with duplexes at the top and an amenity deck on the first floor. The project guide covers that destination in full:

Beach Walk Grand 2: Furnished Homes and Duplexes on Island A
Beach Walk Grand 2 is an Imtiaz building of 108 fully furnished apartments and duplexes on Island A at Dubai Islands.
View the Beach Walk Grand 2 Project GuideConsidering an Early-Stage Entry?
Limited Units Available. Entering while the structure is under way means settling the instalments already due at signing, per the developer's current terms, with 40% of the price held until completion in Q4 2027. If the record on this page is what brought you here, ask me for current availability and the amount due at signing for each option.
Ask About Remaining Availability on WhatsAppStage Record
Beach Walk Grand 2 Build Stages, Mapped to the Inspections
The five stages below follow the dates the register actually prints for project 3724, from the 01 July 2025 start to the 14 September 2026 reading, so the record shows where Beach Walk Grand 2 stood at 23.53% and which stages remain before its Q4 2027 handover.
Mobilisation and Enabling Works
Construction is recorded as started on 01 July 2025 and the project as registered on 11 July 2025. By the 14 September 2026 visit, enabling works were complete while mobilisation was still ongoing.
Piling Beneath the Building
Piling for the G+2P+12+R building was recorded as completed at the 14 September 2026 inspection, giving the structure its base on the Island A plot.
Structure and Internal Works
Structure works and internal works were both recorded as progressing on 14 September 2026, the date of the 23.53% register reading, under the RERA status Main Contract, Progressing.
Upper Floors, Roof, and Fit-Out
Completing the frame through the 12 residential floors and the roof level, then fit-out and furnishing of all 108 residences, including the duplexes on the 11th and 12th floors.
Amenity Deck, Commissioning, and Handover
The first-floor amenity deck with its pools, clubhouse and gym, then building systems and final external works, closing the record at 100% ahead of handover expected in Q4 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Walk Grand 2's own record.
Buyer Position
Tracking Your Position at Beach Walk Grand 2
This page is one of four project resources that together cover a Beach Walk Grand 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Walk Grand 2 Construction Updates
This page: each dated DLD register reading for Beach Walk Grand 2 through to handover.

Beach Walk Grand 2 Golden Visa: Every Unit Type on Its Own
Imtiaz's Beach Walk Grand 2, 108 residences on Island A, meets the threshold at all four unit types individually.
Read the Beach Walk Grand 2 Golden Visa Guide
Beach Walk Grand 2 Escrow: Imtiaz's Second Beach Walk Account
Imtiaz's Beach Walk Grand 2 escrows 108 units at First Abu Dhabi Bank, DLD project 3724, 23.53% certified September 2026.
Verify the Beach Walk Grand 2 Escrow AccountApproaching Handover
Between 23.53% and Handover: What Beach Walk Grand 2 Buyers Should Do Now
At the 14 September 2026 reading of 23.53%, Beach Walk Grand 2 still has its frame, fit-out and amenity deck ahead, yet its 60/40 plan runs on calendar dates: 40% of the price had fallen due by 15 June 2026, and the next 10% is dated 15 October 2026. With payments moving on dates and construction moving on readings, the three steps below are worth setting up now rather than when the handover notice arrives.
First, send every instalment only to the project's escrow account at First Abu Dhabi Bank (FAB); the Beach Walk Grand 2 escrow account page shows how to confirm that account against the DLD record for project 3724 before any transfer.
Second, if residency matters to you, settle eligibility early through the Beach Walk Grand 2 Golden Visa eligibility guide, since every price tier from AED 2.60M ≈ USD 708K clears the threshold and buying before completion shapes the application path.
Third, keep the specification this record is measured against close at hand: the Beach Walk Grand 2 layouts and payment plan sit on the project guide, from the first-floor amenity deck to the duplexes on the 11th and 12th floors.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
A register reading for one building is easier to weigh against what surrounds it: the other homes on Island A, the island's own build-out, and the developer building it. These three pages hold that context:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Beach Walk Grand 2 Construction Updates Frequently Asked Questions
Beach Walk Grand 2 (DLD project 3724, status Active) is in its structure stage, recorded at 23.53% in the Dubai Land Department project register on 14 September 2026. The RERA report for that visit lists enabling and piling works as completed and structure and internal works as progressing, under the progress status Main Contract, Progressing. Each stage is mapped to its dates in the stage record above.
The Beach Walk Grand 2 record holds one dated reading so far: 23.53% in the DLD project register on 14 September 2026. The register also lists 17.48% as the previous inspection but prints no date for it, so that figure appears as a marker on the track rather than as a timeline row. The dated reading is covered in the September 2026 Beach Walk Grand 2 construction update.
Measured from the recorded construction start of 01 July 2025, Beach Walk Grand 2 averaged about 1.60 points per month to reach 23.53% on 14 September 2026, 440 days later. Reaching 100% by the registered completion date of 15 December 2027 needs about 5.02 points per month over the remaining 457 days. Both figures are arithmetic, not a forecast, and a measured pace between inspections becomes possible once a second dated reading is published; the workings are in the pace analysis above.
Handover at Beach Walk Grand 2 is expected in Q4 2027, and the DLD record for project 3724 lists a registered completion date of 15 December 2027, which falls inside that quarter. At the 14 September 2026 reading of 23.53%, the registered date was 457 days away and had not lapsed. Any revision to it would show in the register first and would be carried onto this page with the next dated reading.
Beach Walk Grand 2 will deliver 108 residences, the same total the DLD register shows for project 3724: 1, 2 and 3 bedroom apartments plus duplexes on the 11th and 12th floors, all sold fully furnished. All 108 sit in a single building, so each register reading, such as the 23.53% of 14 September 2026, describes the whole project rather than one phase of it.
G+2P+12+R is the configuration RERA records for Beach Walk Grand 2: a ground floor, two podium parking levels, 12 residential floors and a roof level. Per the developer's floor plans, the lobby is on the ground floor, the amenity deck with pools, clubhouse and gym is on the first floor, and the duplexes occupy the 11th and 12th floors. At the 14 September 2026 inspection, structure works on this building were recorded as progressing, with the register at 23.53%.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Walk Grand 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.