Canal Heights 2 Construction Update - April 2026
April 2026 Inspection Records Canal Heights 2 at 28.06% Construction Progress in Business Bay
Structure works advanced while internal, MEP, and finishing packages ran at different stages, with Canal Heights 2 recorded at 28.06 percent in the April 2026 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Canal Heights 2 Construction Snapshot
A 5.50 point gain on the previous recorded reading puts Canal Heights 2 in the superstructure band, the stage where the rate the frame climbs sets the pace for everything scheduled after it. The register carries that earlier 22.56% figure without a date, so the movement is read here as distance covered rather than as a monthly rate.
Canal Heights 2 by DAMAC
2615
Active
28.06%
22 April 2026
10 June 2023
501 residential units
36,848.50 sq m
Q3 2027
Data source: RERA inspection conducted on 22 April 2026, tracked against DLD inspection records for project 2615. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Canal Heights 2 Construction Progress Summary
The 22 April 2026 inspection put Canal Heights 2 at 28.06%, 5.50 points above the 22.56% previous reading held in the register. That earlier figure is undated in the record, so no monthly rate can honestly be drawn from it; what the two numbers do establish is that the concrete frame has moved past its foundation phase and is now the item carrying the schedule.
- Enabling works across the Business Bay plot
- Foundation works beneath the residential tower
- Trust account established with Emirates NBD Bank
- Structure works progressing at advanced stages
- Mobilization works continuing on site
- Internal works and internal finishing at varying stages
- Mechanical, electrical, and plumbing packages underway
- Concrete frame through the upper residential levels
- External finishes across the tower elevations
- Remaining RERA inspection cycles toward 100%
- Completion certification ahead of the Q3 2027 window
Payment Linked Progress
What 28.06% Progress Means for Canal Heights 2 Buyers
Dubai off plan payment plans attach installments to construction milestones or to handover, so a certified reading of 28.06% is a payment signal as much as a status line: it tells you which obligations sit close and which are still years out. At this point in the Canal Heights 2 schedule, four actions carry the weight.
Verify the escrow account
Project 2615 is registered to Resta Real Estate Development L.L.C, with Emirates NBD Bank named as the trust account bank in the April 2026 monitoring report. Every installment belongs in that DLD regulated escrow account and nowhere else. Canal Heights 2 escrow account verification walks it through; the check against the official DLD project record takes roughly two minutes.
Reread your SPA milestone schedule
Find the clause that names the construction percentage or milestone triggering your next payment, then hold it against the 28.06% figure certified on 22 April 2026. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
Interim registration in the Oqood system is what places an off plan purchase on the DLD record before a title deed exists, and it matters most while a project is still years from handover. Check that your registration was filed and that the unit reference on it matches your sale and purchase agreement exactly.
Track the structural climb
A tower at 28.06% has several inspection cycles ahead, and the points recorded per cycle are the clearest early read on whether the Q3 2027 window holds. Canal Heights 2 construction updates hub keeps every reading in one place.
General framework, not legal advice: the milestones that trigger your payments, the notice periods that apply, and the fees you owe are defined by your own sale and purchase agreement and by the DLD record, and both deserve a direct read.
Buying at 28.06%?
Entering while the frame is still rising buys payment plan runway at the cost of time: the foundations are certified, the structure is visibly moving, and the handover window is still more than a year out. Every payment goes to the DLD-registered escrow account for project 2615, released against certified construction progress.
- Enabling and foundation works already certified in the record
- Structure recorded at advanced stages on 22 April 2026
- Inspection history you can read before you commit
- Construction risk carried from excavation onward
- No certified reading exists yet to check the promise against
- Longer installment runway, priced at launch levels
20 or more units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Canal Heights 2 Project Details

The DLD record describes Canal Heights 2 as a concrete framed residential and commercial building of four basements, ground, three podium levels, 43 floors, two mechanical levels, and a roof, holding 501 residences that run from studios to super luxury duplexes, with interiors developed alongside de GRISOGONO.
At 28.06% the trade off for a buyer entering now is a longer wait against a longer payment runway, with 71.94 points of certified progress still to be recorded before the Q3 2027 handover window.
Site Context This Cycle
Explore Canal Heights 2 Location on Dubai Map
Canal Heights 2 occupies plot 290 in Business Bay, a compact waterway facing site where a 43 storey frame has to rise inside tight boundaries rather than spread across them. That constraint is why this cycle reads the way it does: with four basement levels and a three level podium already behind the foundation works, the vertical structure is now the single item that moves the recorded percentage, and mobilization continues alongside it because material and access logistics stay demanding on an urban plot of this shape.
Business Bay itself is finished around the site, with roads, the canal promenade, and utility networks long since in service, so the district will not be under construction when this tower is handed over even though the tower will be for some time yet. For a buyer weighing the Q3 2027 window, that separation matters: the wait here is a building wait, not a neighborhood wait. Plot 290 and its canal frontage are marked on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Canal Heights 2 During Structural Construction Progress
The superstructure band is where payment protection and residency planning are worth settling early, well before a handover notice makes them urgent. Each resource below is matched to where Canal Heights 2 stands right now.

Canal Heights 2 Construction Updates
This page: what the April 2026 RERA inspection recorded on site for Canal Heights 2.

Canal Heights 2 by DAMAC Golden Visa: Four of Five Tiers Qualify
Four of five tiers at Canal Heights 2 by DAMAC qualify alone, from the 1 bedroom; the studio sits below.
Read Canal Heights 2 Golden Visa Guide
Canal Heights 2 by DAMAC: Checking the Canal Tower's Escrow
Canal Heights 2 by DAMAC lists 505 units as DLD project 2615, escrowed at Emirates NBD, 28.06% certified by April 2026.
Verify Canal Heights 2 Escrow AccountUpdate Timeline
Other Canal Heights 2 Construction Updates
This April 2026 reading opens the published record for Canal Heights 2; every cycle from here is added to the hub so the structural climb can be read end to end.
Where This Update Fits
Explore Canal Heights 2 Structure
This monthly report is one node in the wider record: the district around the site, the developer building it, and the stock a buyer would weigh against it.

Business Bay Properties for Sale
Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.
See Business Bay Properties for Sale
Business Bay Community Overview
Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.
Explore the Business Bay Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileFAQs
Canal Heights 2 Construction Progress in April 2026: Frequently Asked Questions
As of the RERA inspection conducted on 22 April 2026, Canal Heights 2 stands at 28.06% construction progress in the DLD project register for project 2615, with the status recorded as Main Contract - Progressing.
The register holds 22.56% at the previous inspection and 28.06% on 22 April 2026, a gain of 5.50 points. That earlier reading carries no date in the record, so the figure describes distance covered between two inspections rather than a monthly rate, and no month should be attached to it.
The 22 April 2026 monitoring report records enabling works and foundation works as completed, structure works progressing at advanced stages, and mobilization, internal works, internal finishing, and MEP packages running at different stages. The building is designed as a concrete structure with block work carrying internal and external finishes.
Q3 2027 is the handover window on record as of this April 2026 update. Completion timing held in the DLD project register is not fixed: it can be revised between cycles, and this page carries whichever version is current at each reading. The way inspections feed that register is set out on the Canal Heights 2 construction updates hub.
The April 2026 Independent Progress Monitoring Report names Emirates NBD Bank (P.J.S.C) as the trust account bank for project 2615, which is registered to Resta Real Estate Development L.L.C as the DLD-listed developer entity. Account references should always be read from the live DLD project record before a transfer rather than from a brochure or an email.
71.94 percentage points separate the 28.06% recorded on 22 April 2026 from full completion certification. The remaining work covers the balance of the concrete frame across 43 floors, two mechanical levels and the roof, the external finishes on the elevations, and the internal and MEP packages already running.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Canal Heights 2 by DAMAC correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.