Como Residences by Nakheel in Palm Jumeirah project rendering used for the July 2025 construction update showing the planned luxury pool deck landscaped terraces and waterfront views in Dubai - Presented by Tohid Fetrat

Nakheel · Palm Jumeirah · Construction Update

Como Residences Construction Update - July 2025

July 2025 Inspection Recorded Como Residences at 10.85% With Structural Works Noted at Site on Palm Jumeirah

For the 30-07-2025 inspection, the report listed enabling and foundation works completed and structural works progressing at Como Residences, with the DLD register at 10.85%.

Direct advisor access. Every message answered personally, never by a call center.

10.85%DLD Register Reading
30-07-2025Inspection Date
Q3 2027Expected Handover
2565DLD Project Number

Verified DLD Inspection Data

Como Residences Construction Snapshot

Up 4.78 points in the 90 days after 01-05-2025, the 10.85% reading of 30-07-2025 moved at 1.59 points per 30-day month, the fastest interval on the Como Residences record so far, while the project stayed in the early stage band below 20%, the band where escrow and Oqood checks come first.

Project Name

Como Residences by Nakheel

Project Number

2565

Project Status

Active

Construction Progress

10.85%

Inspection Date

30-07-2025

Construction Start

27-09-2023

Total Units

81 residences

Total Built Area

68,563.62 sq m

Expected Completion

Q3 2027

Data source: DLD project register, 10.85% for the inspection conducted on 30-07-2025 and 6.07% for the previous inspection on 01-05-2025. The Independent Progress Monitoring Report dated 30-07-2025 prints no percentage; its Progress Status reads Main Contract - Progressing, and both its notes and the register fields are quoted on this page as they stand. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Written on 25-09-2026 about the record as of 30-07-2025, a reading 422 days old at that date: re-verify on Dubai REST before publishing. The hero image is a project rendering of the planned pool deck and terraces: it shows design intent, not the site and not progress. Last updated: July 2025.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Como Residences Construction Progress Summary

The 30-07-2025 report was the first in the Como Residences record to note structural works progressing at site, and it listed enabling and foundation works as completed while mobilization stayed ongoing. The 4.78 points added in this one interval make up about 44% of the 10.85% reading; spread over the 672 days since construction started on 27-09-2023, that reading averages 0.48 points per 30-day month, which is arithmetic, not a forecast.

On Record by 30-07-2025
  • Enabling and foundation works, listed as completed in the 30-07-2025 notes
  • Main Contract - Progressing status on three consecutive reports since January 2025
  • Five earlier dated readings, from 0% on 22-02-2023 to 6.07% on 01-05-2025
In Progress at 10.85%
  • Structural works, noted as progressing at site for the first time
  • Mobilization works, still recorded as ongoing
  • DLD register reading of 10.85%, 4.78 points above May 2025
Ahead of Handover
  • Structural works still to run across the Ground + 3 podiums + 72 floors Residential structure named in the report
  • The internal and external finishes named in the report's project description
  • Nakheel's Q3 2027 handover, set against a registered completion date of 27-03-2027
Next inspectionThe reading that followed this one is on the November 2025 update page, linked from the Updates section below.
Completion targetNakheel expects handover in Q3 2027; the registered completion date held on the DLD record was 27-03-2027, 605 days after the 30-07-2025 inspection. Both are recorded entries, set side by side, with no required pace or forecast drawn from them.
Remaining distance89.15 percentage points lay between the 30-07-2025 reading and 100%.

Payment Linked Progress

What 10.85% Progress Means for Como Residences Buyers

No instalment in Nakheel's launch schedule of record fell between the May and July 2025 inspections, so the scheduled total still stood at 60%: 20% upon booking plus four 10% instalments, the last dated 30-04-2025, set against a register reading of 10.85% on 30-07-2025. The next 10% was dated 30-10-2025. That pairing is arithmetic taken from the schedule, not a judgment on it. With structural works noted at site for the first time, four actions matter most.

92 Days Before the Next Due Date

Verify the escrow account

The launch schedule's next 10% was dated 30-10-2025, 92 days after this reading. Before any transfer toward it, confirm that the receiving account is the DLD regulated escrow account registered to project 2565: Como Residences escrow account verification sets out the check, and the lookup takes about two minutes against the official DLD project record.

Against the 60% Scheduled

Reread your SPA milestone schedule

The dates and triggers in your own contract may differ from the launch schedule of record. Look for any clause tied to a construction stage, such as the structural works first noted in July, and read it against the 10.85% reading of 30-07-2025. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.

840 Days on the Register

Check your Oqood entry

By 30-07-2025 the DLD register had carried project 2565 for 840 days. Oqood is the DLD's record of each off plan sale, so before the October 2025 instalment confirm that your contract sits under that project number with the right unit and buyer names.

Every Cycle

Compare the pace across intervals

The 1.59 points per 30-day month measured to 30-07-2025 stands against 0.57, 0.31 and 0.27 in the three intervals before it, and one fast interval says nothing certain about the next. The Como Residences construction timeline lists every dated reading, so each new one can be read in context.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 10.85%?

An entry at this reading came just as structural works were first noted and foundations were recorded as completed; 60% of the launch schedule of record had fallen due, and Nakheel expected handover in Q3 2027. Every payment goes to the DLD-registered escrow account for project 2565, released against construction progress recorded in the DLD project register.

Entering at 10.85%
  • Foundations recorded as completed on 30-07-2025
  • 89.15 points between this reading and 100%
  • Next dated instalment in the launch schedule: 30-10-2025
Typical Late Stage Entry
  • Most of the structure already standing at signing
  • A shorter wait from contract to keys
  • Fewer instalments left to spread, often at later prices
AED 27.00M ≈ USD 7.35MStarting Price
81 ResidencesTotal in the Tower
Q3 2027Expected Handover
Ask What Is Available at Como Residences

Unit availability is confirmed at the time of each enquiry; availability shifts between cycles.

About the Development

Como Residences Project Details

Como Residences by Nakheel ultra luxury tower rising above Palm Jumeirah with panoramic Gulf views in Dubai Presented by Tohid Fetrat
Palm Jumeirah · Nakheel

When inspected on 30-07-2025, Como Residences had its foundations recorded as completed and structural works progressing for what Nakheel describes as a 71-floor, seashell-shaped tower of 81 residences, from 2 bedroom apartments to a 7 bedroom duplex. Starting prices today: AED 27.00M ≈ USD 7.35M.

An entry at 10.85% left 89.15 points of recorded progress still ahead, about two years before the Q3 2027 handover, when 60% of the launch schedule of record had fallen due and the next 10% was set for 30-10-2025.

Como Residences by Nakheel Project Guide

Site Context This Cycle

Explore Como Residences Location on Dubai Map

Plot 2692 sits in the heart of Palm Jumeirah, bounded by established villas and residential buildings, so the structural works first noted on 30-07-2025 went up on a tightly enclosed site. The report's photographs of that date, examined for this page and not reproduced, show three concrete cores rising inside climbing formwork above scaffolded lower levels, with tower cranes and concrete placing booms working inside the hoarding line.

By July 2025 the island's roads, beaches and utility connections had long been in daily use, so the tower Nakheel plans with 180- or 360-degree views toward Burj Al Arab, Burj Khalifa and Ain Dubai rose among occupied homes rather than on open land, and a buyer at 10.85% could judge the finished setting as it already stood. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Como Residences by Nakheel on Dubai Map

Buyer Resources for This Project

Investing in Como Residences as Structural Works Began

At 10.85%, with foundations recorded as completed and the next scheduled instalment dated 30-10-2025, payment protection and residency planning were the live questions. Each resource below is matched to this stage of Como Residences.

Como Residences by Nakheel in Palm Jumeirah construction updates cover image featuring a project rendering of the waterfront tower and surrounding skyline in Dubai - Presented by Tohid Fetrat
You Are Here

Como Residences Construction Updates

This page: the July 2025 Como Residences register reading of 10.85%, with structural works first noted.

Como Residences by Nakheel in Palm Jumeirah Golden Visa concept graphic featuring the waterfront tower and residency investment theme in Dubai - Presented by Tohid Fetrat

Como Residences Golden Visa: 81 Residences on Palm Jumeirah

Como Residences, Nakheel's 81-residence tower on Palm Jumeirah, has each listed unit type clear the threshold individually, under Oqood during construction.

Read Como Residences Golden Visa Guide
Como Residences by Nakheel in Palm Jumeirah escrow account protection concept featuring the waterfront tower with shield and padlock icons in Dubai - Presented by Tohid Fetrat

Como Residences Escrow: Nakheel's Palm Jumeirah Account at Commercial Bank of Dubai

Nakheel's Como Residences on Palm Jumeirah is DLD project 2565, with 81 units and its escrow at Commercial Bank of Dubai.

Verify Como Residences Escrow Account

Update Timeline

Other Como Residences Construction Updates

July 2025 falls between the May 2025 and November 2025 readings; opening the three pages in date order shows the record on either side of the first report to note structural works.

All Como Residences Construction Updates

FAQs

Como Residences Construction Progress in July 2025: Frequently Asked Questions

Como Residences read 10.85% in the DLD project register for the 30-07-2025 inspection, up from 6.07% on 01-05-2025. Because the Independent Progress Monitoring Report of the same date carries no percentage of its own, 10.85% is a register figure; it was 422 days old on 25-09-2026, so confirm the current Dubai REST entry before relying on it.

It was the fastest interval on the record to that date: 4.78 points over the 90 days from 01-05-2025 to 30-07-2025, or 1.59 points per 30-day month, against 0.57 in the interval to May 2025, 0.31 to January 2025, 0.27 to August 2024 and 0.01 points over 258 days to November 2023. Those 4.78 points were about 44% of the whole 10.85% reading, and the average since the 27-09-2023 start rose to 0.48 points per 30-day month over 672 days. All of this is arithmetic on dated register entries, not a forecast; the dated sequence is set out on the Como Residences inspection record.

In the report dated 30-07-2025, which recorded structural works progressing at site. None of the five earlier reports, from 22-02-2023 to 01-05-2025, mentioned structural works. The report names no floor or level reached, and this page does not supply one.

It listed enabling and foundation works as completed, with mobilization works still noted as ongoing. The previous report, dated 01-05-2025, had described enabling and foundation works as progressing at site. The July report gives no date on which the foundations were finished, so none is stated here.

No. Nakheel's launch schedule of record dated no instalment between 01-05-2025 and 30-07-2025, so the scheduled share of the price stayed at 60%: 20% upon booking plus four 10% instalments, the last dated 30-04-2025. Over the same span the register moved from 6.07% to 10.85%. The next dated 10% was 30-10-2025, 92 days after the July inspection. The figures are schedule arithmetic with no judgment attached, and any unit bought today follows the terms of its own contract.

605 days. The DLD record showed 27-03-2027 as the registered completion date, and the 30-07-2025 reading of 10.85% left 89.15 points still to cover. Nakheel's expected handover is Q3 2027, later than the registered date; the two are recorded entries shown side by side, and neither is turned into a required pace or a delivery forecast.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2025 inspection record for Como Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts