Como Residences by Nakheel in Palm Jumeirah project rendering used for the November 2025 construction update showing the planned rooftop infinity pool and panoramic skyline views in Dubai - Presented by Tohid Fetrat

Nakheel · Palm Jumeirah · Construction Update

Como Residences Construction Update - November 2025

November 2025 Inspection Recorded Como Residences at 15.30% as MEP and Internal Works Entered the Notes on Palm Jumeirah

The 10-11-2025 report added MEP and internal works to the structural works progressing at Como Residences, alongside completed foundations, with the DLD register at 15.30%.

Direct advisor access. Every message answered personally, never by a call center.

15.30%DLD Register Reading
10-11-2025Inspection Date
Q3 2027Expected Handover
2565DLD Project Number

Verified DLD Inspection Data

Como Residences Construction Snapshot

Up 4.45 points in the 103 days after 30-07-2025, the 15.30% reading of 10-11-2025 moved at 1.30 points per 30-day month, below July's 1.59 but above every interval before it, and Como Residences remained inside the early stage band, still under 20%, where escrow and Oqood checks still lead.

Project Name

Como Residences by Nakheel

Project Number

2565

Project Status

Active

Construction Progress

15.30%

Inspection Date

10-11-2025

Construction Start

27-09-2023

Total Units

81 residences

Total Built Area

68,563.62 sq m

Expected Completion

Q3 2027

Data source: DLD project register, 15.30% for the inspection conducted on 10-11-2025 and 10.85% for the previous inspection on 30-07-2025. The Independent Progress Monitoring Report dated 10-11-2025 prints no percentage; its Progress Status reads Main Contract - Progressing, and its notes and the register fields are quoted on this page as they stand. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Written on 25-09-2026 about the record as of 10-11-2025, a reading 319 days old at that date: re-verify on Dubai REST before publishing. The hero image is a rendering of Nakheel's planned rooftop infinity pool: design intent, not the site and not progress. Last updated: November 2025.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Como Residences Construction Progress Summary

No earlier report on Como Residences had named MEP or internal works; the one dated 10-11-2025 listed them with structural works as progressing at different stages, while enabling and foundation works stayed completed and mobilization ongoing. The 4.45 points of this interval are about 29% of the 15.30% reading; measured from the 27-09-2023 construction start, 775 days earlier, the reading works out at 0.59 points per 30-day month, an arithmetic average rather than a forecast.

On Record by 10-11-2025
  • Enabling and foundation works, again listed as completed on 10-11-2025
  • Main Contract - Progressing status on four consecutive reports since January 2025
  • Six dated readings before this one, starting at 0% on 22-02-2023 and ending at 10.85% on 30-07-2025
In Progress at 15.30%
  • Structural works, progressing for a second report in a row
  • MEP and internal works, named for the first time, at different stages
  • Mobilization works, noted as ongoing once more
  • DLD register reading of 15.30%, 4.45 points above July 2025
Ahead of Handover
  • The rest of the Ground + 3 podiums + 72 floors Residential structure described in the report
  • External finishes, named in the project description but not yet in the notes
  • Nakheel's Q3 2027 handover, shown with the registered completion date of 27-03-2027
Next inspectionThe April 2026 update page, linked in the Updates section below, carries the reading taken after this one.
Completion targetQ3 2027 is Nakheel's expected handover, while the DLD record held the registered completion date of 27-03-2027, 502 days after the 10-11-2025 inspection. Both are recorded entries shown together; neither is turned into a required pace or a forecast.
Remaining distance84.70 percentage points lay between the 10-11-2025 reading and 100%.

Payment Linked Progress

What 15.30% Progress Means for Como Residences Buyers

The fifth 10% instalment in Nakheel's launch schedule of record was dated 30-10-2025, eleven days before this inspection, taking the scheduled total to 70%: 20% upon booking plus five 10% instalments, set against a register reading of 15.30% on 10-11-2025. The next 10% was dated 30-04-2026. That pairing is schedule arithmetic, recorded without judgment. With MEP and internal works entering the notes, four actions matter most.

11 Days After the October Instalment

Verify the escrow account

The 10% dated 30-10-2025 fell due just before this reading, and the next was dated 30-04-2026, 171 days after it. For either transfer, the receiving account should be the DLD regulated escrow account registered to project 2565: Como Residences escrow account verification sets out the check, and the lookup takes about two minutes against the official DLD project record.

Against the 70% Scheduled

Reread your SPA milestone schedule

Your own contract may date or trigger payments differently from the launch schedule of record. Where a clause refers to MEP, fit out or any other stage, read it beside the report of 10-11-2025, the first to name MEP and internal works, and its 15.30% reading. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.

943 Days on the Register

Check your Oqood entry

Project 2565 had been on the DLD register for 943 days by 10-11-2025. Oqood records each off plan sale against that number, so after the October 2025 instalment confirm that the entry still shows the right unit, buyer names and project before the April 2026 payment.

Every Cycle

Read the slower interval in context

At 1.30 points per 30-day month, the interval to 10-11-2025 ran below July's 1.59 yet above the 0.57, 0.31 and 0.27 recorded before it, and one slower interval is not a trend. The Como Residences dated reading history sets every register entry in sequence.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 15.30%?

An entry at this reading came as MEP and internal works first appeared in the notes beside structural works; by then 70% of the launch schedule of record was dated, against a Q3 2027 handover expected by Nakheel. Every payment goes to the DLD-registered escrow account for project 2565, released against construction progress recorded in the DLD project register.

Entering at 15.30%
  • MEP and internal works noted as under way on 10-11-2025
  • 84.70 points between this reading and 100%
  • Launch schedule still to run: 10% on 30-04-2026, 20% on handover
Typical Late Stage Entry
  • Structure and envelope largely visible before signing
  • Months rather than years between contract and handover
  • Little of the price left to phase, often at later prices
AED 27.00M ≈ USD 7.35MStarting Price
81 ResidencesTotal in the Tower
Q3 2027Expected Handover
Ask What Is Available at Como Residences

Unit availability is confirmed at the time of each enquiry; availability shifts between cycles.

About the Development

Como Residences Project Details

Como Residences by Nakheel ultra luxury tower rising above Palm Jumeirah with panoramic Gulf views in Dubai Presented by Tohid Fetrat
Palm Jumeirah · Nakheel

At the 10-11-2025 inspection, Como Residences had completed foundations and structural, MEP and internal works under way in Nakheel's 71-floor seashell tower of 81 homes, from 2 bedroom apartments up to a 7 bedroom duplex. Starting prices today: AED 27.00M ≈ USD 7.35M.

Entering at 15.30% meant 84.70 points of recorded progress still ahead and 70% of the launch schedule of record already dated, with one 10% set for 30-04-2026 and the final 20% tied to the Q3 2027 handover.

Como Residences by Nakheel Project Guide

Site Context This Cycle

Explore Como Residences Location on Dubai Map

Plot 2692 lies in the heart of Palm Jumeirah, closely bordered by existing villas and apartment buildings, so the MEP and internal works first noted on 10-11-2025 began inside a structure rising on a tight plot. Photographs in that report, examined for this page but not republished, show podium levels wrapped in scaffolding with concrete cores above them, a covered level still propped on shoring beneath a cast slab, and tower cranes over the hoarding at street level.

With the island's roads, beaches and services long in use by November 2025, Como Residences was taking shape among lived-in streets, and Nakheel's plan for panoramic views toward Burj Al Arab, Burj Khalifa and Ain Dubai could be weighed against a skyline that already stood rather than one still to come. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Como Residences by Nakheel on Dubai Map

Buyer Resources for This Project

Investing in Como Residences as MEP Works Entered the Record

At 15.30%, with the October 2025 instalment just past and the next dated 30-04-2026, payment protection and residency planning stayed the practical questions. Each resource below answers one of them for Como Residences at this reading.

Como Residences by Nakheel in Palm Jumeirah construction updates cover image featuring a project rendering of the waterfront tower and surrounding skyline in Dubai - Presented by Tohid Fetrat
You Are Here

Como Residences Construction Updates

This page: the November 2025 Como Residences register reading of 15.30%, with MEP works first noted.

Como Residences by Nakheel in Palm Jumeirah Golden Visa concept graphic featuring the waterfront tower and residency investment theme in Dubai - Presented by Tohid Fetrat

Como Residences Golden Visa: 81 Residences on Palm Jumeirah

Como Residences, Nakheel's 81-residence tower on Palm Jumeirah, has each listed unit type clear the threshold individually, under Oqood during construction.

Read Como Residences Golden Visa Guide
Como Residences by Nakheel in Palm Jumeirah escrow account protection concept featuring the waterfront tower with shield and padlock icons in Dubai - Presented by Tohid Fetrat

Como Residences Escrow: Nakheel's Palm Jumeirah Account at Commercial Bank of Dubai

Nakheel's Como Residences on Palm Jumeirah is DLD project 2565, with 81 units and its escrow at Commercial Bank of Dubai.

Verify Como Residences Escrow Account

Update Timeline

Other Como Residences Construction Updates

November 2025 sits between the July 2025 and April 2026 readings; reading the three in order shows the record before and after MEP and internal works were first named.

All Como Residences Construction Updates

FAQs

Como Residences Construction Progress in November 2025: Frequently Asked Questions

Como Residences read 15.30% in the DLD project register for the 10-11-2025 inspection, up from 10.85% on 30-07-2025. The regulator's Independent Progress Monitoring Report for that date prints no percentage, so 15.30% is the register's figure; it was 319 days old on 25-09-2026, and the current Dubai REST entry should be checked before it is relied on.

In rate terms, yes: the reading rose 4.45 points over the 103 days from 30-07-2025 to 10-11-2025, or 1.30 points per 30-day month, against 1.59 in the 90 days to July 2025. It was still faster than every interval before July: 0.57 to May 2025, 0.31 to January 2025 and 0.27 to August 2024. The November report gives no reason for the change and none is offered here; the figures are worked from dated register entries and are not a forecast, and the full sequence sits on the Como Residences register history.

MEP stands for mechanical, electrical and plumbing, the building services that carry cooling, power and water. The report dated 10-11-2025 was the first on the Como Residences record to name MEP and internal works, listing them beside structural works as progressing at different stages. It gives no floor, zone or percentage for any of the three, so this page does not divide them further.

No. The report's project description names a concrete structure and block with internal and external finishes, and by 10-11-2025 its notes had covered enabling, foundation, structural, MEP and internal works, but not external finishes or facade works. The notes do not identify any floor or level reached, so none is given here.

Eleven days. The fifth 10% instalment in Nakheel's launch schedule of record was dated 30-10-2025 and the inspection took place on 10-11-2025, which brought the scheduled total to 70% (20% upon booking plus five 10% instalments) against a register reading of 15.30%. The next 10% was dated 30-04-2026, 171 days after the inspection, with the final 20% due on handover. The pairing is arithmetic from the schedule, offered without judgment; a unit bought now is governed by its own contract terms.

11.00 points: from 4.30% on 28-01-2025, the first report to carry the Main Contract - Progressing status, to 15.30% on 10-11-2025, across 286 days and three inspection intervals, an average of 1.15 points per 30-day month. That span accounts for about 72% of the whole 15.30% reading, the rest having been recorded under the earlier Pre-Construction status. These figures are calculated from dated register entries and do not forecast later readings.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the November 2025 inspection record for Como Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts