Nakheel · Palm Jumeirah · Construction Update

Como Residences Construction Update - May 2025

May 2025 Inspection Recorded Como Residences at 6.07% During Mobilization Works on Palm Jumeirah

Mobilization was ongoing and enabling and foundation works were progressing at site as the DLD register logged Como Residences at 6.07% for the 01-05-2025 inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.07%DLD Register Reading
01-05-2025Inspection Date
Q3 2027Expected Handover
2565DLD Project Number

Verified DLD Inspection Data

Como Residences Construction Snapshot

A rise of 1.77 points in 93 days, from 4.30% on 28-01-2025 to 6.07% on 01-05-2025, works out at 0.57 points per 30-day month, the fastest measured interval in the Como Residences record up to that date, while the reading remained in the enabling and foundation stage band.

Project Name

Como Residences by Nakheel

Project Number

2565

Project Status

Active

Construction Progress

6.07%

Inspection Date

01-05-2025

Construction Start

27-09-2023

Total Units

81 residences

Total Built Area

68,563.62 sq m

Expected Completion

Q3 2027

Data source: DLD project register, 6.07% for the inspection conducted on 01-05-2025 against 4.30% for the previous inspection on 28-01-2025 (the app displays the earlier figure as 4.3%). The Independent Progress Monitoring Report dated 01-05-2025 carries no percentage; it gives the Progress Status as Main Contract - Progressing, and its notes and the register fields appear here as recorded. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Prepared on 25-09-2026, this page describes the record as of 01-05-2025, a reading then 512 days old: re-verify on Dubai REST before publishing. The hero image is an annotated masterplan marking the project's position on Palm Jumeirah, not a photograph of the site and not a record of progress. Last updated: May 2025.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Como Residences Construction Progress Summary

The May 2025 report held the Main Contract - Progressing status that January introduced and added a line no earlier notes had carried: mobilization works ongoing, beside enabling and foundation works progressing at site. Spread across the 582 days since construction started on 27-09-2023, the 6.07% reading averages 0.31 points per 30-day month, a calculation and not a forecast.

On Record by 01-05-2025
  • Main contractor assignment and building permit, both noted on the 28-01-2025 report
  • Main Contract - Progressing status, now shown on two consecutive reports
  • Dated readings of 0%, 0.01%, 2.72% and 4.30% from February 2023 to January 2025
In Progress at 6.07%
  • Mobilization works, recorded as ongoing on 01-05-2025
  • Enabling and foundation works, noted as progressing at site
  • DLD register reading of 6.07%, 1.77 points above January 2025
Ahead of Handover
  • Close-out of the enabling and foundation works still listed as progressing
  • The structural frame of the Ground + 3 podiums + 72 floors Residential building the report describes
  • Handover in Q3 2027 per Nakheel, beside the registered completion date of 27-03-2027
Next inspectionThe July 2025 update page carries the register reading that followed this one; it is linked from the Updates section of this page.
Completion targetHandover is expected by Nakheel in Q3 2027, while the DLD register lists 27-03-2027 as the registered completion date, 695 days after this inspection. The two are recorded facts, placed side by side with no forecast drawn.
Remaining distance93.93 percentage points separated the 01-05-2025 reading from 100%.

Payment Linked Progress

What 6.07% Progress Means for Como Residences Buyers

The day before the 01-05-2025 inspection, Nakheel's launch schedule of record dated another 10% on 30-04-2025, taking the scheduled total to 60%: 20% upon booking plus 10% on each of 30-10-2023, 30-04-2024, 30-10-2024 and 30-04-2025, set against a register reading of 6.07%. The pairing is a sum taken from the schedule, not a verdict on it. With mobilization noted as ongoing and foundations under way, four actions matter most.

Before the 30-10-2025 Instalment

Verify the escrow account

The next dated 10% in the launch schedule of record fell on 30-10-2025, 182 days after this reading, and every Como Residences transfer belongs in the DLD regulated escrow account registered to project 2565 and nowhere else. Start with Como Residences escrow account verification; the lookup takes about two minutes against the official DLD project record.

Beside the 30-04-2025 Payment

Reread your SPA milestone schedule

Your sale and purchase agreement, not the launch schedule, decides what fell due around 30-04-2025 and what comes next: see whether your instalments are tied to calendar dates or to construction stages, and read them against the 6.07% reading of 01-05-2025. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.

750 Days on the Register

Check your Oqood entry

By 01-05-2025 project 2565 had been on the DLD register for 750 days. Oqood is the DLD record of each off plan sale, so with 60% of the launch schedule already dated, confirm that your contract appears under that project number with the correct unit and buyer names.

Every Cycle

Read each report's notes as written

The 01-05-2025 notes added mobilization to the site record while the stage label held at Main Contract - Progressing, so the wording of each report deserves the same attention as its number. The Como Residences inspection timeline sets every dated reading and note out in order.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 6.07%?

At this reading an entry meant committing while the tower was still at foundation stage, with 60% of the launch schedule of record already dated and handover expected in Q3 2027. Every payment goes to the DLD-registered escrow account for project 2565, released against construction progress recorded in the DLD project register.

Entering at 6.07%
  • Main Contract - Progressing on two consecutive reports
  • 93.93 points between this reading and 100%
  • 60% of the launch schedule of record dated by 30-04-2025
Typical Late Stage Entry
  • A standing frame to inspect before signing
  • Less waiting between contract and handover
  • A shorter instalment runway, usually at later pricing
AED 27.00M ≈ USD 7.35MStarting Price
81 ResidencesTotal in the Tower
Q3 2027Expected Handover
Ask What Is Available at Como Residences

Unit availability is confirmed at the time of each enquiry; availability shifts between cycles.

About the Development

Como Residences Project Details

Como Residences by Nakheel ultra luxury tower rising above Palm Jumeirah with panoramic Gulf views in Dubai Presented by Tohid Fetrat
Palm Jumeirah · Nakheel

At the 01-05-2025 inspection Como Residences was a foundation-stage site with mobilization still ongoing, the base of a 71-floor seashell-shaped tower, by Nakheel's description, planned for 81 residences ranging from 2 bedroom apartments up to a 7 bedroom duplex. Starting prices today: AED 27.00M ≈ USD 7.35M.

Entering at 6.07% meant the entire superstructure still lay ahead, with a Q3 2027 handover a little over two years away and 60% of the launch schedule of record already dated.

Como Residences by Nakheel Project Guide

Site Context This Cycle

Explore Como Residences Location on Dubai Map

Plot 2692 lies in the heart of Palm Jumeirah among established waterfront villas, the position the annotated masterplan at the top of this page marks. On 01-05-2025 the report recorded mobilization works ongoing with enabling and foundation works progressing at site, so the cycle's work went on inside a plot with existing villas just beyond its boundary.

By May 2025 Palm Jumeirah was a mature island, its roads, beaches and utility connections long complete, so the site worked beside neighbors rather than open land, and a buyer could treat the finished surroundings as a known quantity while the tower Nakheel plans with views toward Burj Al Arab, Burj Khalifa and Ain Dubai stood at 6.07%. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Como Residences by Nakheel on Dubai Map

Buyer Resources for This Project

Investing in Como Residences at the Mobilization Stage

At 6.07%, with 60% of the launch schedule of record dated and mobilization noted on site, the questions that mattered were payment protection and residency. The resources below match those questions to this stage of Como Residences.

Como Residences by Nakheel in Palm Jumeirah construction updates cover image featuring a project rendering of the waterfront tower and surrounding skyline in Dubai - Presented by Tohid Fetrat
You Are Here

Como Residences Construction Updates

This page: the May 2025 Como Residences register reading of 6.07%, with mobilization noted on site.

Como Residences by Nakheel in Palm Jumeirah Golden Visa concept graphic featuring the waterfront tower and residency investment theme in Dubai - Presented by Tohid Fetrat

Como Residences Golden Visa: 81 Residences on Palm Jumeirah

Como Residences, Nakheel's 81-residence tower on Palm Jumeirah, has each listed unit type clear the threshold individually, under Oqood during construction.

Read Como Residences Golden Visa Guide
Como Residences by Nakheel in Palm Jumeirah escrow account protection concept featuring the waterfront tower with shield and padlock icons in Dubai - Presented by Tohid Fetrat

Como Residences Escrow: Nakheel's Palm Jumeirah Account at Commercial Bank of Dubai

Nakheel's Como Residences on Palm Jumeirah is DLD project 2565, with 81 units and its escrow at Commercial Bank of Dubai.

Verify Como Residences Escrow Account

Update Timeline

Other Como Residences Construction Updates

May 2025 sits between the January 2025 and July 2025 readings; opening the pages in date order shows how the record developed on either side of this mobilization report.

All Como Residences Construction Updates

FAQs

Como Residences Construction Progress in May 2025: Frequently Asked Questions

Como Residences read 6.07% in the DLD project register for the 01-05-2025 inspection, 1.77 points above the 4.30% of 28-01-2025 (displayed in the app as 4.3%). The inspection report issued for that visit prints no percentage, so the figure is the register's; it was 512 days old on 25-09-2026, which is why the live entry on Dubai REST should be checked before relying on it.

At 0.57 points per 30-day month: 1.77 points over the 93 days from 28-01-2025 to 01-05-2025. That was the fastest measured interval on the record up to that date, against 0.31 in the interval to January 2025 and 0.27 in the one to August 2024, and it lifted the whole-build average since 27-09-2023 to 0.31 over 582 days. These are calculations on dated register entries and predict nothing; every dated entry in sequence sits on the Como Residences construction progress hub.

The inspection notes of 01-05-2025 state that mobilization works were ongoing and that enabling and foundation works were progressing at site. It is the first time mobilization appears in the notes of the five Como Residences reports issued up to that date; the report gives no breakdown of what the mobilization covered, and this page adds none.

The report's images show reinforcement cages and cylindrical forms in the excavated plot, concrete pump booms and a tower crane at work, and low-rise villas beyond the site boundary; one of the photo slots displays no preview. The photographs belong to the inspection record: they are described here as examined and are not reproduced on this page.

The 10% dated 30-04-2025 in Nakheel's launch schedule of record, one day before the 01-05-2025 inspection. Added to the 20% due at booking and the three earlier 10% instalments of October 2023, April 2024 and October 2024, it brought the scheduled share of the price to 60% while the register stood at 6.07%. The comparison is a plain sum from the schedule, not an assessment; the following dated 10% was set for 30-10-2025, and any unit sold now is governed by its own sale and purchase agreement.

The DLD register listed project 2565 as registered on 12-04-2023, with construction started on 27-09-2023 and a registered completion date of 27-03-2027, 695 days after the 01-05-2025 inspection; Nakheel's expected handover is Q3 2027. A registered completion date is an entry that can be amended in later cycles; the version shown on Dubai REST when you check is the one that counts, and neither date is used here to predict delivery.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2025 inspection record for Como Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts