Canal Heights 2 by DAMAC Construction Updates
The Certified Build Record of a 43-Storey Canal-Side Tower
Canal Heights 2 reached 28.06% construction progress at its 22 April 2026 RERA inspection, with the tower frame climbing toward a handover window held at Q3 2027.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Canal Heights 2 by DAMAC at a Glance
Canal Heights 2 is DAMAC's 501-residence address on plot 290 in Business Bay, held in the Dubai Land Department register as project 2615. Its shape is vertical rather than broad: 43 floors stacked over three podium levels and four basements, with two mechanical floors and a roof above them. Just under three years separate the 10 June 2023 construction start from the 28.06% certified on 22 April 2026, and because the register currently publishes one dated inspection for this project, every percentage on this page is tied to that single certification date.
2615
Active
10 June 2023
501 residential units
36,848.50 sq m
Q3 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Canal Heights 2 by DAMAC Construction Update Timeline
Canal Heights 2 currently carries one dated reading in the DLD register: 28.06%, certified on 22 April 2026. An earlier value of 22.56% sits in the register as the previous inspection but carries no date, so it is described here in words and never plotted as a point or converted into a monthly rate. The track below therefore marks a single certified position on the run from the June 2023 start toward handover, and the row beneath it opens the full report for that cycle.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 28.06% | 22 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Canal Heights 2 by DAMAC Has Been Built
With one dated inspection in the register, this project has no measured velocity between inspections yet. Three arithmetic positions can still be read honestly, each labelled for exactly what it is:
- 10 June 2023 start to 22 April 2026: 0% to 28.06%About 0.8 points per month, derived
- Undated previous reading to 22 April 2026: 22.56% to 28.06%5.50 points, interval unknown
- 22 April 2026 to the Q3 2027 window: 28.06% to 100%About 4.2 to 5.0 points per month, schedule-implied
Reading those three lines together is the whole exercise at this stage. The 0.8 points a month is a lifetime average dragged down by the substructure years, when four basement levels and the foundations consumed calendar time without moving the recorded percentage far. The 5.50 point gain over the undated prior reading confirms distance covered but supports no rate at all, which is precisely why it stays out of the track. The number that matters is the third one: closing 71.94 points before the Q3 2027 window needs roughly five times the pace the project has averaged so far. A concrete frame at advanced structure normally does record several points per cycle, so the requirement is not unusual in itself, but it makes the next certified figure the single most informative data point this project will produce. An investor should watch whether it lands near four points a month; an end user planning around Q3 2027 gets the same early signal from the same number.
Get the Next Inspection Figure First
Tell me you are tracking Canal Heights 2 by DAMAC and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Canal Heights 2 by DAMAC at Business Bay
A percentage only means something beside what it is building. The project guide covers the residences sitting behind the 28.06% on this page:

Canal Heights 2 by DAMAC: de GRISOGONO Residences on the Canal
Canal Heights 2 by DAMAC holds 501 residences, studios to four bedroom duplexes, on the Dubai Canal in Business Bay.
View the Canal Heights 2 by DAMAC Project GuideConsidering an Entry at 28.06%?
Buying while the frame is still climbing trades a longer wait for a longer installment runway, and what remains unsold shifts between inspection cycles. Ask me what is currently listed before the next reading is published.
Ask About Remaining Availability on WhatsAppStage Record
Canal Heights 2 by DAMAC Build Stages, Mapped to the Inspections
Each stage below is pinned to where Canal Heights 2 actually sits in the DLD register rather than to a generic build sequence, so the one certified reading can be placed inside the run from registration to handover.
Registration and Site Activation
Project 2615 was entered in the Dubai Land Department register on 29 March 2023, and construction start was recorded on 10 June 2023, opening work on the Business Bay plot.
Enabling Works and Substructure
By the April 2026 monitoring report, enabling works and the foundations beneath the tower were certified complete, the phase that fixes four basement levels before any floor plate rises.
Superstructure and First-Fix Packages
Structure works were logged at advanced stages with mobilization continuing, while first-fix trades, finishing and mechanical packages ran at their own heights inside the completed levels.
Topping Out and External Finishes
Carrying the frame up to roof level and then closing the elevations accounts for most of the 71.94 points left to certify after the April 2026 reading.
Fit-Out, Commissioning and Handover
Apartment finishing, systems commissioning and completion certification close the record, against a handover window currently held at Q3 2027 in the project register.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Canal Heights 2 by DAMAC's own record.
Buyer Position
Tracking Your Position at Canal Heights 2 by DAMAC
This page is one of four project resources that together cover a Canal Heights 2 by DAMAC purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Canal Heights 2 by DAMAC Construction Updates
This page: every certified RERA reading for Canal Heights 2, from the June 2023 start onward.

Canal Heights 2 by DAMAC Golden Visa: Four of Five Tiers Qualify
Four of five tiers at Canal Heights 2 by DAMAC qualify alone, from the 1 bedroom; the studio sits below.
Read the Canal Heights 2 by DAMAC Golden Visa Guide
Canal Heights 2 by DAMAC: Checking the Canal Tower's Escrow
Canal Heights 2 by DAMAC lists 505 units as DLD project 2615, escrowed at Emirates NBD, 28.06% certified by April 2026.
Verify the Canal Heights 2 by DAMAC Escrow AccountApproaching Handover
Between 28.06% and Handover: What Canal Heights 2 by DAMAC Buyers Should Do Now
At this point in a build the work that protects a buyer is administrative rather than physical. With 71.94 points left to certify and installments falling due against milestones rather than calendar dates, three checks belong in the diary now instead of in 2027.
First, make sure every transfer lands in the escrow account registered against project 2615; the Canal Heights 2 escrow account page covers the trust account named in the monitoring report and how certified milestones release money to the developer.
Second, read your own payment schedule against the certified figure rather than a calendar month, because a construction-linked installment is triggered by a percentage entering the register, and each new percentage for this project is published on this page.
Third, if residency forms part of the plan, settle eligibility early through the Canal Heights 2 Golden Visa page, since the qualifying route differs before and after a title deed exists.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Business Bay Structure
A build record reads better beside the district holding it and the developer delivering it. These three pages put the 28.06% reading in its wider setting:

Business Bay Properties for Sale
Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.
See Business Bay Properties for Sale
Business Bay Community Overview
Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.
Explore the Business Bay Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Canal Heights 2 by DAMAC Construction Updates Frequently Asked Questions
Project 2615 holds an Active status in the Dubai Land Department register, and Canal Heights 2 was certified at 28.06% construction progress at the RERA inspection of 22 April 2026, logged under a progress status of Main Contract - Progressing. That single certified position is plotted in the inspection record above.
The 22 April 2026 inspection certified 28.06%, which is 5.50 points above the 22.56% figure held as the previous reading in the register. Enabling and foundation works were logged as complete, the concrete frame was recorded at advanced stages, and the internal, finishing and mechanical trades were each running at their own height in the building. The full report for that cycle is published in the April 2026 Canal Heights 2 construction update.
No measured inter-inspection velocity exists yet, because the register holds only one dated reading for this project. Across the 34 months from the 10 June 2023 start to the 28.06% certified on 22 April 2026, the derived average is about 0.8 percentage points per month, a figure weighted down by the long substructure phase. Closing the remaining 71.94 points inside the Q3 2027 window implies roughly 4.2 to 5.0 points per month from April 2026 onward. Both figures are broken down in the pace analysis above.
The Dubai Land Department register holds 22.56% as the previous inspection value for project 2615 without publishing the date it was certified. An undated figure cannot be plotted as a point in time or divided into a monthly rate, so it appears on this page only in words, while the progress track and the timeline table carry the 22 April 2026 reading of 28.06% alone.
The handover window on record for Canal Heights 2 is Q3 2027, more than a year beyond the 22 April 2026 inspection date, and 71.94 percentage points of certified progress separate that reading from completion. A completion window logged against a project is never permanent: it can shift as further inspection cycles are added, and the version standing at the next certified reading is what will show here.
Registration records for project 2615 show 501 residential units and a total built-up area of 36,848.50 sq m. The mix opens at studios, runs through one and two bedroom apartments, and closes with super luxury duplexes of three and four bedrooms, with de GRISOGONO shaping the interiors. Layouts are set out in the Canal Heights 2 project guide.
Project 2615 was entered in the Dubai Land Department register on 29 March 2023, and construction start is recorded as 10 June 2023. The first dated inspection published for the project is the 22 April 2026 reading of 28.06%, so the tracked record on this page opens at that point rather than at the start date.
As of 22 April 2026, enabling works and the foundations were certified complete and the concrete frame was progressing at advanced stages, with mobilization continuing on site and the first-fix trades started inside the completed levels. The register sets it down as a residential and commercial tower built in concrete: 43 floors, three podium levels, four basements, two mechanical floors and a roof.
Yes. The tower sits on plot 290, a tight parcel facing the water in Business Bay, which is why the design climbs 43 floors instead of spreading out. Roads, promenade and utilities around the site are long since in service, so the only countdown this page measures is the building itself.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Canal Heights 2 by DAMAC construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.