Cove Grand by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the residential tower in Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Dubai Land Residence Complex

Cove Grand by Imtiaz Construction Updates

The Dated DLD Record for a Single 538-Residence Tower in Dubailand

Cove Grand by Imtiaz read 13.4% in the DLD register on 8 October 2026, the record's first dated figure and the foundations baseline for one Dubailand tower.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

13.4%Construction Progress
8 October 2026Latest RERA Inspection
538 residencesTotal Units
Project 3774DLD Registration

Construction Snapshot

Cove Grand by Imtiaz at a Glance

Imtiaz Developments is building Cove Grand by Imtiaz as one 1B+G+3P+17+R tower holding 538 apartments in Dubai Land Residence Complex, and its handover is expected in Q4 2027. The register dates its construction start to 30 May 2025, and 496 days later, on 8 October 2026, it read 13.4%. A record this young works less as a progress report than as a set of fixed anchors: every later reading for this tower will be measured against the figures below.

DLD Project Number

3774

Project Status

Active

Construction Start

30 May 2025

Total Units

538 residences

Total Built-Up Area

31,600.58 sq m

Registered Completion Date

15 December 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Cove Grand by Imtiaz Construction Update Timeline

The Cove Grand record holds one dated reading so far: 13.4% on 8 October 2026, taken 496 days after the registered start of 30 May 2025. The register also shows a previous inspection at 8.67% but prints no date for it, so that reading appears on the track below as an unlabelled dot rather than as a table row. Each reading that posts from here adds a dot to the track and a row to the table, linked to its own monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
October 202613.4%8 October 2026View the October 2026 update

Pace Analysis

How Fast Cove Grand by Imtiaz Has Been Built

With one dated reading on record, Cove Grand's pace can only be read as arithmetic from the register's own dates, not yet as a measured curve between inspections. Two figures frame it:

  • 30 May 2025 to 8 October 2026: registered start to the 13.4% reading over 496 days, enabling, piling and foundationsAbout 0.81 points per month
  • 8 October 2026 to the 15 December 2027 registered completion date: the remaining 86.6 points spread evenly over 433 daysAbout 6.00 points per month

Neither figure is a forecast. The 0.81 average spans the below-ground phase of a 1B+G+3P+17+R tower, which the RERA report of 8 October 2026 lists as enabling, piling and foundation works completed with substructure works progressing and mobilisation still ongoing. The 6.00 figure is only the even spread that would carry the remaining 86.6 points to the registered completion date, a date that also sits inside the Q4 2027 handover quarter. The undated 8.67% previous reading cannot be turned into a velocity, so the first measured pace for Cove Grand arrives with the next dated reading after 8 October 2026. For an end user planning a Q4 2027 move, and for an investor timing the completion payment, that next reading is the first point at which the record shows a rate rather than an average.

Get the Next Inspection Figure First

Tell me you are tracking Cove Grand by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Cove Grand by Imtiaz at Dubai Land Residence Complex

The 13.4% recorded on 8 October 2026 only means something next to what the tower will hold at handover. The project guide covers the finished building this record is tracking toward:

Cove Grand by Imtiaz in Dubai Land Residence Complex project rendering showing residential tower exterior render in Dubai - Presented by Tohid Fetrat

Cove Grand by Imtiaz, a 17-Floor Dubailand Tower

Cove Grand by Imtiaz holds 538 furnished studios and one to three bedroom apartments in one tower beside the park.

View the Cove Grand by Imtiaz Project Guide

Considering an Early-Stage Entry?

Entering Cove Grand at the foundations stage puts you on Imtiaz's calendar-dated instalment schedule with several dates already passed, and the choice of remaining apartments narrows as the tower rises. If the record on this page is what brought you here, ask me for current availability before the next instalment date.

Ask About Remaining Availability on WhatsApp

Stage Record

Cove Grand by Imtiaz Build Stages, Mapped to the Inspections

Cove Grand's record is still short, so the stage map below pins the completed and current steps to the register dates and the 8 October 2026 report, and leaves the three later steps open until dated readings arrive for them.

30 May 2025 to Oct 2026

Site Activation, Enabling and Piling

From the registered construction start of 30 May 2025, with DLD registration on 12 June 2025, to the 8 October 2026 report, which lists enabling and piling works as completed and mobilisation as ongoing.

Current PhaseOct 2026, 13.4% at last reading

Foundations and Substructure

Foundation works under the single tower were recorded as completed and substructure works as progressing when the register read 13.4% on 8 October 2026, up from an undated 8.67%.

After Oct 2026, no reading yet

Podium and Tower Structure

The ground floor, the three podium levels and the 17 residential floors of the 1B+G+3P+17+R building, which no dated reading has reached so far.

Not yet reached

Envelope, Fit-Out and Amenity Decks

Facade closure, fit-out of the 538 furnished apartments, the landscaped first-floor amenity podium and the rooftop pool deck shown in the developer floor plans.

Toward Q4 2027

Finishing, Commissioning and Handover

The closing readings toward 100%, with handover expected in Q4 2027 and the DLD registered completion date falling inside that same quarter.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Grand by Imtiaz's own record.

Buyer Position

Tracking Your Position at Cove Grand by Imtiaz

This page is one of four project resources that together cover a Cove Grand by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Grand by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the residential tower in Dubai - Presented by Tohid Fetrat
You Are Here

Cove Grand by Imtiaz Construction Updates

This page: the dated register record for Cove Grand, from its May 2025 start to handover.

Cove Grand by Imtiaz in Dubai Land Residence Complex Golden Visa concept graphic with a gold card and residential tower rendering in Dubai - Presented by Tohid Fetrat

Cove Grand by Imtiaz Golden Visa: Every Type Measured

Cove Grand, one tower of 538 Imtiaz residences, has no apartment type at AED 2M; even the 3 bedroom sits below.

Read the Cove Grand by Imtiaz Golden Visa Guide
Cove Grand by Imtiaz in Dubai Land Residence Complex escrow concept graphic with a shield and padlock over an interior rendering in Dubai - Presented by Tohid Fetrat

Cove Grand by Imtiaz Escrow: 538 Units at Ajman Bank

Cove Grand by Imtiaz Developments is DLD project 3774, 538 units in Ajman Bank escrow, 13.4% certified October 2026.

Verify the Cove Grand by Imtiaz Escrow Account

Approaching Handover

Between 13.4% and Handover: What Cove Grand by Imtiaz Buyers Should Do Now

Payments at Cove Grand follow the calendar rather than the build. When the register read 13.4% on 8 October 2026, buyers on the 50/50 plan had 40% of the price due and buyers on the three year post handover plan 45%; with the 15 October 2026 instalment those shares became 45% and 50%. The next dated instalment under both plans, 5% on 15 March 2027, is the point by which the three steps below should be settled, not the day it falls due.

First, confirm that every instalment is going to the Ajman Bank escrow account that the DLD register ties to project 3774; the Cove Grand by Imtiaz escrow account page shows how to check it against the DLD record.

Second, settle residency expectations early, since none of the four Cove Grand apartment types reaches the property value threshold on its starting price; the Cove Grand by Imtiaz Golden Visa guide sets out what that means for an application.

Third, choose between the 50/50 plan and the three year post handover plan before you sign, using the schedules in the Cove Grand by Imtiaz project guide, since the plan sets how much of the price is still ahead of you at the Q4 2027 handover.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Land Residence Complex Structure

A foundations-stage record is only part of the picture; the rest is the community, the market, and the developer around the plot. These three pages place the 13.4% Cove Grand reading of 8 October 2026 in that context:

Dubailand Residence Complex properties for sale in Dubai showing a modern residential building with balconies and landscaped surroundings, Presented by Tohid Fetrat

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand

Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.

See Dubai Land Residence Complex Properties for Sale
Street view of Dubailand Residence Complex community in Dubai showing modern residential buildings, landscaped roads and pedestrian areas, Presented by Tohid Fetrat

Dubai Land Residence Complex: Dubailand's Established Apartment Community

Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.

Explore the Dubai Land Residence Complex Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Cove Grand by Imtiaz Construction Updates Frequently Asked Questions

Cove Grand by Imtiaz, DLD project 3774, is an active project in its foundations and substructure stage, with the Dubai Land Department register reading 13.4% as of 8 October 2026. The RERA report of that date lists enabling, piling and foundation works as completed and substructure works as progressing; the dated record sits in the Cove Grand inspection timeline above.

The register reading of 13.4% on 8 October 2026 is 4.73 points above the previous inspection reading of 8.67%, which the DLD register lists without a date. Because that earlier reading carries no date, the rise cannot be converted into a monthly pace; the October 2026 Cove Grand by Imtiaz inspection update covers the 13.4% reading in full.

Handover for Cove Grand by Imtiaz is expected in Q4 2027, and the DLD register lists a registered completion date of 15 December 2027, which falls inside that quarter. When the register read 13.4% on 8 October 2026, that date was 433 days away and had not passed, so no lapsed-date framing applies; this page's record is updated as each new reading posts.

The Cove Grand by Imtiaz tower will contain 538 residences, the unit count held in the DLD register for project 3774. Its 1B+G+3P+17+R configuration stacks 17 residential floors above a basement, the ground floor and three podium levels, under a roof level, and the developer floor plans put the three bedroom apartments on floors 8 to 17 only.

Counting from its 30 May 2025 registered start, Cove Grand by Imtiaz gained 13.4 points in 496 days to the 8 October 2026 reading, about 0.81 points per month. Spreading the remaining 86.6 points evenly over the 433 days to the registered completion date gives about 6.00 points per month; both figures are arithmetic, not a forecast, and the Cove Grand pace analysis sets them side by side.

The Cove Grand by Imtiaz timeline runs from a registered construction start of 30 May 2025, through the 13.4% register reading of 8 October 2026, to an expected handover in Q4 2027. Between those points the tower has to rise from its foundations through three podium levels and 17 residential floors, and each dated reading joins the timeline as it posts to the register.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Grand by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.