Canal Heights 2 by DAMAC in Business Bay construction updates cover image featuring a project rendering of twin residential towers beside the canal at night in Dubai - Presented by Tohid Fetrat

DAMAC · Business Bay

Canal Heights 2 by DAMAC Construction Updates

The Certified Build Record of a 43-Storey Canal-Side Tower

Canal Heights 2 reached 28.06% construction progress at its 22 April 2026 RERA inspection, with the tower frame climbing toward a handover window held at Q3 2027.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

28.06%Construction Progress
22 April 2026Latest RERA Inspection
501 residential unitsTotal Units
Project 2615DLD Registration

Construction Snapshot

Canal Heights 2 by DAMAC at a Glance

Canal Heights 2 is DAMAC's 501-residence address on plot 290 in Business Bay, held in the Dubai Land Department register as project 2615. Its shape is vertical rather than broad: 43 floors stacked over three podium levels and four basements, with two mechanical floors and a roof above them. Just under three years separate the 10 June 2023 construction start from the 28.06% certified on 22 April 2026, and because the register currently publishes one dated inspection for this project, every percentage on this page is tied to that single certification date.

DLD Project Number

2615

Project Status

Active

Construction Start

10 June 2023

Total Units

501 residential units

Total Built-Up Area

36,848.50 sq m

Registered Completion Date

Q3 2027

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Canal Heights 2 by DAMAC Construction Update Timeline

Canal Heights 2 currently carries one dated reading in the DLD register: 28.06%, certified on 22 April 2026. An earlier value of 22.56% sits in the register as the previous inspection but carries no date, so it is described here in words and never plotted as a point or converted into a monthly rate. The track below therefore marks a single certified position on the run from the June 2023 start toward handover, and the row beneath it opens the full report for that cycle.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202628.06%22 April 2026View the April 2026 update

Pace Analysis

How Fast Canal Heights 2 by DAMAC Has Been Built

With one dated inspection in the register, this project has no measured velocity between inspections yet. Three arithmetic positions can still be read honestly, each labelled for exactly what it is:

  • 10 June 2023 start to 22 April 2026: 0% to 28.06%About 0.8 points per month, derived
  • Undated previous reading to 22 April 2026: 22.56% to 28.06%5.50 points, interval unknown
  • 22 April 2026 to the Q3 2027 window: 28.06% to 100%About 4.2 to 5.0 points per month, schedule-implied

Reading those three lines together is the whole exercise at this stage. The 0.8 points a month is a lifetime average dragged down by the substructure years, when four basement levels and the foundations consumed calendar time without moving the recorded percentage far. The 5.50 point gain over the undated prior reading confirms distance covered but supports no rate at all, which is precisely why it stays out of the track. The number that matters is the third one: closing 71.94 points before the Q3 2027 window needs roughly five times the pace the project has averaged so far. A concrete frame at advanced structure normally does record several points per cycle, so the requirement is not unusual in itself, but it makes the next certified figure the single most informative data point this project will produce. An investor should watch whether it lands near four points a month; an end user planning around Q3 2027 gets the same early signal from the same number.

Get the Next Inspection Figure First

Tell me you are tracking Canal Heights 2 by DAMAC and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Canal Heights 2 by DAMAC at Business Bay

A percentage only means something beside what it is building. The project guide covers the residences sitting behind the 28.06% on this page:

Canal Heights 2 by DAMAC in Business Bay twin residential towers on the canal waterfront viewed from above at dusk in Dubai - Presented by Tohid Fetrat

Canal Heights 2 by DAMAC: de GRISOGONO Residences on the Canal

Canal Heights 2 by DAMAC holds 501 residences, studios to four bedroom duplexes, on the Dubai Canal in Business Bay.

View the Canal Heights 2 by DAMAC Project Guide

Considering an Entry at 28.06%?

Buying while the frame is still climbing trades a longer wait for a longer installment runway, and what remains unsold shifts between inspection cycles. Ask me what is currently listed before the next reading is published.

Ask About Remaining Availability on WhatsApp

Stage Record

Canal Heights 2 by DAMAC Build Stages, Mapped to the Inspections

Each stage below is pinned to where Canal Heights 2 actually sits in the DLD register rather than to a generic build sequence, so the one certified reading can be placed inside the run from registration to handover.

Mar 2023 to Jun 2023

Registration and Site Activation

Project 2615 was entered in the Dubai Land Department register on 29 March 2023, and construction start was recorded on 10 June 2023, opening work on the Business Bay plot.

Jun 2023 to early 2026

Enabling Works and Substructure

By the April 2026 monitoring report, enabling works and the foundations beneath the tower were certified complete, the phase that fixes four basement levels before any floor plate rises.

Current PhaseCertified at 28.06% on 22 Apr 2026

Superstructure and First-Fix Packages

Structure works were logged at advanced stages with mobilization continuing, while first-fix trades, finishing and mechanical packages ran at their own heights inside the completed levels.

Ahead of the next readings

Topping Out and External Finishes

Carrying the frame up to roof level and then closing the elevations accounts for most of the 71.94 points left to certify after the April 2026 reading.

Toward the Q3 2027 window

Fit-Out, Commissioning and Handover

Apartment finishing, systems commissioning and completion certification close the record, against a handover window currently held at Q3 2027 in the project register.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Canal Heights 2 by DAMAC's own record.

Buyer Position

Tracking Your Position at Canal Heights 2 by DAMAC

This page is one of four project resources that together cover a Canal Heights 2 by DAMAC purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Canal Heights 2 by DAMAC in Business Bay construction updates cover image featuring a project rendering of twin residential towers beside the canal at night in Dubai - Presented by Tohid Fetrat
You Are Here

Canal Heights 2 by DAMAC Construction Updates

This page: every certified RERA reading for Canal Heights 2, from the June 2023 start onward.

Canal Heights 2 by DAMAC in Business Bay Golden Visa card graphic above the twin residential towers framed by palm trees in Dubai - Presented by Tohid Fetrat

Canal Heights 2 by DAMAC Golden Visa: Four of Five Tiers Qualify

Four of five tiers at Canal Heights 2 by DAMAC qualify alone, from the 1 bedroom; the studio sits below.

Read the Canal Heights 2 by DAMAC Golden Visa Guide
Canal Heights 2 by DAMAC in Business Bay escrow account protection concept with shield and padlock icons above the twin residential towers in Dubai - Presented by Tohid Fetrat

Canal Heights 2 by DAMAC: Checking the Canal Tower's Escrow

Canal Heights 2 by DAMAC lists 505 units as DLD project 2615, escrowed at Emirates NBD, 28.06% certified by April 2026.

Verify the Canal Heights 2 by DAMAC Escrow Account

Approaching Handover

Between 28.06% and Handover: What Canal Heights 2 by DAMAC Buyers Should Do Now

At this point in a build the work that protects a buyer is administrative rather than physical. With 71.94 points left to certify and installments falling due against milestones rather than calendar dates, three checks belong in the diary now instead of in 2027.

First, make sure every transfer lands in the escrow account registered against project 2615; the Canal Heights 2 escrow account page covers the trust account named in the monitoring report and how certified milestones release money to the developer.

Second, read your own payment schedule against the certified figure rather than a calendar month, because a construction-linked installment is triggered by a percentage entering the register, and each new percentage for this project is published on this page.

Third, if residency forms part of the plan, settle eligibility early through the Canal Heights 2 Golden Visa page, since the qualifying route differs before and after a title deed exists.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Business Bay Structure

A build record reads better beside the district holding it and the developer delivering it. These three pages put the 28.06% reading in its wider setting:

Business Bay properties for sale featuring modern residential towers and premium Dubai skyline views Captured by Tohid Fetrat.

Business Bay Properties for Sale

Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.

See Business Bay Properties for Sale
Business Bay skyline view featuring Opus Tower Bugatti Residences by Binghatti The Binary by Omniyat and Ahad Tower with modern high rise architecture and urban city streets captured by Tohid Fetrat.

Business Bay Community Overview

Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.

Explore the Business Bay Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Canal Heights 2 by DAMAC Construction Updates Frequently Asked Questions

Project 2615 holds an Active status in the Dubai Land Department register, and Canal Heights 2 was certified at 28.06% construction progress at the RERA inspection of 22 April 2026, logged under a progress status of Main Contract - Progressing. That single certified position is plotted in the inspection record above.

The 22 April 2026 inspection certified 28.06%, which is 5.50 points above the 22.56% figure held as the previous reading in the register. Enabling and foundation works were logged as complete, the concrete frame was recorded at advanced stages, and the internal, finishing and mechanical trades were each running at their own height in the building. The full report for that cycle is published in the April 2026 Canal Heights 2 construction update.

No measured inter-inspection velocity exists yet, because the register holds only one dated reading for this project. Across the 34 months from the 10 June 2023 start to the 28.06% certified on 22 April 2026, the derived average is about 0.8 percentage points per month, a figure weighted down by the long substructure phase. Closing the remaining 71.94 points inside the Q3 2027 window implies roughly 4.2 to 5.0 points per month from April 2026 onward. Both figures are broken down in the pace analysis above.

The Dubai Land Department register holds 22.56% as the previous inspection value for project 2615 without publishing the date it was certified. An undated figure cannot be plotted as a point in time or divided into a monthly rate, so it appears on this page only in words, while the progress track and the timeline table carry the 22 April 2026 reading of 28.06% alone.

The handover window on record for Canal Heights 2 is Q3 2027, more than a year beyond the 22 April 2026 inspection date, and 71.94 percentage points of certified progress separate that reading from completion. A completion window logged against a project is never permanent: it can shift as further inspection cycles are added, and the version standing at the next certified reading is what will show here.

Registration records for project 2615 show 501 residential units and a total built-up area of 36,848.50 sq m. The mix opens at studios, runs through one and two bedroom apartments, and closes with super luxury duplexes of three and four bedrooms, with de GRISOGONO shaping the interiors. Layouts are set out in the Canal Heights 2 project guide.

Project 2615 was entered in the Dubai Land Department register on 29 March 2023, and construction start is recorded as 10 June 2023. The first dated inspection published for the project is the 22 April 2026 reading of 28.06%, so the tracked record on this page opens at that point rather than at the start date.

As of 22 April 2026, enabling works and the foundations were certified complete and the concrete frame was progressing at advanced stages, with mobilization continuing on site and the first-fix trades started inside the completed levels. The register sets it down as a residential and commercial tower built in concrete: 43 floors, three podium levels, four basements, two mechanical floors and a roof.

Yes. The tower sits on plot 290, a tight parcel facing the water in Business Bay, which is why the design climbs 43 floors instead of spreading out. Roads, promenade and utilities around the site are long since in service, so the only countdown this page measures is the building itself.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Canal Heights 2 by DAMAC construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.