Binghatti Cullinan by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the illuminated residential building and swimming pool at sunset in Dubai - Presented by Tohid Fetrat

Binghatti · Al Jaddaf

Binghatti Cullinan Construction Updates

A Curved Al Jaddaf Residence, Tracked from Its November 2025 Baseline

Binghatti Cullinan read 0% in the DLD register on 25 November 2025, a baseline logged before site works had begun on its curved Al Jaddaf building.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
25 November 2025Latest RERA Inspection
624 residential unitsTotal Units
Project 4247DLD Registration

Construction Snapshot

Binghatti Cullinan at a Glance

Binghatti Cullinan is a single Binghatti building in Al Jaddaf: 624 residences above ground-floor retail, planned as a basement, ground floor, four podium levels and 14 residential floors plus a roof, a configuration on which the developer fact sheet and RERA's 25 November 2025 report agree. Its DLD file, project 4247, runs in an order worth noticing: the only inspection on this page, dated 25 November 2025 at 0%, comes before both the 01 December 2025 construction start and the 30 December 2025 registration, so this record opens at a true starting line rather than partway up a structure. Handover is scheduled for Q2 2027, the quarter that closes on the registered completion date below.

DLD Project Number

4247

Project Status

Active

Construction Start

01 December 2025

Total Units

624 residential units

Total Built-Up Area

41,503.36 sq m

Registered Completion Date

30 June 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Cullinan Construction Update Timeline

One dated reading makes up the Binghatti Cullinan record so far: 0% in the DLD register on 25 November 2025, taken at a visit where RERA found no construction activity on plot 300 and left the Progress Status at N/A. That is why the single dot below sits at the very left of the track, six days ahead of the recorded construction start, and why the table holds one row linking the full November 2025 update.

Inspection MonthConstruction ProgressInspection DateFull Update
November 20250%25 November 2025View the November 2025 update

Pace Analysis

How Fast Binghatti Cullinan Has Been Built

A single 0% reading cannot show how quickly Binghatti Cullinan is rising; that needs a second dated inspection. What the record does fix are the intervals around the 25 November 2025 baseline:

  • 25 Nov 2025 inspection to the 01 Dec 2025 recorded construction start6 days
  • 25 Nov 2025 inspection to the 30 Dec 2025 DLD registration35 days
  • 01 Dec 2025 recorded start to the 30 Jun 2027 registered completion dateAbout 19 months
  • 25 Nov 2025 reading to the October 2026 preparation of this page333 days

Read together, those intervals describe a project caught at its starting line. RERA's visit came before the start and registration dates were entered, so the 0% figure is a baseline rather than a verdict: nothing on plot 300 had been built yet, and the whole sequence from basement excavation through four podium levels, 14 residential floors and the roof still lay ahead of it. Between the recorded start and the 30 June 2027 registered completion date sit roughly 19 months, which is the window the Q2 2027 handover depends on. The reading that matters next is the first one dated after 01 December 2025: it is the earliest point at which works on this plot can register as a percentage, and the first pair of readings from which a measured trend can be drawn. For an end user, that figure frames the handover conversation; for an investor, it is the first evidence to set beside the 50% of the price that the 20/50/30 plan schedules during construction.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Cullinan and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Cullinan at Al Jaddaf

A 0% reading from November 2025 only makes sense next to the building it measures. The full project guide covers what this record is tracking toward:

Binghatti Cullinan by Binghatti in Al Jaddaf aerial project rendering of a white residential building with landscaped podium and swimming pool in Dubai - Presented by Tohid Fetrat

Binghatti Cullinan: Al Jaddaf Apartments Around an Inner Courtyard

Binghatti Cullinan is an off-plan Binghatti building in Al Jaddaf with 624 studio to three bedroom apartments around a landscaped courtyard.

View the Binghatti Cullinan Project Guide

Considering a Pre-Construction Entry?

Binghatti Cullinan is listed as Units Available as of this update, and the choice of floor, orientation and layout is widest before the building takes shape. If the baseline on this page is what brought you here, ask me what is open now before the selection narrows.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Cullinan Build Stages, Mapped to the Inspections

With one reading on file, only the first stage below has a dated entry; the other four are anchored to RERA's project description for plot 300 and to the register's 30 June 2027 completion date, and each will gain its own inspection window as readings are posted.

Current PhaseNov 2025 to Dec 2025, 0% on 25 Nov 2025

Baseline, Registration and Site Start

The 25 November 2025 inspection found no construction activity and the register read 0%; the DLD record then logs a 01 December 2025 start and 30 December 2025 registration.

After 01 Dec 2025, no reading yet

Basement Excavation and Foundations

Digging out the single basement level and casting its foundations come first on plot 300; no inspection on this page postdates the recorded start, so this stage is still unmeasured.

Ahead of the Nov 2025 baseline

Ground Floor, Four Podiums and 14 Residential Floors

Every level in RERA's B + G + 4P + 14 residential floors + roof description rises in this window, up to the roof; none of it had begun at the November 2025 visit.

Ahead of the Nov 2025 baseline

Curved Facade, Courtyard and Fit-Out

The glass facade with its geometric grid, the inner courtyard pool deck, and the fit-out of 624 residences and ground-floor retail all follow the structure.

Registered completion 30 Jun 2027

Completion and Handover

Handover is scheduled for Q2 2027, the quarter ending on the register's 30 June 2027 completion date; this record closes with the final inspection reading.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Cullinan's own record.

Buyer Position

Tracking Your Position at Binghatti Cullinan

This page is one of four project resources that together cover a Binghatti Cullinan purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Cullinan by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the illuminated residential building and swimming pool at sunset in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Cullinan Construction Updates

This page: the Binghatti Cullinan inspection record, opened at the 0% baseline of 25 November 2025.

Binghatti Cullinan by Binghatti in Al Jaddaf Golden Visa concept graphic featuring a gold card over an aerial rendering of a residential building in Dubai - Presented by Tohid Fetrat

Binghatti Cullinan Golden Visa: One Clear Route to Residency

Binghatti Cullinan, 624 residences in Al Jaddaf, qualifies only through the 3 bedroom apartment; studios, 1 and 2 bedrooms sit below.

Read the Binghatti Cullinan Golden Visa Guide
Binghatti Cullinan by Binghatti in Al Jaddaf escrow account concept graphic showing a shield and padlock above a landscaped pool terrace and residential facade in Dubai - Presented by Tohid Fetrat

Binghatti Cullinan Escrow: An Al Jaddaf Account at United Arab Bank

Binghatti Cullinan in Al Jaddaf escrows 652 units with United Arab Bank, DLD project 4247, 0% certified November 2025.

Verify the Binghatti Cullinan Escrow Account

Approaching Handover

Between 0% and Handover: What Binghatti Cullinan Buyers Should Do Now

At the 0% baseline of 25 November 2025 the useful work for a buyer is on paper, not on site: which account receives the money, which apartment type serves your residency plans, and how the 50% construction share is spread across a build that had not started in November 2025. Under the 20/50/30 plan the 20% first instalment and the 4% DLD fee fall due at reservation, so the three checks below belong before any money moves, not after.

First, before the 20% instalment, compare the account on your payment instructions with the record on the Binghatti Cullinan escrow verification page, so every payment for project 4247 lands in the United Arab Bank escrow account and nowhere else.

Second, if residency is part of the plan, settle eligibility before you pick a unit: the Binghatti Cullinan Golden Visa eligibility guide explains why the 3 bedroom tier is the only one that reaches the property value threshold on price.

Third, set your SPA's construction-instalment schedule against the plan in the Binghatti Cullinan payment plan overview, since the developer publishes the 50% construction share without dates.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

A building recorded at 0% in November 2025 is better judged against what already stands around it. These three pages set Binghatti Cullinan's record beside the Al Jaddaf market, the community it will join, and the developer behind the build:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Cullinan Construction Updates Frequently Asked Questions

Binghatti Cullinan, DLD project 4247 with status Active, sits at its pre-construction baseline in the record on this page: the DLD register shows 0% at the inspection of 25 November 2025, and RERA's report for that visit notes that no construction activity had started on plot 300. Readings dated after 25 November 2025 may since have been posted, and the dated entries are laid out in the inspection timeline above.

Progress at Binghatti Cullinan is tracked through dated readings in the DLD project register for project 4247, cross-checked against RERA's Independent Progress Monitoring Report for each visit. For 25 November 2025 the register shows 0% while the RERA report prints no percentage and a Progress Status of N/A, so this page attributes the figure to the register. Each dated reading becomes one timeline row linked to its own monthly update.

The Binghatti Cullinan timeline holds one dated entry: 0% in the DLD register on 25 November 2025, documented in the Binghatti Cullinan November 2025 construction update. Around it, the register records a construction start of 01 December 2025, registration on 30 December 2025 and a registered completion date of 30 June 2027. With no earlier reading on file, there is no change in percentage points to state yet.

Both point to the same quarter. Binghatti Cullinan's handover is scheduled for Q2 2027, and the DLD register carries a registered completion date of 30 June 2027, the final day of that quarter. At the 0% reading of 25 November 2025, about 19 months separated the recorded 01 December 2025 construction start from that date, and this page is revised if the register changes it.

Binghatti Cullinan is planned as 624 residences, from studios to 3 bedroom apartments, above ground-floor retail in one building of a basement, ground floor, four podium levels and 14 residential floors plus a roof. Binghatti's fact sheet and RERA's 25 November 2025 report give the same configuration, B + G + 4P + 14 residential floors + roof, and the fact sheet puts the plot at 6,428.84 sq m (69,199 sq ft).

The DLD register records 01 December 2025 as the construction start for Binghatti Cullinan, six days after the first tracked reading of 0% on 25 November 2025, when RERA found no construction activity at the site. Both dates are shown exactly as recorded, and no reading on this page yet postdates the start date.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Cullinan construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status