Binghatti Aquarise by Binghatti in Business Bay construction updates cover image featuring an aerial project rendering of the curved residential complex with landscaped pools and surrounding towers in Dubai - Presented by Tohid Fetrat

Binghatti · Business Bay

Binghatti Aquarise Construction Updates

The Verified Build Record for Plot 261, Business Bay

Binghatti Aquarise recorded 21.04% construction at its 14 May 2026 RERA inspection, the first tracked reading establishing how fast its two Business Bay towers are rising.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

21.04%Construction Progress
14 May 2026Latest RERA Inspection
1,598 residential unitsTotal Units
Project 3585DLD Registration

Construction Snapshot

Binghatti Aquarise at a Glance

Project 3585 covers 1,598 residences on plot 261 in Business Bay, and its register runs from a construction start of 15 March 2025 to the 21.04% certified fourteen months later on 14 May 2026. The anchors below are the registered figures behind that span. What makes the record read differently from most projects this early is that the inspection already names internal and MEP trades alongside the frame, so the percentage is not describing a site that is still only moving earth.

DLD Project Number

3585

Project Status

Active

Construction Start

15 March 2025

Total Units

1,598 residential units

Total Built-Up Area

120,062.34 sq m

Registered Completion Date

Q4 2027

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Aquarise Construction Update Timeline

One certified percentage anchors this record so far: 21.04%, dated 14 May 2026, the first inspection figure published against project 3585. An earlier entry in the register shows zero percent, but no inspection date is published beside it, so that reading appears here in prose only and is never placed on the track or in the table. The row below links the full May 2026 update and what the inspector found on plot 261.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202621.04%14 May 2026View the May 2026 update

Pace Analysis

How Fast Binghatti Aquarise Has Been Built

With a single dated inspection on file, velocity between cycles cannot be measured here yet. What the record does support is one derived figure and one schedule-implied figure, and the difference between them matters:

  • 15 Mar 2025 register start to the 14 May 2026 inspection: 0% to 21.04%About 1.5 points per month (derived)
  • 14 May 2026 to the Q4 2027 window: 78.96 points left to certifyAbout 4.0 points per month (schedule-implied)

Neither number is an observed pace, and reading the second as an acceleration over the first would be wrong. The 1.5 figure is derived by spreading 21.04 points across roughly fourteen months from the register start, a span dominated by excavation and three basement levels, where a great deal of work registers as very little percentage. The 4.0 figure is arithmetic against a published target: it is what the distance to Q4 2027 would ask for if the window holds, not something the site has demonstrated. The first genuine inter-cycle velocity for Binghatti Aquarise arrives with the second dated inspection, and that reading is the one worth waiting for. Until then, the honest position for an investor weighing entry or a buyer already committed is that project 3585 has one certified data point, a plausible trajectory, and no trend.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Aquarise and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Aquarise at Business Bay

A percentage only means something next to what it is delivering. The project guide sets out what a buyer at 21.04% is actually tracking toward:

Binghatti Aquarise by Binghatti in Business Bay residential building with a sweeping curved facade seen beyond a landscaped park and palm trees in Dubai - Presented by Tohid Fetrat

Binghatti Aquarise, a Business Bay Tower with Royal Suite Lap Pools

Binghatti Aquarise is a 1,598-residence Business Bay tower of studio to four bedroom apartments, Royal Suite layouts with private lap pools.

View the Binghatti Aquarise Project Guide

Considering an Early-Stage Entry?

Availability at Binghatti Aquarise shifts as certified progress accumulates, and the tiers the building holds fewest of are the ones that close first. If the record on this page is what brought you here, ask me what remains open before the next inspection publishes.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Aquarise Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is tied to the window it occupies in this project's own record, so you can see where the 21.04% of 14 May 2026 actually sits.

Mar 2025 to mid 2025

Site Activation and Enabling Works

From the 15 March 2025 register start on plot 261: shoring, excavation and enabling packages, none of which had a certified percentage attached to them at the time.

Through 2025

Basements and Common Podium

Foundation and substructure across the three basement levels beneath the ground and mezzanine podium that the RERA description sets out as shared by both towers.

Current PhaseRecorded at 21.04% on 14 May 2026

Superstructure on Both Towers

Frame climbing on both structures at once, the 25-storey element and its six-storey neighbour, with internal and MEP packages already trailing the leading slab rather than waiting for topping out.

Ahead: 2026 into 2027

Facade, Fit-Out and Podium Works

Most of the 78.96 points still uncertified after May 2026 belong to envelope, interior fit-out, and the pool-deck and artificial-beach landscaping across the shared podium.

Toward the Q4 2027 window

Commissioning and Delivery

Systems testing, completion certificate procedures and the closing inspection cycles that carry project 3585 from its final recorded percentage into handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Aquarise's own record.

Buyer Position

Tracking Your Position at Binghatti Aquarise

This page is one of four project resources that together cover a Binghatti Aquarise purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Aquarise by Binghatti in Business Bay construction updates cover image featuring an aerial project rendering of the curved residential complex with landscaped pools and surrounding towers in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Aquarise Construction Updates

This page: the verified inspection record for Binghatti Aquarise, from the March 2025 start to handover.

Binghatti Aquarise by Binghatti in Business Bay Golden Visa graphic with a gold card above a project rendering and the Downtown Dubai skyline in Dubai - Presented by Tohid Fetrat

Binghatti Aquarise Golden Visa: Where the Line Crosses the Ladder

Binghatti Aquarise, a 1,598 residence Business Bay tower, qualifies from the 2 bedroom apartment up; studios and 1 bedrooms do not.

Read the Binghatti Aquarise Golden Visa Guide
Binghatti Aquarise by Binghatti in Business Bay escrow account protection graphic with shield and padlock icons above an illuminated pool and curved residential facades in Dubai - Presented by Tohid Fetrat

Binghatti Aquarise Escrow, a First Abu Dhabi Bank Account in Business Bay

Binghatti Aquarise counts 1598 units under DLD project 3585; First Abu Dhabi Bank holds the escrow, certified 21.04% in May 2026.

Verify the Binghatti Aquarise Escrow Account

Approaching Handover

Between 21.04% and Handover: What Binghatti Aquarise Buyers Should Do Now

Early in an off-plan purchase the money moves ahead of anything you can see, because construction-linked instalments are triggered by certified readings rather than by the calendar. The larger part of this build still sits above the 14 May 2026 figure, which makes the quiet period between inspection cycles, not the handover notice, the window where the three steps below actually matter.

First, make sure every remaining instalment lands in the regulated trust account and nowhere else; the Binghatti Aquarise escrow account page shows the First Abu Dhabi Bank account registered to project 3585 and how certified milestones release funds from it.

Second, if your tier may carry residency, establish the eligibility timing now through the Binghatti Aquarise Golden Visa guide, because an off-plan unit is held by interim registration rather than a title deed until the Q4 2027 window closes.

Third, follow the record cycle by cycle. The Binghatti Aquarise May 2026 construction update sets the baseline every later reading gets measured against, and this page collects each new percentage as it is published.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Business Bay Structure

A build record is only half the picture; the other half is what is rising around it. These three pages put Aquarise's progress in its market, community and developer context:

Business Bay properties for sale featuring modern residential towers and premium Dubai skyline views Captured by Tohid Fetrat.

Business Bay Properties for Sale

Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.

See Business Bay Properties for Sale
Business Bay skyline view featuring Opus Tower Bugatti Residences by Binghatti The Binary by Omniyat and Ahad Tower with modern high rise architecture and urban city streets captured by Tohid Fetrat.

Business Bay Community Overview

Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.

Explore the Business Bay Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Aquarise Construction Updates Frequently Asked Questions

Binghatti Aquarise is an active DLD-registered project (number 3585) in its superstructure phase, recorded at 21.04% at the RERA inspection of 14 May 2026. The full record is in the inspection timeline above.

The 14 May 2026 inspection recorded 21.04% construction progress, the first dated percentage published for project 3585. The entry preceding it in the register reads zero percent and carries no inspection date, so those 21.04 points measure everything certified between the 15 March 2025 register start and that inspection, not one cycle of output. The inspector's findings are documented in the Binghatti Aquarise May 2026 update.

The developer-stated handover window for Binghatti Aquarise is Q4 2027. The DLD register for project 3585 records a construction start of 15 March 2025 and registration on 16 April 2025, and the most recent certified reading is 21.04% on 14 May 2026, which leaves 78.96 points to certify before delivery. This page updates each time a new inspection percentage is published.

Binghatti Aquarise comprises 1,598 residential units spread across studio through four-bedroom layouts, with a further 28 retail units at ground level and a total built-up area of 120,062.34 sq m. The DLD unit field currently displays 1,592 for project 3585; the developer project facts state 1,598, and 1,598 is the figure carried on this page.

The DLD register records the construction start for project 3585 as 15 March 2025, with its registration entry dated 16 April 2025. The first tracked inspection followed fourteen months later, on 14 May 2026, at 21.04%, and the derived pace for that span is set out in the pace analysis above.

The 14 May 2026 RERA report lists live packages across enabling and foundation, the substructure, the superstructure of both towers, and the internal and MEP trades. Several trades running at once is what places the 21.04% reading in the structural band rather than in groundworks, and it is also why a single figure understates how much of the site is active.

The RERA project description for 3585 records a shared podium of three basement levels plus ground and mezzanine, above which two separate structures rise: a 25-storey residential element topped by a mechanical level and roof, and a shorter six-storey element with its own roof. Both were in superstructure at the 21.04% reading of 14 May 2026.

The site is plot 261, set inside Business Bay a short distance from the Dubai Water Canal and a few minutes from Downtown Dubai. The district context around the plot is covered in the Business Bay community guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Aquarise construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.