Belmore Residences by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of the residential tower and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Ellington · Meydan Horizon

Belmore Residences Construction Updates

The Dated Register Record of an Ellington Tower Beside Ras Al Khor

Belmore Residences reached 6.53% on the DLD register, recorded on 6 August 2026, an opening record of enabling, piling and foundation works beside Ras Al Khor.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.53%Construction Progress
6 August 2026Latest RERA Inspection
214 unitsTotal Units
Project 4033DLD Registration

Construction Snapshot

Belmore Residences at a Glance

Belmore Residences is Ellington's single tower of 210 residences in Meydan Horizon, entered in the Dubai Land Department register as project 4033 and recorded at 6.53% on 6 August 2026. The register gives 7 August 2025 as the construction start and 27 August 2025 as the registration date, and RERA describes a B+G+5P+26F residential and commercial building whose first year on record closed with enabling, piling and foundation works still in progress. The cards below are the register anchors that every later Belmore Residences reading will be measured against.

DLD Project Number

4033

Project Status

Active

Construction Start

7 August 2025

Total Units

214 units

Total Built-Up Area

19,104.29 sq m

Registered Completion Date

31 December 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Belmore Residences Construction Update Timeline

One dated reading makes up the Belmore Residences record so far: 6.53% on the DLD register, recorded on 6 August 2026, the same day RERA inspected the site and noted enabling, piling and foundation works progressing. The register also shows an earlier reading of 3.16% without a date, so that figure sits on the track below as an unlabelled dot and stays out of the table, which lists dated readings only. The August 2026 update carries a developer rendering of the tower's planned entrance in place of site photography.

Inspection MonthConstruction ProgressInspection DateFull Update
August 20266.53%6 August 2026View the August 2026 update

Pace Analysis

How Fast Belmore Residences Has Been Built

With a single dated reading, Belmore Residences has no inspection-to-inspection pace yet. What can be computed is the average from the registered start to 6 August 2026, which is arithmetic, not a forecast:

  • Aug 2025 to Aug 2026: enabling, piling and foundations, from the registered start to 6.53% on 6 Aug 2026About 0.54 points per month

That 0.54 spreads 6.53 points across the 364 days between the 7 August 2025 start and the 6 August 2026 reading, a first year that ended, per RERA's notes, with enabling, piling and foundation work in progress. Early readings commonly sit low in that phase, because the register percentage covers the whole B+G+5P+26F building and most of that building is yet to rise above the foundations. The earlier 3.16% on the register shows the direction of travel, but without a date it cannot be turned into a rate, so this curve has one measured point and no shape yet. For an end user planning around the Q4 2027 handover, the practical step is to confirm the current construction timetable with the developer in writing; for an investor, the first measurable Belmore Residences pace arrives with the next dated reading, which joins the table above as a second row.

Get the Next Inspection Figure First

Tell me you are tracking Belmore Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Belmore Residences at Meydan Horizon

A 6.53% reading describes a site; the project guide describes what that site is meant to become, from the apartment layouts to the podium and rooftop amenity decks:

Belmore Residences by Ellington in Meydan Horizon project rendering of the residential tower above landscaped community surroundings in Dubai - Presented by Tohid Fetrat

Belmore Residences: A Family-Scaled Tower Beside a Protected Wetland

Belmore Residences places 210 one to three bedroom apartments over a retail arcade, with amenity decks on the podium and rooftop.

View the Belmore Residences Project Guide

Considering an Early-Stage Entry?

Belmore Residences is still in enabling, piling and foundations on the record, and limited units are available at this stage. If the record on this page is what brought you here, ask me what is open now, before the current release moves on.

Ask About Remaining Availability on WhatsApp

Stage Record

Belmore Residences Build Stages, Mapped to the Inspections

Only the first two stages below carry evidence so far: the register's 7 August 2025 start and the 6 August 2026 inspection at 6.53%. The later three are laid out from RERA's B+G+5P+26F description and the Q4 2027 handover, and each will gain dated readings as Belmore Residences moves into it.

Aug 2025, registered start

Site Activation and Enabling Works

The register records construction starting on 7 August 2025 and project registration on 27 August 2025; enabling works were still listed as progressing at the August 2026 inspection.

Current Phase6 Aug 2026 at 6.53%

Piling and Foundations

RERA's 6 August 2026 report recorded enabling, piling and foundation works progressing under a status of Main Contract, Progressing, with the register at 6.53% and an undated earlier reading of 3.16%.

Next, not yet recorded

Basement, Ground Floor and Podium Levels

The B+G+5P portion of RERA's description: the basement, the ground floor with its retail arcade, and the podium levels beneath the residences. No dated reading covers this stage yet.

Later, not yet recorded

The 26 Residential Floors

The 26F in the RERA configuration, crowned in the developer's plans by a rooftop amenity level. No register reading has reached this stage.

Toward handover, expected Q4 2027

Finishing, Commissioning and Handover

Apartment fit-out, building systems and final works ahead of the handover the developer expects in Q4 2027; the register lists 31 December 2027 as the registered completion date.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Belmore Residences's own record.

Buyer Position

Tracking Your Position at Belmore Residences

This page is one of four project resources that together cover a Belmore Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Belmore Residences by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of the residential tower and landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Belmore Residences Construction Updates

This page: the dated register record for Belmore Residences, from the August 2025 start to handover.

Belmore Residences by Ellington in Meydan Horizon Golden Visa concept graphic with a gold card beside rendered balconies and the Dubai skyline in Dubai - Presented by Tohid Fetrat

Belmore Residences Golden Visa Through a 2 or 3 Bedroom Apartment

Belmore Residences, Ellington's Meydan Horizon tower, qualifies at its 2 and 3 bedroom apartments, while 1 bedroom starts below the threshold.

Read the Belmore Residences Golden Visa Guide
Belmore Residences by Ellington in Meydan Horizon escrow concept graphic with a shield and padlock over a rendered residential building and landscaped grounds in Dubai - Presented by Tohid Fetrat

Belmore Residences Escrow: Arab Bank Holds Instalments for Project 4033

Belmore Residences, Ellington's Meydan Horizon tower, escrows its 214 registered units at Arab Bank under DLD project 4033, certified at 6.53%.

Verify the Belmore Residences Escrow Account

Approaching Handover

Between 6.53% and Handover: What Belmore Residences Buyers Should Do Now

At 6.53%, recorded on 6 August 2026, the work on record at Belmore Residences is still piling and foundations, so the decisions that matter now concern payments and paperwork rather than the building itself. Timing still counts at this stage: half of the 70/30 price, the booking payment included, is scheduled by reservation date and comes due within 360 days of the buyer's reservation date, regardless of site progress, whereas none of the four construction-linked 5% payments, set at 30%, 40%, 50% and 60% construction, had been triggered by the 6 August 2026 reading.

First, before any transfer, check the account details against the DLD record: the Belmore Residences escrow account page sets out the Arab Bank account registered for project 4033 and how payments are matched to it.

Second, if UAE residency is part of the plan, read the Belmore Residences Golden Visa guide before choosing a layout, since the 2 and 3 bedroom apartments start above the property threshold while the 1 bedroom, from AED 1.65M ≈ USD 449K, does not reach it on its own.

Third, confirm the current construction timetable with the developer in writing, then follow each dated reading as it is posted, starting with the Belmore Residences August 2026 inspection record.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Meydan Horizon Structure

A single tower's 6.53% means more beside its surroundings, so these three pages set Belmore Residences against the Meydan Horizon listings, community and developer around it:

Street view of Meydan Horizon properties for sale in Dubai showing modern residential buildings, palm lined roads and urban community spaces, Presented by Tohid Fetrat

Meydan Horizon: The Symphony Apartments in a Lagoon District

Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.

See Meydan Horizon Properties for Sale
View of Meydan Horizon in Dubai showing modern high rise buildings, a central waterway and landscaped waterfront surroundings, Presented by Tohid Fetrat

Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary

Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.

Explore the Meydan Horizon Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Belmore Residences Construction Updates Frequently Asked Questions

Belmore Residences is an active project on the Dubai Land Department register, number 4033, recorded at 6.53% construction progress on 6 August 2026. RERA's inspection on that date found enabling, piling and foundation works under way, with the progress status given as Main Contract, Progressing. The dated record is in the inspection timeline above.

The reading dated 6 August 2026 places Belmore Residences at 6.53%, which is 3.37 points above the previous register reading of 3.16%; the register does not show when that earlier reading was taken. The August 2026 Belmore Residences construction update covers that inspection in full.

The DLD register records the Belmore Residences construction start as 7 August 2025 and the project registration as 27 August 2025. The first dated reading on this record, 6.53%, followed on 6 August 2026, a year into the build, with RERA noting enabling, piling and foundation works progressing that day.

The DLD register lists 31 December 2027 as the registered completion date for project 4033, the last day of the Q4 2027 window in which the developer expects handover. With 6.53% recorded on 6 August 2026, buyers should confirm the current construction timetable with the developer in writing, and this page adds each new dated reading as it is posted.

Belmore Residences comprises 210 residences in one, two and three bedroom apartments. The RERA inspection report of 6 August 2026 classes it as a residential and commercial building with a B+G+5P+26F configuration, and the developer plans place a retail arcade on the ground floor with amenity decks on the podium and the rooftop.

Averaged over the 364 days from the 7 August 2025 start to the 6 August 2026 reading of 6.53%, Belmore Residences moved about 0.54 percentage points per month, which is arithmetic, not a forecast. Because the earlier 3.16% reading is undated, no inspection-to-inspection pace can be measured yet; the pace analysis shows the calculation.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Belmore Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status