Como Residences Construction Update - August 2024
August 2024 Inspection Records Como Residences at 2.72% With Pre-Construction Still Progressing on Palm Jumeirah
The DLD register moved Como Residences to 2.72% at the 29-08-2024 RERA inspection, while the report itself listed no inspection notes and kept its Pre-Construction status.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Como Residences Construction Snapshot
A rise of 2.71 points over 296 days, from 0.01% on 07-11-2023 to 2.72% on 29-08-2024, is the first interval in the Como Residences record to show a measurable pace, 0.27 points per 30-day month, with the project still inside the pre-construction band.
Como Residences by Nakheel
2565
Active
2.72%
29-08-2024
27-09-2023
81 residences
68,563.62 sq m
Q3 2027
Data source: DLD project register, 2.72% for the inspection conducted on 29-08-2024 and 0.01% for the previous inspection on 07-11-2023. The Independent Progress Monitoring Report for 29-08-2024 prints no percentage, gives its Progress Status as Pre-Construction - Progressing and records no inspection notes; register fields are shown as recorded. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This page reads the record as it stood on 29-08-2024; on 25-09-2026, when it was prepared, that reading was 757 days old: re-verify on Dubai REST before publishing. The hero image is a project rendering of planned interiors and sea views, not a photograph of the site. Last updated: August 2024.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Como Residences Construction Progress Summary
Across the 296 days between the 07-11-2023 and 29-08-2024 inspections, the register reading for Como Residences rose from 0.01% to 2.72%. Measured instead from the registered construction start of 27-09-2023, the same 2.72% spread over 337 days gives 0.24 points per 30-day month, an arithmetic average and not a forecast. Where the November report listed fencing and underground services works, the notes field of the August report reads NA, so no site works are named for this cycle.
- Baseline of 0% on 22-02-2023, then 0.01% on 07-11-2023
- Registration on 12-04-2023 and construction start on 27-09-2023
- Fencing and services rerouting noted on the 07-11-2023 report
- DLD register reading of 2.72%, 2.71 points above November 2023
- Progress Status on the 29-08-2024 report: Pre-Construction - Progressing
- Inspection notes field on the same report: NA
- Any Progress Status beyond Pre-Construction on a later report
- The Ground + 3 podiums + 72 floors Residential building set out in the report
- Q3 2027 handover from Nakheel, beside the registered completion date 27-03-2027
Payment Linked Progress
What 2.72% Progress Means for Como Residences Buyers
Ten months after the first dated instalment, the payment schedule and the register can be set side by side again. Nakheel's launch schedule of record dated 40% of the price by 30-04-2024 (20% upon booking, 10% on 30-10-2023 and 10% on 30-04-2024), 121 days before a 29-08-2024 register reading of 2.72%. With the report still at Pre-Construction, four actions matter most.
Verify the escrow account
The launch schedule of record dated its next 10% for 30-10-2024, 62 days after this reading, and any Como Residences transfer belongs only in the DLD regulated escrow account held for project 2565. Como Residences escrow account verification is the step before the money moves; the lookup takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
Your sale and purchase agreement, not the launch schedule, fixes what you owe and when: lay its dates beside the 2.72% reading of 29-08-2024 and the 0.01% reading before it. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.
Check your Oqood entry
By 29-08-2024 project 2565 had been in the DLD register for 505 days. Oqood is the DLD record of off plan contracts: confirm that yours appears there under that project number, with the correct unit and buyer names, before a further instalment is paid.
Read each interval, not just the figure
At 2.72% a single reading says little on its own; what it adds lies in the dates either side, 296 days back to 07-11-2023 and forward to the next report. The Como Residences construction update timeline lists each dated register reading in order.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 2.72%?
Seen from this reading, a pre-construction entry meant paying to a dated schedule while the register moved at its own pace: 40% of the launch schedule was dated by 30-04-2024, the register read 2.72% on 29-08-2024, and handover was expected in Q3 2027. Every payment goes to the DLD-registered escrow account for project 2565, released against construction progress recorded in the DLD project register.
- Pre-Construction - Progressing on the 29-08-2024 report
- 97.28 points between this reading and 100%
- 40% of the launch schedule of record dated by 30-04-2024
- A standing structure to inspect before signing
- A handover date close enough to plan around
- Most instalments already behind, at a later stage price
Unit availability is confirmed at the time of each enquiry; availability shifts between cycles.
About the Development
Como Residences Project Details

At 2.72% on 29-08-2024 Como Residences existed as a register entry and a plan: 81 residences across the 71 floors Nakheel describes, from 2 bedroom apartments up to a 7 bedroom duplex, with no stage beyond Pre-Construction recorded. Starting prices today: AED 27.00M ≈ USD 7.35M.
Entering at this point meant carrying nearly the whole build ahead, roughly three years to a Q3 2027 handover, while 40% of the launch schedule of record had already been dated.
Como Residences by Nakheel Project GuideSite Context This Cycle
Explore Como Residences Location on Dubai Map
Plot 2692 lies in the heart of Palm Jumeirah, where Nakheel sets the tower to look toward Burj Al Arab, Burj Khalifa and Ain Dubai, and describes every residence as having 180- or 360-degree views. For this cycle the report adds nothing about the plot itself: its inspection notes field reads NA, so the site is recorded here through the register alone, at 2.72% on 29-08-2024.
By August 2024 Palm Jumeirah was a settled island whose roads, beaches and utilities had long been in service, so Como Residences was being prepared inside a finished community rather than beside new infrastructure. For a buyer, the setting was already there to inspect, and the open question at 2.72% was the building itself. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Como Residences as Pre-Construction Readings Rise
With 40% of the launch schedule dated and the register at 2.72% on 29-08-2024, the decisions open to a buyer concerned protecting payments and planning residency. Each resource below is matched to that point in the Como Residences record.

Como Residences Construction Updates
This page: the August 2024 register reading of 2.72% for Como Residences, 2.71 points above November.

Como Residences Golden Visa: 81 Residences on Palm Jumeirah
Como Residences, Nakheel's 81-residence tower on Palm Jumeirah, has each listed unit type clear the threshold individually, under Oqood during construction.
Read Como Residences Golden Visa Guide
Como Residences Escrow: Nakheel's Palm Jumeirah Account at Commercial Bank of Dubai
Nakheel's Como Residences on Palm Jumeirah is DLD project 2565, with 81 units and its escrow at Commercial Bank of Dubai.
Verify Como Residences Escrow AccountUpdate Timeline
Other Como Residences Construction Updates
This August 2024 page sits between the November 2023 reading before it and the January 2025 reading after it; follow the links in date order to see how each interval compares.
Where This Update Fits
Explore Como Residences Structure
The August 2024 reading is one line in a longer record that also runs through the Palm Jumeirah community around plot 2692, Nakheel as the developer of both the island and the tower, and the listings a buyer would compare against it.

Palm Jumeirah Dubai Properties for Sale
Browse beachfront apartments, penthouses, sky mansions and signature villas for sale across Palm Jumeirah.
See Palm Jumeirah Dubai Properties for Sale
Palm Jumeirah Dubai Community Overview
Read the Palm Jumeirah guide: Nakheel's island of signature villas, branded residences, private beaches and five-star resorts.
Explore the Palm Jumeirah Dubai Community
Nakheel: The Master Developer of Dubai's Island Living and Reclaimed Coastline
Founded in 2003, Nakheel created Palm Jumeirah and Dubai Islands, adding over 300 kilometers of coastline and building complete waterfront communities.
View the Nakheel Developer ProfileFAQs
Como Residences Construction Progress in August 2024: Frequently Asked Questions
The DLD project register records 2.72% for Como Residences at the inspection conducted on 29-08-2024, the third dated reading for project 2565 after 0% on 22-02-2023 and 0.01% on 07-11-2023. The inspection report of that date prints no percentage of its own, and the reading was 757 days old on 25-09-2026, so the current figure should be read on Dubai REST.
It rose 2.71 points in 296 days, from 0.01% on 07-11-2023 to 2.72% on 29-08-2024, which works out at 0.27 points per 30-day month over that interval. The figure is arithmetic on two dated readings, not a forecast; the full sequence of dated readings is on the Como Residences construction updates guide.
NA. The 29-08-2024 report for project 2565 recorded no inspection notes, so it names no fencing, services, enabling or foundation works for that date, and this page does not supply any. The only stage information on the report is its Progress Status, Pre-Construction - Progressing.
No. The reports of 07-11-2023 and 29-08-2024 both give the Progress Status as Pre-Construction - Progressing, while the DLD register reading moved from 0.01% to 2.72% between them. The stage label and the register figure are separate fields, and each is reported here as printed.
0.24 points per 30-day month: 2.72 points over the 337 days from the registered construction start of 27-09-2023 to the 29-08-2024 inspection. It is an arithmetic average and not a forecast, stated beside the 0.27 points per 30-day month measured between the November 2023 and August 2024 readings.
One: 10% on 30-04-2024, 121 days before the 29-08-2024 inspection, which took the dated total in Nakheel's launch schedule of record to 40% (20% upon booking, 10% on 30-10-2023 and 10% on 30-04-2024) against a register reading of 2.72%. The next dated instalment was 10% on 30-10-2024; a unit bought today follows the terms of its own sale and purchase agreement.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2024 inspection record for Como Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.