Ellington · Meydan Horizon · Construction Update

Belmore Residences Construction Update - August 2026

August 2026 Inspection Places Belmore Residences at 6.53% in the DLD Register in Meydan Horizon

Enabling, piling and foundation works were progressing at Belmore Residences when RERA inspected on 6 August 2026, with the DLD register reading recorded at 6.53 percent.

Direct advisor access. Every message answered personally, never by a call center.

6.53%DLD Register Reading
6 August 2026Inspection Date
Q4 2027Expected Handover
4033DLD Project Number

DLD Register and RERA Inspection Data

Belmore Residences Construction Snapshot

A 3.37 point rise since the previous DLD reading, whose date the register does not show, places Belmore Residences in the opening band of construction, where enabling, piling and foundations set the base for everything a buyer is paying toward.

Project Name

Belmore Residences by Ellington

Project Number

4033

Project Status

Active

Construction Progress

6.53%

Inspection Date

6 August 2026

Construction Start

7 August 2025

Total Units

214 units

Total Built Area

19,104.29 sq m

Expected Completion

Q4 2027

Data source: DLD project register reading for project 4033 recorded on 6 August 2026, read with the RERA inspection report of the same date. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering of the planned entrance, not a site photograph. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Belmore Residences Construction Progress Summary

The 6.53% recorded on 6 August 2026 came almost exactly a year after the register's construction start of 7 August 2025, a whole-build average of about 0.54 points per month (arithmetic, not a forecast). RERA's report for the same day lists enabling, piling and foundation works as progressing and the main contract as progressing, the opening sequence for a B+G+5P+26F tower.

On the Register
  • Construction start recorded on 7 August 2025
  • Project registration recorded on 27 August 2025
  • Escrow trust account with Arab Bank listed for project 4033
In Progress at 6.53%
  • Enabling works on the site
  • Piling works
  • Foundation works
  • Main contract, recorded by RERA as progressing
Ahead of Handover
  • Basement, ground floor and five podium levels
  • The 26 residential floors above the podium
  • Further DLD register readings toward 100%
  • Handover expected in Q4 2027
Next inspectionPosted in the DLD project register after each RERA site visit; the reading on this page was recorded on 6 August 2026, so a newer one may be listed.
Completion targetHandover expected in Q4 2027; the DLD register lists a registered completion date of 31 December 2027.
Remaining distance93.47 percentage points separate the 6 August 2026 reading from 100% in the register.

Payment Linked Progress

What 6.53% Progress Means for Belmore Residences Buyers

On the 70/30 plan, the five reservation-date instalments, half the price including the booking payment, fall due within 360 days of each buyer's own reservation date, independent of the site. Four further 5% instalments wait on 30%, 40%, 50% and 60% construction, and the 6.53% reading of 6 August 2026 had reached none of them. At this stage of Belmore Residences, four actions matter most.

Before Any Transfer

Verify the escrow account

Every payment ahead of handover should go only to the DLD regulated escrow account with Arab Bank registered for project 4033. Belmore Residences escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before You Sign

Reread your SPA milestone schedule

Check how your sale and purchase agreement words the construction-linked instalments and the 30% due on completion, and map those clauses against each dated register reading and the Q4 2027 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Reservation

Confirm your Oqood registration

An off plan unit at Belmore Residences is registered with the Dubai Land Department through Oqood while the tower is built. Once your booking payment clears, ask for the Oqood record and check that it names project 4033 and your exact unit.

Every Cycle

Track the coming cycles

Many inspection readings lie between 6.53% and completion, so confirm the current construction timetable with the developer in writing. Belmore Residences construction updates keeps every reading dated as the foundations give way to the podium.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 6.53%?

Entering a project in its foundation phase trades a longer wait for more runway: most construction-linked milestones of the plan lie ahead, the site record is short, and the choice is among the units still released. Every payment goes to the DLD-registered escrow account for project 4033, released against verified construction progress.

Entering Now at 6.53%
  • Enabling, piling and foundation works progressing per RERA on 6 August 2026
  • Handover expected in Q4 2027, with most of the build still ahead
  • 30% of the 70/30 plan held back until completion
Typical Near-Handover Entry
  • A long inspection record to judge before paying
  • A short wait between purchase and keys
  • Less runway, with larger sums due over fewer months
AED 1.65M ≈ USD 449KStarting Price
70/30 Plan30% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at Belmore Residences

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Belmore Residences Project Details

Belmore Residences by Ellington in Meydan Horizon project rendering of the residential tower above landscaped community surroundings in Dubai - Presented by Tohid Fetrat
Meydan Horizon · Ellington

With foundations still being laid at the August 2026 inspection, Belmore Residences is an early-stage tower of 210 residences in one, two and three bedroom layouts, registered by RERA as B+G+5P+26F, beside the Ras Al Khor Wildlife Sanctuary. Starting prices: AED 1.65M ≈ USD 449K.

For buyers entering at this stage, the trade off is a longer wait against more of the payment plan still ahead, with handover expected in Q4 2027 per the developer.

Belmore Residences by Ellington Project Guide

Site Context This Cycle

Explore Belmore Residences Location on Dubai Map

Belmore Residences sits on the Meydan Horizon edge closest to the Ras Al Khor Wildlife Sanctuary, with E44 Ras Al Khor Road running between the two on the developer's building elevation, and this cycle that position matters below ground: the piling and foundation works RERA recorded on 6 August 2026 have to carry a basement, a ground floor with retail and five podium levels before the residential floors begin.

Meydan Horizon is a community still taking shape, with several apartment towers, this one included, under construction around its lagoon, while the road network already places Dubai International Airport about 9 minutes' drive away per the developer's location guide. For buyers at 6.53%, the useful question is how the district will look around the Q4 2027 handover rather than today. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Belmore Residences by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Belmore Residences During Early Construction Progress

The opening band is where payment protection and residency planning matter more than handover logistics. Each resource below is matched to where Belmore Residences stood at the 6 August 2026 reading.

Belmore Residences by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of the residential tower and landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Belmore Residences Construction Updates

This page: the 6.53% DLD register reading recorded on 6 August 2026, with RERA's site notes.

Belmore Residences by Ellington in Meydan Horizon Golden Visa concept graphic with a gold card beside rendered balconies and the Dubai skyline in Dubai - Presented by Tohid Fetrat

Belmore Residences Golden Visa Through a 2 or 3 Bedroom Apartment

Belmore Residences, Ellington's Meydan Horizon tower, qualifies at its 2 and 3 bedroom apartments, while 1 bedroom starts below the threshold.

Read Belmore Residences Golden Visa Guide
Belmore Residences by Ellington in Meydan Horizon escrow concept graphic with a shield and padlock over a rendered residential building and landscaped grounds in Dubai - Presented by Tohid Fetrat

Belmore Residences Escrow: Arab Bank Holds Instalments for Project 4033

Belmore Residences, Ellington's Meydan Horizon tower, escrows its 214 registered units at Arab Bank under DLD project 4033, certified at 6.53%.

Verify Belmore Residences Escrow Account

Update Timeline

Other Belmore Residences Construction Updates

This August 2026 record opens the monthly series for Belmore Residences; each newer register reading joins the dated timeline on the construction updates hub as it is posted.

All Belmore Residences Construction Updates

FAQs

Belmore Residences Construction Progress in August 2026: Frequently Asked Questions

The Dubai Land Department project register recorded Belmore Residences, project 4033, at 6.53% construction progress on 6 August 2026, the date of that month's RERA inspection. The RERA report itself prints no percentage, so 6.53% is the register reading, and it describes the site on that date only.

Alongside the 6.53% recorded on 6 August 2026, the register lists a previous inspection reading of 3.16% but does not show the date on which that earlier reading was taken. Because the earlier reading is undated, no monthly pace can be measured between the two figures; they show direction, not speed.

The RERA inspection report of 6 August 2026 notes that enabling, piling and foundation works were progressing at the site, and it records the main contract's progress status as progressing. It describes the project as a residential and commercial building configured B+G+5P+26F, and the report carries inspection photographs as part of the official record.

It places the tower at an early construction stage on 6 August 2026, with the recorded work still in enabling, piling and foundations rather than in the floors above ground. Readings commonly sit low while piling and foundations are underway, and a single early reading is not a forecast: handover is expected in Q4 2027 per the developer.

No. The image at the top of this page is a developer rendering of the planned curved entrance with palm trees and landscaping, used to identify the project rather than to show site progress. The site record for August 2026 is the RERA inspection report and the DLD register reading of 6 August 2026; the report's own inspection photographs are not reproduced here.

Possibly. RERA inspections recur throughout construction, so a reading newer than the 6.53% recorded on 6 August 2026 may have been posted since this page was prepared. Searching project number 4033 in the Dubai Land Department's Dubai REST app shows the current register figure, and each newer reading is dated on the Belmore Residences construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Belmore Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts