Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring a project rendering of a white residential tower with rounded balconies viewed from above in Dubai - Presented by Tohid Fetrat

Imtiaz · Island A, Dubai Islands

Beach Walk Residence 2 Construction Updates

The 726-Day Build Record Behind a Completed Beachside Building on Island A

Beach Walk Residence 2 reached 100% in the DLD register on 6 August 2026, a completed G+2P+8F+R building on Island A now standing at the handover stage.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
6 August 2026Latest RERA Inspection
63 residencesTotal Units
Project 3224DLD Registration

Construction Snapshot

Beach Walk Residence 2 at a Glance

Beach Walk Residence 2 is Imtiaz's 63-residence building on Island A at Dubai Islands, DLD project 3224, now listed in the register as Finished. Construction started on 10 August 2024, the Building Completion Certificate was issued on 9 July 2026, and the register reached 100% on 6 August 2026, four days before the registered completion date. With one G+2P+8F+R building and a single dated reading, this record is read through its dates and completion approvals rather than through a long climb of percentages.

DLD Project Number

3224

Project Status

Finished

Construction Start

10 August 2024

Total Units

63 residences

Total Built-Up Area

7,116.87 sq m

Registered Completion Date

10 August 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Beach Walk Residence 2 Construction Update Timeline

The Beach Walk Residence 2 record closes on one dated register reading: 100% at the RERA inspection of 6 August 2026, which listed the building as Completed. A previous reading of 97.15% also appears in the register without a date, so it sits on the track as an unlabelled dot and has no row in the table. Construction started on 10 August 2024, 726 days before that closing reading, and the row below links the full August 2026 update, which is illustrated with developer renderings rather than site photographs.

Inspection MonthConstruction ProgressInspection DateFull Update
August 2026100%6 August 2026View the August 2026 update
!

Reading the dates: the DLD-registered completion date for project 3224 is 10 August 2026, and the register recorded 100% on 6 August 2026, four days before it, with the Building Completion Certificate already issued on 9 July 2026. The registered date has passed and was met on the record; what remains is handover, which Imtiaz confirms to each buyer under the sale and purchase agreement.

Pace Analysis

How Fast Beach Walk Residence 2 Has Been Built

A single dated reading leaves no pair of inspections to compare at Beach Walk Residence 2, so the pace is read across the whole build and against the registered dates:

  • Aug 2024 to Aug 2026: whole build, 0% to 100% over 726 daysAbout 4.13 points per month
  • 6 Aug 2026 reading against the 10 Aug 2026 registered completion dateMet, 4 days before the date
  • After 6 Aug 2026: Progress Status Completed, handover stageNo points remain

Because the earlier 97.15% reading carries no date, this record cannot show where the Beach Walk Residence 2 build accelerated or tapered, and no phase velocity is drawn here. What it does show is how the finish was sequenced: the Dubai Civil Defence certificate on 27-04-2026, the Building Completion Certificate on 9 July 2026, the DCD LPG approval on 16-07-2026, then the 100% register reading on 6 August 2026, 28 days after the BCC. The 4.13 figure is a straight average across all 726 days counted in 30-day months, which makes it arithmetic for the whole build rather than a forecast. For an end user the useful signal is that the Building Completion Certificate came before the closing reading, so handover preparation rather than construction is what remains; for an investor, the registered completion date of 10 August 2026 was met on the record, with no points left to build.

Get the Next Inspection Figure First

Tell me you are tracking Beach Walk Residence 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Beach Walk Residence 2 at Island A

The register reading tells you the building is finished; the project guide tells you what was finished, and what a buyer is accepting at handover:

Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands project rendering of the residential building with flowing white balconies, landscaped grounds and palm trees in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 2: Furnished Homes Under a Rooftop Pool Deck

Beach Walk Residence 2 is an Imtiaz building of 63 furnished residences on Island A, with three bedroom duplexes.

View the Beach Walk Residence 2 Project Guide

Considering a Ready Unit?

Beach Walk Residence 2 is a completed building with limited units available, and what is left changes as handover proceeds. If the record on this page is what brought you here, ask me what remains before the choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Beach Walk Residence 2 Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Beach Walk Residence 2 record actually dates, from the 10 August 2024 start to the 6 August 2026 closing reading. With only one dated percentage on file, the middle windows are anchored by the approvals listed in the RERA report rather than by interim readings.

Aug 2024

Construction Start and Registration

The register dates the construction start to 10 August 2024, and the DLD registered the project as number 3224 on 28 August 2024; both dates stand exactly as the register prints them.

Aug 2024 onward

Concrete Structure and Blockwork

The concrete frame and block walls of a ground floor, two podium levels, eight residential floors and a roof, recorded as substantially complete by 6 August 2026; no dated reading exists for this stage.

Through 27-04-2026

Finishes, Services, and Civil Defence Sign-Off

Internal and external finishes and building services across the G+2P+8F+R stack, with the Dubai Civil Defence certificate issued 27-04-2026 as the first completion-stage approval on the record.

July 2026

Building Completion Certificate

The Building Completion Certificate was issued on 9 July 2026 and the DCD LPG approval followed on 16-07-2026, the two approvals that moved the building from works to completion.

Current Phase6 Aug 2026 onward, 100% at last reading

Cleaning, Snagging, and Handover Readiness

On 6 August 2026 the RERA report had DEWA water and electricity meters in place and air conditioning live on a DEWA connection, while deep cleaning and the developer's own snagging and de-snagging were still running; handover status is Ready.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Walk Residence 2's own record.

Buyer Position

Tracking Your Position at Beach Walk Residence 2

This page is one of four project resources that together cover a Beach Walk Residence 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring a project rendering of a white residential tower with rounded balconies viewed from above in Dubai - Presented by Tohid Fetrat
You Are Here

Beach Walk Residence 2 Construction Updates

This page: the Beach Walk Residence 2 build record, from the August 2024 start to 100%.

Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands Golden Visa concept graphic with a gold card beside a rendered rooftop pool and curved residential terraces in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 2 Golden Visa: 2 Bedroom and 3 Bedroom Duplex

Beach Walk Residence 2, Imtiaz's 63 residences on Island A, qualifies at 2 bedroom apartments and 3 bedroom duplexes.

Read the Beach Walk Residence 2 Golden Visa Guide
Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands escrow account concept graphic with a shield and padlock in front of a rendered residential tower in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 2 Escrow: The Second Release, Fully Certified

Beach Walk Residence 2, DLD project 3224, read 100% certified August 2026, its 63 units escrowed at First Abu Dhabi Bank.

Verify the Beach Walk Residence 2 Escrow Account
Beach Walk Residence 2 by Imtiaz in Island A at Dubai Islands snagging inspection graphic over a rendered bedroom with an upholstered bed and full-height windows in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 2 Snagging: Apartments and 3 Bedroom Duplexes

Beach Walk Residence 2 is configured as G+2P+8F+R, holding 63 fully furnished residences, 1 and 2 bedroom apartments plus duplexes.

Book Beach Walk Residence 2 Snagging

Approaching Handover

Between 100% and Handover: What Beach Walk Residence 2 Buyers Should Do Now

At Beach Walk Residence 2 the gap left to close is no longer construction: the register reads 100% and the Building Completion Certificate was issued on 9 July 2026, while the RERA report of 6 August 2026 still had deep cleaning and the developer's own snagging and de-snagging in progress. Handover notices typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.

First, arrange an independent snagging inspection so defects in your furnished unit, from fixed joinery to the balcony, are documented before you accept it; the Beach Walk Residence 2 snagging page explains timing and what gets checked in this building.

Second, confirm the 40% completion payment against the record on the Beach Walk Residence 2 escrow account page, so the final transfer goes to the registered trust account for project 3224 and nowhere else.

Third, if your unit is valued at AED 2M ≈ USD 545K or more, which on the current price list means the 2 bedroom and 3 bedroom duplex types, settle eligibility through the Beach Walk Residence 2 Golden Visa guide, since the application rests on the title deed issued when the unit transfers at handover.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island A Structure

A finished build record is half the picture; the other half is the island still filling in around it. These three pages put Beach Walk Residence 2 in its listings, community, and developer context:

Aerial masterplan view of Island A properties for sale with waterfront residences, marinas, green spaces, and connected roadways in Dubai. Presented by Tohid Fetrat

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses

Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.

See Island A Properties for Sale
Aerial masterplan view highlighting Island A at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island A Community Overview

Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.

Explore the Island A Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Beach Walk Residence 2 Construction Updates Frequently Asked Questions

Beach Walk Residence 2 is complete on the record: DLD project 3224 is listed as Finished at 100% in the project register as of the RERA inspection of 6 August 2026, with the Building Completion Certificate issued on 9 July 2026 and handover status Ready. The dated record is in the inspection timeline above.

The RERA inspection of 6 August 2026 closed it, with the register moving to 100%, 2.85 points above a previous reading of 97.15% whose date the register does not show. That inspection is the only dated reading on this record, and its full write-up is in the Beach Walk Residence 2 August 2026 construction update.

Yes, on the register. The DLD registered completion date for project 3224 is 10 August 2026, and the register recorded 100% on 6 August 2026, four days before it, following the Building Completion Certificate of 9 July 2026. The date has now passed and was met; handover to buyers is the remaining step, and this page's record is updated when that status changes.

Beach Walk Residence 2 contains 63 residences on the DLD record for project 3224, made up of 1 and 2 bedroom apartments and 3 bedroom duplexes, all fully furnished, in a single building on Island A at Dubai Islands. Layouts, sizes and prices are in the Beach Walk Residence 2 by Imtiaz project guide.

Beach Walk Residence 2 averaged about 4.13 points per month across the 726 days from its 10 August 2024 construction start to the 100% register reading of 6 August 2026, counting 30-day months. That figure is arithmetic over the whole build, not a forecast and not a phase measurement, because the earlier 97.15% reading has no date to pair with. The working is in the pace analysis above.

G+2P+8F+R is the RERA report's description of Beach Walk Residence 2: a ground floor, two podium levels, eight residential floors and a roof level, built as a concrete structure with blockwork and internal and external finishes. On the developer's floor plans the amenities floor holds a pool, gym and club house, and the roof carries a second pool and deck.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Walk Residence 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.