Binghatti Spectre Construction Update - February 2026

February 2026 Inspection Records a 0% Baseline for Binghatti Spectre in Al Jaddaf

The 9 February 2026 RERA inspection found no construction activities started at Binghatti Spectre, so this first DLD register reading sets the 0% baseline for both towers.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
9 February 2026Inspection Date
Q4 2028Expected Completion
4370DLD Project Number

DLD Register and RERA Inspection Data

Binghatti Spectre Construction Snapshot

A 0% baseline dated 9 February 2026 places Binghatti Spectre at the very start of its construction record, the stage where registration, escrow and the payment plan shape a buyer's decisions more than anything visible on site.

Project Name

Binghatti Spectre by Binghatti

Project Number

4370

Project Status

Active

Construction Progress

0%

Inspection Date

9 February 2026

Construction Start

1 September 2026

Total Units

966 units

Total Built Area

81,831.63 sq m

Expected Completion

31 December 2028

Data source: the Dubai Land Department project register reading of 0% dated 9 February 2026, and the RERA Independent Progress Monitoring Report of the same date, which records Progress Status N/A and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This is the reading supplied for February 2026; it was 258 days old when this page was prepared on 25 October 2026. The hero image is a Binghatti project rendering, not a site photograph. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Binghatti Spectre Construction Progress Summary

With no earlier inspection on record, there is no movement to measure: the February 2026 visit is the reference point that every subsequent Binghatti Spectre reading will be compared with. The inspector noted that no construction activities had been started at the time of inspection, and the register, as read in October 2026, records a construction start of 1 September 2026 and a project registration of 13 October 2026, both dated after this inspection.

Completed
  • Baseline RERA inspection held on 9 February 2026
  • Project 4370 listed as Active in the DLD register
  • Trust account bank named: Arab Bank for Investment and Foreign Trade (Al Masraf)
In Progress at 0%
  • No construction activities started at the time of inspection
  • RERA Progress Status recorded as N/A, with 0% in the DLD register
  • Register construction start of 1 September 2026, dated after this visit
Ahead of Handover
  • Basement levels and the shared multi-level podium
  • Twin towers of 26 floors, with the office units in Tower B
  • 712 residences and the ground-floor retail shops
  • Handover expected in Q4 2028, registered completion 31 December 2028
Next inspectionNo date is published in advance; the next reading appears in the DLD project register after the next RERA site visit, and this record updates with it.
Completion targetQ4 2028 expected handover, with a registered completion date of 31 December 2028, about 35 months after this inspection.
Remaining distance100 percentage points separate the 9 February 2026 baseline from completion.

Payment Linked Progress

What 0% Progress Means for Binghatti Spectre Buyers

Binghatti Spectre runs on a 10/40/50 plan: 10% as the down payment, 40% during construction and 50% on handover. At a 0% baseline almost every installment still lies ahead, so the protections that apply before money moves count for more than the reading itself. At this stage of Binghatti Spectre, four actions matter most.

Before Any Installment

Verify the escrow account

Installments for Binghatti Spectre should go only to the DLD regulated escrow account registered for project 4370, held at Al Masraf. Binghatti Spectre escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing the SPA

Read the 40% construction schedule

The plan sets the shares, but the timing of the 40% due during construction is defined in your sale and purchase agreement: confirm the construction schedule with Binghatti and check whether installments follow dates or register readings from this 0% baseline. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the dated register readings.

After Booking

Confirm your Oqood registration

Oqood is the Dubai Land Department's interim registration for off-plan units, and it is your registered interest in the unit until a title deed is issued at handover. Check that the record names you, your unit and project 4370 before the 40% construction share begins.

Every Cycle

Track the readings that follow

From a 0% baseline the record has the full build still to show, with handover expected in Q4 2028. Binghatti Spectre construction updates hub logs each dated reading as it is published.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at the 0% Baseline?

Entering at the very start of the record trades certainty for runway: no construction activities had started at the February 2026 inspection, the delivery horizon is long, and most of the price is still ahead of you. Every installment goes to the DLD-registered escrow account for project 4370, released against engineer-verified construction progress.

Entering Now at 0%
  • 10% down payment, then 40% spread across construction
  • Handover expected in Q4 2028, years after this reading
  • Full build risk carried from the 0% baseline onward
Typical Advanced Stage Entry
  • Structure visible in the inspection record before you commit
  • Shorter wait between signing and handover
  • Less installment runway before the balance falls due
AED 775K ≈ USD 211KStarting Price
10/40/50 Plan50% Due on Handover
Q4 2028Expected Handover
Ask What Is Available at Binghatti Spectre

Limited units available per the project page at the time of writing; availability shifts between cycles. Confirm the construction schedule for the 40% share with Binghatti before you commit.

About the Development

Binghatti Spectre Project Details

Binghatti Spectre by Binghatti in Al Jaddaf project rendering of two residential towers beside an elevated road in daylight in Dubai - Presented by Tohid Fetrat
Al Jaddaf · Binghatti

Measured against the February 2026 baseline, Binghatti Spectre is an off-plan purchase at its earliest point: 712 residences from studio to 3 bedroom, plus office units in Tower B, planned across two 26-floor towers on a shared podium. Starting prices: AED 775K ≈ USD 211K.

For buyers entering at this stage, the trade off is the longest wait in exchange for the lightest upfront commitment, with half of the price due on handover, expected in Q4 2028.

Binghatti Spectre Project Guide

Site Context This Cycle

Explore Binghatti Spectre Location on Dubai Map

Binghatti places Spectre at the northern gateway of the Al Jaddaf Waterfront, on a plot beside the D68 corridor with ramp access onto Al Khail Road (E44). At the February 2026 inspection the plot showed no construction activities, so in this cycle its position matters for what it will offer rather than for any works: depending on orientation, Binghatti describes outlooks north and northwest across Za'abeel toward Downtown Dubai, or east and southeast toward Dubai Creek and the Mohammed bin Rashid Library.

The district around the plot is built out: Binghatti's location map puts the Al Jaddaf and Creek Metro Stations about 2 minutes away and Dubai Healthcare City about 3 minutes away, so a buyer committing at the baseline is waiting on the building itself, not on roads or transit still to arrive. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Binghatti Spectre on Dubai Map

Buyer Resources for This Project

Investing in Binghatti Spectre at the Baseline Stage

At a 0% baseline the open questions concern payment protection and residency eligibility rather than handover logistics. Each resource below is matched to where Binghatti Spectre stood in February 2026.

Binghatti Spectre by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of illuminated towers and surrounding roads at night in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Spectre Construction Updates

This page: the 9 February 2026 baseline reading of 0% and the RERA inspection note.

Binghatti Spectre by Binghatti in Al Jaddaf Golden Visa concept graphic with a gold card over a sunset cityscape and rendered towers in Dubai - Presented by Tohid Fetrat

Binghatti Spectre Golden Visa: Only the 3 Bedroom Apartments

Binghatti Spectre, 712 residences in two 26-floor Al Jaddaf towers, qualifies only through 3 bedroom apartments; every other type sits below.

Read Binghatti Spectre Golden Visa Guide
Binghatti Spectre by Binghatti in Al Jaddaf escrow account concept graphic with a shield and padlock above illuminated residential towers in Dubai - Presented by Tohid Fetrat

Binghatti Spectre Escrow: A 966-Unit Al Jaddaf Account

Binghatti Spectre, DLD project 4370, escrows 966 units with Arab Bank for Investment & Foreign Trade, 0% certified February 2026.

Verify Binghatti Spectre Escrow Account

Update Timeline

Other Binghatti Spectre Construction Updates

February 2026 is the first dated reading in the Binghatti Spectre record. The hub collects every inspection that follows, reading by reading, from this 0% baseline toward handover.

All Binghatti Spectre Construction Updates

FAQs

Binghatti Spectre Construction Progress in February 2026: Frequently Asked Questions

The Dubai Land Department project register shows Binghatti Spectre, project 4370, at 0% as of the inspection dated 9 February 2026. It is the first reading on record, so there is no earlier inspection to compare it with and no change to report; the RERA monitoring report of the same date lists Progress Status N/A and prints no percentage of its own.

Handover is expected in Q4 2028, and the register records a completion date of 31 December 2028, about 35 months after the 9 February 2026 inspection. A 0% baseline does not show whether that date will hold: registered completion dates can be revised between inspection cycles, and any revision would be dated in a subsequent update.

The Independent Progress Monitoring Report dated 9 February 2026 notes that, at the time of inspection, no construction activities had been started. It names Arab Bank for Investment and Foreign Trade (Al Masraf) as the trust account bank and shows the RERA Progress Status as N/A. The register lists two inspection photos with the record; they are not reproduced on this page.

The register, as read in October 2026, records a construction start of 1 September 2026 and a project registration of 13 October 2026, both after the 9 February 2026 inspection. The record states no reason for that order, so this page prints the dates exactly as recorded and treats the 0% reading as the baseline for the project rather than as a measure of site activity.

In the Dubai REST app from the Dubai Land Department, look up the project by its name or by project number 4370. The project details screen lists inspection reports by date, and the entry for 9 February 2026 shows 0% current progress; the same screen carries the registered start, registration and completion dates.

No date is published in advance. A new reading is added to the DLD project register after each RERA site visit, and readings after 9 February 2026 may have been posted by the time you read this, so check the register first. How the cycle of readings works is explained on the Binghatti Spectre construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the February 2026 inspection record for Binghatti Spectre correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts