Binghatti · Jumeirah Village Triangle
Binghatti Luxuria Construction Updates
One Jumeirah Village Triangle Tower, Recorded from Its Foundations Up
Binghatti Luxuria reached 7.04% on the DLD register at its 17 September 2026 inspection, the first dated reading, fixing this Jumeirah Village Triangle tower's foundation-stage baseline.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Luxuria at a Glance
Binghatti Luxuria is Binghatti's single tower of 457 residences in Jumeirah Village Triangle, planned as three basement levels, a ground-floor retail level, four podium levels and 24 residential floors. Its register record opens on 1 January 2026 with the recorded construction start, then DLD registration on 8 January 2026, and the 17 September 2026 inspection put it at 7.04%. With three basement levels planned beneath the podium, the opening stretch of this record is work below street level, and that is exactly what the inspection report for that date describes: enabling and foundation works ongoing at site.
4299
Active
1 January 2026
457 Residential
25,415.45 sq m
30 July 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Luxuria Construction Update Timeline
The Binghatti Luxuria record holds one dated inspection so far: 7.04% on 17 September 2026, reached 259 days after the recorded 1 January 2026 start. The register also shows a previous-inspection value of 0% with no date beside it, so that value is named in the track description rather than drawn as a dated dot, and the single table row links the full September 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 7.04% | 17 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Binghatti Luxuria Has Been Built
With one dated reading, Binghatti Luxuria has no inspection-to-inspection pace yet. What the record does support is two pieces of arithmetic, not a forecast, each expressed in 30-day months:
- 1 Jan 2026 start to 17 Sep 2026: enabling and foundations, 7.04 points over 259 daysAbout 0.8 points per month
- 17 Sep 2026 to 30 Jul 2027 registered completion: 92.96 points over 316 daysAbout 8.8 points per month
The two figures measure different things. The first spreads the 7.04% recorded on 17 September 2026 across everything since the 1 January 2026 start, a period the inspection report describes as enabling and foundation works, beneath a tower whose three basement levels come before any floor rises above ground. The second is simply the 92.96 points left, divided by the 316 days to the registered completion date of 30 July 2027. Neither is a prediction; the distance between them is the figure that each new register reading will narrow or widen, and the second dated inspection will give Luxuria its first measured pace between two known dates. For an end user, that next reading is the first one to set against the Q3 2027 expected handover; for an investor, the run of readings from the foundations to the four podium levels shows how construction moves between instalments of the 50% construction share.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Luxuria and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Luxuria at Jumeirah Village Triangle
A foundation-stage percentage only matters next to what is being delivered. The full project guide covers the tower this record is tracking:

Binghatti Luxuria: One JVT Tower in a Satin-Chrome Exoskeleton
Binghatti Luxuria is a single Binghatti tower in Jumeirah Village Triangle, with 457 studio, 1 bedroom and 2 bedroom apartments.
View the Binghatti Luxuria Project GuideConsidering an Early-Stage Entry?
Availability at Binghatti Luxuria changes as the tower moves out of its foundations and toward the podium levels. If the record on this page is what brought you here, ask me for current availability before you settle on a unit type.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Luxuria Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates Binghatti Luxuria has actually recorded, from the 1 January 2026 start to the 7.04% reading of 17 September 2026. The stages after the foundations carry no inspection window yet, because no reading has reached them; they fill in as the register posts new figures.
Construction Start and DLD Registration
The register dates the construction start to 1 January 2026, then DLD registration on 8 January 2026 under project number 4299, with Mashreq Bank listed as the trust account bank.
Enabling Works and Foundations
The 17 September 2026 inspection noted enabling and foundation works ongoing at site, with the register at 7.04% against a previous-inspection field of 0%, undated.
Basements, Retail Level and Podium
Three basement levels, the ground-floor retail level and four podium levels; the 17 September 2026 report records enabling and foundation works only, so none of these levels has a reading of its own yet.
24 Residential Floors and Exoskeleton Facade
The 24 residential floors holding the 457 residences, wrapped in the satin-chrome exoskeleton that Binghatti describes as giving the tower solar shading and privacy.
Fit-Out, Amenity Deck and Handover
Apartment interiors, the 5th floor amenity deck and building systems, ahead of handover, expected in Q3 2027, with 30 July 2027 as the registered date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Luxuria's own record.
Buyer Position
Tracking Your Position at Binghatti Luxuria
This page is one of four project resources that together cover a Binghatti Luxuria purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Luxuria Construction Updates
This page: the dated register record for Binghatti Luxuria, from the January 2026 start to handover.

Binghatti Luxuria Golden Visa: 2 Bedroom Closest to the AED 2M Line
At Binghatti Luxuria, Binghatti's single tower in Jumeirah Village Triangle, no apartment type clears the AED 2M Golden Visa threshold.
Read the Binghatti Luxuria Golden Visa Guide
Binghatti Luxuria Escrow Account at Mashreq Bank, Project 4299
Binghatti Luxuria, DLD project 4299, escrows its 457 residences at Mashreq Bank and read 7.04% at the September 2026 inspection.
Verify the Binghatti Luxuria Escrow AccountApproaching Handover
Between 7.04% and Handover: What Binghatti Luxuria Buyers Should Do Now
Under the 20/50/30 plan, 20% is paid on booking, 50% is spread over construction on the developer's schedule, and 30% falls at the Q3 2027 handover, so at the 17 September 2026 reading of 7.04% the construction share is the part of the price that follows this record. Terms agreed before the SPA is signed are the hardest to change afterwards, so the three steps below come first, not after the first construction instalment falls due.
First, confirm that every booking and construction payment goes to the escrow account registered for project 4299; the Binghatti Luxuria escrow account page shows how to match the Mashreq Bank account to the register.
Second, if residency is part of the plan, read the Binghatti Luxuria Golden Visa analysis before choosing a unit size, since every apartment type here is priced below the property threshold on its own.
Third, set the three shares against your budget with the Binghatti Luxuria prices and payment plan, then check whether your SPA schedules the 50% construction share against dates or against build milestones.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Jumeirah Village Triangle Structure
A foundation-stage record reads differently once you see what already surrounds it. These three pages place the 7.04% recorded on 17 September 2026 in its market, community, and developer context:

Jumeirah Village Triangle Properties for Sale
Villas, townhouses, apartments and off-plan tower units currently available across the community's nine districts.
See Jumeirah Village Triangle Properties for Sale
Jumeirah Village Triangle by Nakheel: Villas, Townhouses, Apartments and Nine Residential Districts
Explore JVT's nine residential districts, garden villas, townhouses, apartment towers, community parks, schools and upcoming developments in Dubai.
Explore the Jumeirah Village Triangle Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Luxuria Construction Updates Frequently Asked Questions
As of the 17 September 2026 inspection, Binghatti Luxuria (DLD project 4299, status Active) was in its enabling and foundation stage, with the DLD register showing 7.04% and the RERA progress status reading Main Contract, Progressing. The dated record is in the inspection timeline above.
The 17 September 2026 inspection put Binghatti Luxuria at 7.04% on the DLD register, 7.04 points above the previous-inspection field of 0%, which the register shows without a date. The inspection report from that visit noted enabling and foundation works ongoing at site; the full record is in the Binghatti Luxuria September 2026 construction update.
The DLD register gives 30 July 2027 as the registered completion date for Binghatti Luxuria, a date inside the Q3 2027 expected handover and not yet passed as of 1 November 2026. At the 17 September 2026 reading of 7.04%, 92.96 points were still to go across the 316 days to that date. If the register revises the date, the change appears in the project 4299 entry, and this timeline records the new date next to the reading that accompanies it.
Binghatti Luxuria holds 457 residences, all studio, 1 bedroom and 2 bedroom apartments, in a single tower planned as three basement levels, a ground-floor retail level, four podium levels and 24 residential floors. Binghatti's fact sheet places the tower on a 3,131.72 sq m (33,709.52 sq ft) plot; that figure is the land parcel, not the built-up area of the building.
The DLD register records 1 January 2026 as the construction start for Binghatti Luxuria and 8 January 2026 as its registration date. The first dated reading came 259 days after the start: 7.04% at the inspection of 17 September 2026.
The percentage comes from the Dubai Land Department project register for Binghatti Luxuria, project 4299, as shown in the Dubai REST app: 7.04% on 17 September 2026. The RERA Independent Progress Monitoring Report dated 17 September 2026 adds the works note and the progress status, without a percentage. The general method is set out on the Dubai Construction Updates tracking guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Luxuria construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.