Binghatti · Business Bay
Binghatti Aquarise Construction Updates
The Verified Build Record for Plot 261, Business Bay
Binghatti Aquarise recorded 21.04% construction at its 14 May 2026 RERA inspection, the first tracked reading establishing how fast its two Business Bay towers are rising.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Aquarise at a Glance
Project 3585 covers 1,598 residences on plot 261 in Business Bay, and its register runs from a construction start of 15 March 2025 to the 21.04% certified fourteen months later on 14 May 2026. The anchors below are the registered figures behind that span. What makes the record read differently from most projects this early is that the inspection already names internal and MEP trades alongside the frame, so the percentage is not describing a site that is still only moving earth.
3585
Active
15 March 2025
1,598 residential units
120,062.34 sq m
Q4 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Aquarise Construction Update Timeline
One certified percentage anchors this record so far: 21.04%, dated 14 May 2026, the first inspection figure published against project 3585. An earlier entry in the register shows zero percent, but no inspection date is published beside it, so that reading appears here in prose only and is never placed on the track or in the table. The row below links the full May 2026 update and what the inspector found on plot 261.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 21.04% | 14 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Binghatti Aquarise Has Been Built
With a single dated inspection on file, velocity between cycles cannot be measured here yet. What the record does support is one derived figure and one schedule-implied figure, and the difference between them matters:
- 15 Mar 2025 register start to the 14 May 2026 inspection: 0% to 21.04%About 1.5 points per month (derived)
- 14 May 2026 to the Q4 2027 window: 78.96 points left to certifyAbout 4.0 points per month (schedule-implied)
Neither number is an observed pace, and reading the second as an acceleration over the first would be wrong. The 1.5 figure is derived by spreading 21.04 points across roughly fourteen months from the register start, a span dominated by excavation and three basement levels, where a great deal of work registers as very little percentage. The 4.0 figure is arithmetic against a published target: it is what the distance to Q4 2027 would ask for if the window holds, not something the site has demonstrated. The first genuine inter-cycle velocity for Binghatti Aquarise arrives with the second dated inspection, and that reading is the one worth waiting for. Until then, the honest position for an investor weighing entry or a buyer already committed is that project 3585 has one certified data point, a plausible trajectory, and no trend.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Aquarise and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Aquarise at Business Bay
A percentage only means something next to what it is delivering. The project guide sets out what a buyer at 21.04% is actually tracking toward:

Binghatti Aquarise, a Business Bay Tower with Royal Suite Lap Pools
Binghatti Aquarise is a 1,598-residence Business Bay tower of studio to four bedroom apartments, Royal Suite layouts with private lap pools.
View the Binghatti Aquarise Project GuideConsidering an Early-Stage Entry?
Availability at Binghatti Aquarise shifts as certified progress accumulates, and the tiers the building holds fewest of are the ones that close first. If the record on this page is what brought you here, ask me what remains open before the next inspection publishes.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Aquarise Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is tied to the window it occupies in this project's own record, so you can see where the 21.04% of 14 May 2026 actually sits.
Site Activation and Enabling Works
From the 15 March 2025 register start on plot 261: shoring, excavation and enabling packages, none of which had a certified percentage attached to them at the time.
Basements and Common Podium
Foundation and substructure across the three basement levels beneath the ground and mezzanine podium that the RERA description sets out as shared by both towers.
Superstructure on Both Towers
Frame climbing on both structures at once, the 25-storey element and its six-storey neighbour, with internal and MEP packages already trailing the leading slab rather than waiting for topping out.
Facade, Fit-Out and Podium Works
Most of the 78.96 points still uncertified after May 2026 belong to envelope, interior fit-out, and the pool-deck and artificial-beach landscaping across the shared podium.
Commissioning and Delivery
Systems testing, completion certificate procedures and the closing inspection cycles that carry project 3585 from its final recorded percentage into handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Aquarise's own record.
Buyer Position
Tracking Your Position at Binghatti Aquarise
This page is one of four project resources that together cover a Binghatti Aquarise purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Aquarise Construction Updates
This page: the verified inspection record for Binghatti Aquarise, from the March 2025 start to handover.

Binghatti Aquarise Golden Visa: Where the Line Crosses the Ladder
Binghatti Aquarise, a 1,598 residence Business Bay tower, qualifies from the 2 bedroom apartment up; studios and 1 bedrooms do not.
Read the Binghatti Aquarise Golden Visa Guide
Binghatti Aquarise Escrow, a First Abu Dhabi Bank Account in Business Bay
Binghatti Aquarise counts 1598 units under DLD project 3585; First Abu Dhabi Bank holds the escrow, certified 21.04% in May 2026.
Verify the Binghatti Aquarise Escrow AccountApproaching Handover
Between 21.04% and Handover: What Binghatti Aquarise Buyers Should Do Now
Early in an off-plan purchase the money moves ahead of anything you can see, because construction-linked instalments are triggered by certified readings rather than by the calendar. The larger part of this build still sits above the 14 May 2026 figure, which makes the quiet period between inspection cycles, not the handover notice, the window where the three steps below actually matter.
First, make sure every remaining instalment lands in the regulated trust account and nowhere else; the Binghatti Aquarise escrow account page shows the First Abu Dhabi Bank account registered to project 3585 and how certified milestones release funds from it.
Second, if your tier may carry residency, establish the eligibility timing now through the Binghatti Aquarise Golden Visa guide, because an off-plan unit is held by interim registration rather than a title deed until the Q4 2027 window closes.
Third, follow the record cycle by cycle. The Binghatti Aquarise May 2026 construction update sets the baseline every later reading gets measured against, and this page collects each new percentage as it is published.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Business Bay Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put Aquarise's progress in its market, community and developer context:

Business Bay Properties for Sale
Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.
See Business Bay Properties for Sale
Business Bay Community Overview
Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.
Explore the Business Bay Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Aquarise Construction Updates Frequently Asked Questions
Binghatti Aquarise is an active DLD-registered project (number 3585) in its superstructure phase, recorded at 21.04% at the RERA inspection of 14 May 2026. The full record is in the inspection timeline above.
The 14 May 2026 inspection recorded 21.04% construction progress, the first dated percentage published for project 3585. The entry preceding it in the register reads zero percent and carries no inspection date, so those 21.04 points measure everything certified between the 15 March 2025 register start and that inspection, not one cycle of output. The inspector's findings are documented in the Binghatti Aquarise May 2026 update.
The developer-stated handover window for Binghatti Aquarise is Q4 2027. The DLD register for project 3585 records a construction start of 15 March 2025 and registration on 16 April 2025, and the most recent certified reading is 21.04% on 14 May 2026, which leaves 78.96 points to certify before delivery. This page updates each time a new inspection percentage is published.
Binghatti Aquarise comprises 1,598 residential units spread across studio through four-bedroom layouts, with a further 28 retail units at ground level and a total built-up area of 120,062.34 sq m. The DLD unit field currently displays 1,592 for project 3585; the developer project facts state 1,598, and 1,598 is the figure carried on this page.
The DLD register records the construction start for project 3585 as 15 March 2025, with its registration entry dated 16 April 2025. The first tracked inspection followed fourteen months later, on 14 May 2026, at 21.04%, and the derived pace for that span is set out in the pace analysis above.
The 14 May 2026 RERA report lists live packages across enabling and foundation, the substructure, the superstructure of both towers, and the internal and MEP trades. Several trades running at once is what places the 21.04% reading in the structural band rather than in groundworks, and it is also why a single figure understates how much of the site is active.
The RERA project description for 3585 records a shared podium of three basement levels plus ground and mezzanine, above which two separate structures rise: a 25-storey residential element topped by a mechanical level and roof, and a shorter six-storey element with its own roof. Both were in superstructure at the 21.04% reading of 14 May 2026.
The site is plot 261, set inside Business Bay a short distance from the Dubai Water Canal and a few minutes from Downtown Dubai. The district context around the plot is covered in the Business Bay community guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Aquarise construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.