Binghatti Spectre by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of illuminated towers and surrounding roads at night in Dubai - Presented by Tohid Fetrat

Binghatti · Al Jaddaf

Binghatti Spectre Construction Updates

The Dated Register Record for Twin 26-Floor Towers in Al Jaddaf

Binghatti Spectre stood at 0% in the DLD register on 9 February 2026, the baseline every subsequent reading of its two Al Jaddaf towers will measure against.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
9 February 2026Latest RERA Inspection
966 units (DLD)Total Units
Project 4370DLD Registration

Construction Snapshot

Binghatti Spectre at a Glance

Binghatti Spectre is Binghatti's mixed-use pair of 26-floor towers in Al Jaddaf, planned for 712 residences with office units in Tower B and ground-floor retail shops. Its construction record opens at 0% in the DLD register on 9 February 2026, and the anchors below are the registered figures behind that record. Because that single inspection is dated before both the register's 1 September 2026 start and its 13 October 2026 registration, the order of the dates is itself part of what this page keeps on file.

DLD Project Number

4370

Project Status

Active

Construction Start

1 September 2026 (DLD register)

Total Units

966 units (DLD)

Total Built-Up Area

81,831.63 sq m

Registered Completion Date

31 December 2028 (DLD), handover expected Q4 2028

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Spectre Construction Update Timeline

One dated inspection makes up the Binghatti Spectre record so far: the 9 February 2026 RERA visit, which found no construction activities started and left the DLD register at 0%. The register then dates the construction start to 1 September 2026 and the project registration to 13 October 2026, both after that visit, so the single dot below sits on the baseline until a second dated reading joins it. The table row links the full February 2026 update.

Inspection MonthConstruction ProgressInspection DateFull Update
February 20260%9 February 2026View the February 2026 update
!

Reading the dates: the only RERA inspection, on 9 February 2026, found no construction activities started and recorded Progress Status N/A, with the DLD register at 0%. The register then dates the construction start to 1 September 2026 and the project registration to 13 October 2026, both after that visit, against a registered completion of 31 December 2028; this page prints all four dates exactly as the register shows them.

Pace Analysis

How Fast Binghatti Spectre Has Been Built

A pace figure needs two dated readings, and the Binghatti Spectre record holds one: 0% in the DLD register on 9 February 2026. What the record does hold is a set of dated register milestones:

  • 9 Feb 2026: baseline RERA inspection, no construction activities started0% Register Reading
  • 1 Sep 2026: construction start, as entered in the DLD registerRegister Start
  • 13 Oct 2026: project registration date in the DLD registerDLD Registration
  • 31 Dec 2028: registered completion, inside the Q4 2028 handover quarterRegistered Completion

Read in date order, the list runs against the usual sequence: the only inspection sits almost seven months before the register's start date and about eight months before registration, and this page prints all four dates exactly as the register shows them. From the 1 September 2026 start to the 31 December 2028 registered completion, the register allows about 28 months for basement levels, a shared podium and two 26-floor towers (date arithmetic, not a forecast). The first measured pace arrives with the second dated reading. Until then, an end user is relying on the registered schedule rather than on recorded movement, and an investor committing now is entering before the record has shown any change at all from its 9 February 2026 baseline.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Spectre and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Spectre at Al Jaddaf

A baseline reading only means something beside what is planned for the plot. The full project guide covers what buyers are tracking toward on this page:

Binghatti Spectre by Binghatti in Al Jaddaf project rendering of two residential towers beside an elevated road in daylight in Dubai - Presented by Tohid Fetrat

Binghatti Spectre: Twin 26-Floor Towers in Al Jaddaf

Binghatti Spectre pairs two 26-floor towers on a shared podium at the Al Jaddaf Waterfront, with 712 residences and office units.

View the Binghatti Spectre Project Guide

Considering a Pre-Construction Entry?

Limited units are available at Binghatti Spectre at the time of writing, and what remains can change between releases. If the baseline on this page is what brought you here, ask me what is open now before you weigh a specific unit.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Spectre Build Stages, Mapped to the Inspections

Each stage below is pinned to the Binghatti Spectre record as it stands: only the first carries a dated reading, and the four that follow are named for this building's basements, podium and two towers but wait for inspections to date them.

Current Phase9 Feb 2026 at 0%

Baseline Inspection and Registration

The 9 February 2026 RERA visit found no construction activities started; the register dates the start to 1 September 2026 and registration to 13 October 2026.

From the 1 Sep 2026 register start

Site Activation and Basement Works

Enabling works and the basement levels beneath both towers; no inspection in this record has dated this stage yet.

Not yet recorded

Shared Podium Structure

The multi-level podium joining the two towers, with ground-floor retail shops at street level, still awaiting its first dated reading.

Not yet recorded

Twin 26-Floor Tower Structure

Floor plates and cores rising across both towers, with Tower B carrying the office units alongside residences, ahead of the record so far.

Toward Q4 2028, registered 31 Dec 2028

LED Facade, Amenity Deck, and Delivery

The crystalline glass facade with its LED grid, the amenity deck, interior finishing and handover, set against a registered completion of 31 December 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Spectre's own record.

Buyer Position

Tracking Your Position at Binghatti Spectre

This page is one of four project resources that together cover a Binghatti Spectre purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Spectre by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of illuminated towers and surrounding roads at night in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Spectre Construction Updates

This page: the dated Binghatti Spectre register record, from the 9 February 2026 baseline toward handover.

Binghatti Spectre by Binghatti in Al Jaddaf Golden Visa concept graphic with a gold card over a sunset cityscape and rendered towers in Dubai - Presented by Tohid Fetrat

Binghatti Spectre Golden Visa: Only the 3 Bedroom Apartments

Binghatti Spectre, 712 residences in two 26-floor Al Jaddaf towers, qualifies only through 3 bedroom apartments; every other type sits below.

Read the Binghatti Spectre Golden Visa Guide
Binghatti Spectre by Binghatti in Al Jaddaf escrow account concept graphic with a shield and padlock above illuminated residential towers in Dubai - Presented by Tohid Fetrat

Binghatti Spectre Escrow: A 966-Unit Al Jaddaf Account

Binghatti Spectre, DLD project 4370, escrows 966 units with Arab Bank for Investment & Foreign Trade, 0% certified February 2026.

Verify the Binghatti Spectre Escrow Account

Approaching Handover

Between 0% and Handover: What Binghatti Spectre Buyers Should Do Now

At 0% on 9 February 2026, Binghatti Spectre has its whole build ahead of it, and on the 10/40/50 plan most of a buyer's money lies ahead too: 10% as the down payment, 40% during construction and 50% on handover in Q4 2028. The timing of that 40% is set in each SPA rather than by the register, so confirm the construction schedule with Binghatti and complete the three checks below before the first construction installment falls due, not after it.

First, confirm where the money goes: the Binghatti Spectre escrow account page shows how to match the Al Masraf trust account to project 4370 before any transfer.

Second, if residency is part of the plan, settle eligibility early through the Binghatti Spectre Golden Visa guide, since only the 3 bedroom tier from AED 3.10M ≈ USD 844K clears the AED 2M ≈ USD 545K threshold.

Third, weigh the unit itself against a Q4 2028 horizon using the Binghatti Spectre project guide, where layouts, size bands and the Tower B office units are set out.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

A baseline record reads best beside what already stands around it. These three pages place Binghatti Spectre's February 2026 starting point in its market, community and developer context:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Spectre Construction Updates Frequently Asked Questions

Binghatti Spectre is an active DLD-registered project (number 4370) at the very start of its construction record: the reading supplied for February 2026 shows 0% in the DLD project register as of the 9 February 2026 inspection, when no construction activities had been started. That reading was 258 days old on 25 October 2026, so newer readings may already be posted; the full record is in the inspection timeline above.

The record holds a single dated reading: 0% in the DLD project register from the RERA inspection of 9 February 2026, with the RERA Progress Status shown as N/A. As the first reading, it has no earlier figure to compare with, so no point change applies; that inspection is covered in the Binghatti Spectre February 2026 construction update.

The DLD register gives Binghatti Spectre a registered completion date of 31 December 2028, which falls inside the expected Q4 2028 handover quarter, so the two agree and the registered date has not passed. Measured from the 0% reading of 9 February 2026, that date lies about 35 months ahead; actual handover is confirmed by Binghatti as the build advances, and this page's record is updated as each new inspection is recorded.

Binghatti Spectre is planned for 712 residences in studio, 1, 2 and 3 bedroom layouts, with office units in Tower B and ground-floor retail shops alongside. The developer fact sheet gives the land plot as 11,033.25 sq m (118,760.91 sq ft); no built-up area figure is published in the documents behind this record. Layouts and size bands are set out under Binghatti Spectre layouts and prices.

Binghatti Spectre is designed as twin towers of 26 floors above a shared multi-level podium and basement levels, finished with a mechanical level and roof. Tower B holds the office units alongside residences, ground-floor retail shops sit at street level, and the amenity deck carries more than 20 wellness and leisure facilities, according to Binghatti. At the 9 February 2026 inspection none of this structure had been started, with the register at 0%.

The DLD register records a construction start of 1 September 2026 and a project registration of 13 October 2026 for Binghatti Spectre. The first tracked inspection, on 9 February 2026, is dated before both and recorded 0%; this page prints the dates exactly as the register shows them, and the start date is a register entry rather than an inspection finding.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Spectre construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status