Binghatti Cullinan Construction Update - November 2025

November 2025 Inspection Records Binghatti Cullinan at 0% Ahead of Construction Start in Al Jaddaf

No construction activity had started on the Al Jaddaf plot at the 25 November 2025 RERA inspection; the background image is a developer rendering, not site progress.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
25 November 2025Inspection Date
Q2 2027Expected Handover
4247DLD Project Number

Verified DLD Inspection Data

Binghatti Cullinan Construction Snapshot

A 0% baseline dated 25 November 2025 opens the Binghatti Cullinan record at the very start of the enabling and foundations band, logged six days before the 01 December 2025 construction start date recorded in the DLD register.

Project Name

Binghatti Cullinan

Project Number

4247

Project Status

Active

Construction Progress

0%

Inspection Date

25 November 2025

Construction Start

01 December 2025

Total Units

624 residences

Total Built Area

41,503.36 sq m

Expected Completion

Q2 2027

Data source: DLD project register reading dated 25 November 2025 and the RERA Independent Progress Monitoring Report for the same visit, which shows a Progress Status of N/A. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026, 333 days after this inspection; readings posted to the register after 25 November 2025 are not reflected on this page.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Binghatti Cullinan Construction Progress Summary

As the first entry in the Binghatti Cullinan record, the November 2025 visit has no earlier reading to measure against. RERA's Independent Progress Monitoring Report for 25 November 2025 sets out a planned basement, ground floor, four podium levels and 14 residential floors plus a roof, notes that no construction activity had started at the site, and leaves the Progress Status at N/A; the 0% figure is the DLD register reading for the same date.

On Record
  • Baseline RERA inspection of plot 300 on 25 November 2025
  • Project 4247 listed with United Arab Bank as trust account bank
  • Building configuration B + G + 4P + 14 residential floors + roof on file
Status at 0%
  • No construction activity started at the time of inspection
  • RERA Progress Status shown as N/A
  • Construction start of 01 December 2025 entered in the DLD register
  • Project registration dated 30 December 2025 in the same register
Ahead of Handover
  • Excavation and foundations for the basement level
  • Superstructure: ground floor, four podium levels, 14 residential floors
  • Facade, MEP and fit out across 624 residences and ground-floor retail
  • Handover in Q2 2027, registered completion date 30 June 2027
Next inspectionNo date is announced in advance; the next reading appears in the DLD project register after RERA's following site visit.
Completion targetQ2 2027 handover; the DLD record shows a registered completion date of 30 June 2027, about 19 months after this inspection.
Remaining distance100 percentage points: the entire build lies ahead of the 25 November 2025 baseline.

Payment Linked Progress

What 0% Progress Means for Binghatti Cullinan Buyers

Binghatti Cullinan is sold on a 20/50/30 plan: 20% on booking, 50% during construction and 30% on handover. With the November 2025 reading taken before any site works began, the entire construction share still sits ahead of buyers, and four checks matter most at this point.

Before the Booking Payment

Verify the escrow account

The booking payment and every construction instalment should go only to the DLD regulated escrow account registered for project 4247, which the RERA report lists with United Arab Bank. Binghatti Cullinan escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing the SPA

Read your SPA instalment schedule

The developer publishes the 50% construction share without dates, so check how your sale and purchase agreement spreads those instalments between booking and the Q2 2027 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Off-plan sales in Dubai are recorded with the Dubai Land Department through Oqood. Once your booking clears, check that the Oqood record names Binghatti Cullinan under project 4247, the project the DLD register shows as registered on 30 December 2025.

Every Cycle

Watch the first readings move

From a 0% baseline, the next few inspections show whether basement and foundation works have started to register. Binghatti Cullinan construction updates hub lists each reading in date order.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering at the baseline trades visible progress for runway: nothing stood on the plot in November 2025, and the full construction share of the plan falls between booking and the Q2 2027 handover. Every payment goes to the DLD-registered escrow account for project 4247, released against verified construction progress.

Entering at the 0% Baseline
  • No construction activity at the 25 November 2025 inspection
  • Handover scheduled for Q2 2027
  • 20% on booking, 50% during construction, 30% on handover
Typical Late Stage Entry
  • Structure standing and recorded before you commit
  • A wait to handover measured in months, not years
  • Less plan runway, with more of the price due near completion
AED 819K ≈ USD 223KStarting Price
20/50/30 Plan30% Due on Handover
Q2 2027Expected Handover
Ask What Is Available at Binghatti Cullinan

Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Binghatti Cullinan Project Details

Binghatti Cullinan by Binghatti in Al Jaddaf aerial project rendering of a white residential building with landscaped podium and swimming pool in Dubai - Presented by Tohid Fetrat
Al Jaddaf · Binghatti

At the November 2025 inspection, Binghatti Cullinan was still an unbuilt plot, planned as one curved building of 624 studio to 3 bedroom apartments over ground-floor retail, wrapped around a courtyard pool deck. Starting prices: AED 819K ≈ USD 223K.

Buyers committing before the structure rises carry construction risk for longer in exchange for the full 20/50/30 runway, with handover scheduled for Q2 2027 and a registered completion date of 30 June 2027 in the DLD record.

Binghatti Cullinan Project Guide

Site Context This Cycle

Explore Binghatti Cullinan Location on Dubai Map

Binghatti Cullinan occupies plot 300 in Al Jaddaf, which Binghatti's location map places just off Al Khail Road (E44) near Dubai Healthcare City, and the photographs filed with the 25 November 2025 RERA report show a cleared, hoarded plot with existing towers beyond it. On an infill site like this, basement excavation is the first package the readings will need to capture.

Al Jaddaf already has its road links to Sheikh Zayed Road (E11) and Al Khail Road, and the developer's map marks Al Jaddaf Metro Station on the Green Line close to the project, so buyers entering at 0% are waiting on a building rather than on a district; per Binghatti's location map, Downtown Dubai and Burj Khalifa sit 3 to 5 minutes away by car. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Binghatti Cullinan on Dubai Map

Buyer Resources for This Project

Investing in Binghatti Cullinan at the Pre-Construction Stage

Before the first concrete is poured, payment protection and residency eligibility outweigh handover logistics. Each resource below is matched to where Binghatti Cullinan stood at the November 2025 inspection.

Binghatti Cullinan by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the illuminated residential building and swimming pool at sunset in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Cullinan Construction Updates

This page: the 25 November 2025 inspection record for Binghatti Cullinan, taken before construction began.

Binghatti Cullinan by Binghatti in Al Jaddaf Golden Visa concept graphic featuring a gold card over an aerial rendering of a residential building in Dubai - Presented by Tohid Fetrat

Binghatti Cullinan Golden Visa: One Clear Route to Residency

Binghatti Cullinan, 624 residences in Al Jaddaf, qualifies only through the 3 bedroom apartment; studios, 1 and 2 bedrooms sit below.

Read Binghatti Cullinan Golden Visa Guide
Binghatti Cullinan by Binghatti in Al Jaddaf escrow account concept graphic showing a shield and padlock above a landscaped pool terrace and residential facade in Dubai - Presented by Tohid Fetrat

Binghatti Cullinan Escrow: An Al Jaddaf Account at United Arab Bank

Binghatti Cullinan in Al Jaddaf escrows 652 units with United Arab Bank, DLD project 4247, 0% certified November 2025.

Verify Binghatti Cullinan Escrow Account

Update Timeline

Other Binghatti Cullinan Construction Updates

This November 2025 page opens the Binghatti Cullinan series; each later inspection joins the hub once its reading is posted to the DLD register.

All Binghatti Cullinan Construction Updates

FAQs

Binghatti Cullinan Construction Progress in November 2025: Frequently Asked Questions

The DLD project register shows 0% for Binghatti Cullinan, project 4247, at the inspection dated 25 November 2025. It is the first reading on record for the project, so there is no earlier figure to compare it with and no change to report for the month.

No. Handover remains scheduled for Q2 2027, and the DLD record carries a registered completion date of 30 June 2027, the last day of that quarter. A single baseline reading cannot show how quickly the build will move, and registered completion dates can be revised in the register between cycles, so the date is worth reading again whenever a new reading is posted. How each inspection cycle feeds the record is covered on the Binghatti Cullinan construction updates hub.

The register lists the inspection on 25 November 2025, a construction start of 01 December 2025 six days later, and a project registration date of 30 December 2025, 35 days after the visit. Neither the register nor the RERA report explains the sequence, so the dates are shown here exactly as recorded and the 0% figure is read as the baseline the project starts from.

RERA's Independent Progress Monitoring Report for that date notes that no construction activity had started at the site and shows the Progress Status as N/A. It describes the planned building as a basement, ground floor, four podium levels and 14 residential floors plus a roof on plot 300, and names United Arab Bank as the trust account bank. The report itself prints no percentage; the 0% figure comes from the DLD register.

No. The image at the top of this page is a developer rendering of the planned building, used because no on-site construction photographs were supplied for November 2025. It shows the proposed appearance of Binghatti Cullinan, not completed site works or construction progress.

Search project number 4247 in the Dubai REST app or the DLD project register, where each RERA inspection appears as a dated reading with its own percentage. Any reading dated after 25 November 2025 is newer than the figure on this page, and later readings are added to the Binghatti Cullinan construction updates hub as they are recorded.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the November 2025 inspection record for Binghatti Cullinan correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts