Evergreens at DAMAC Hills 2 Construction Updates
The Register Record for 131 Park and Pool View Apartments
Evergreens read 26.43% on the DLD register on 5 May 2026, up from 17.19%, a climb that carried its DAMAC Hills 2 frame beyond the foundation stage.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Evergreens at DAMAC Hills 2 at a Glance
Evergreens is DAMAC's 131-residence apartment project in DAMAC Hills 2, registered with the Dubai Land Department as project 3092 on 23 May 2024, with construction under way since 3 July 2024. Its record is still short, a single dated register reading of 26.43% on 5 May 2026, and the RERA progress report of that day describes a mid-rise residential building of ground, podium, seven upper floors and roof. The developer floor plans arrange its residences in two wings, labelled Tower A and Tower B, around a central pool deck, so one record here tracks both the park-view and the pool-view homes.
3092
Active
3 July 2024
131 residential units
16,030.41 sq m
Q4 2026 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Evergreens at DAMAC Hills 2 Construction Update Timeline
The Evergreens record so far holds one dated reading and one undated one. The DLD inspection card dated 5 May 2026 gives 26.43% as current progress and 17.19% as the previous inspection, with no date attached to that earlier visit, so the track below plots 17.19% as an undated point and the table carries a single dated row. That row links the full May 2026 update, whose hero image is a developer rendering rather than a record of construction progress.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 26.43% | 5 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Evergreens at DAMAC Hills 2 Has Been Built
With one dated reading on the register, Evergreens has no measured inspection-to-inspection pace yet. What its record does support is arithmetic from the July 2024 start, labelled here as arithmetic, not a forecast:
- 3 July 2024 to 5 May 2026: construction start to the 26.43% reading, 671 daysAbout 1.18 points per month
- Undated 17.19% previous field to 26.43% on 5 May 2026: a 9.24 point differenceNo measured rate
- 5 May 2026 to 31 December 2026: 73.57 points to reach 100% by the end of Q4 2026About 9.20 points per month
Read together, these numbers describe the opening of a curve rather than a settled rate. The 671-day average folds in mobilization, enabling works and the foundations the RERA report called substantially completed on 5 May 2026, while the same report placed the concrete frame of ground, podium, seven upper floors and roof at advanced stages and MEP only at an early stage. The 9.20 figure simply spreads the 73.57 points still to be recorded across the 240 days to the last day of Q4 2026; it is arithmetic, not a forecast. What turns all three lines into a real pace is a second dated reading: for an end user it is the figure to set against the Q4 2026 target, and for an investor it is the first true measure of how quickly DAMAC is moving this 131-residence building through services and finishes.
Get the Next Inspection Figure First
Tell me you are tracking Evergreens at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Evergreens at DAMAC Hills 2
A register percentage means more next to the homes it is building toward. The project guide sets out what this record tracks:

Evergreens at DAMAC Hills 2, Reached via Al Qudra Road
Evergreens at DAMAC Hills 2 is a DAMAC apartment project of 131 one and two bedroom homes, each with a balcony.
View the Evergreens at DAMAC Hills 2 Project GuideConsidering an Early-Stage Entry?
Evergreens has limited units available as of this update, and the choice of layout and outlook narrows as construction moves on. If the record on this page is what brought you here, ask me for current availability and the installments already due before you settle on a unit.
Ask About Remaining Availability on WhatsAppStage Record
Evergreens at DAMAC Hills 2 Build Stages, Mapped to the Inspections
Each stage below is pinned to a dated event in the Evergreens record, from registration on 23 May 2024 and the 3 July 2024 start to the 26.43% reading of 5 May 2026, so the stage marked current reflects that reading and the RERA notes of the same day.
Registration and Mobilization
Project 3092 entered the DLD register on 23 May 2024 and construction started 41 days later on 3 July 2024; the RERA report still listed mobilization as ongoing on 5 May 2026.
Enabling Works and Foundations
By the 5 May 2026 inspection, enabling and foundation works beneath the DAMAC Hills 2 building were reported substantially completed, the base under every later reading.
Concrete Frame, Podium to Roof
Structure works on the frame of ground, podium, seven upper floors and roof were reported at advanced stages on 5 May 2026, when the register read 26.43%, up from an undated 17.19%.
Services, Blockwork and Facade
MEP works stood at an early stage on 5 May 2026; blockwork and the crisp white facade shown in DAMAC's brochure renderings follow across both floor-plan wings.
Interiors, Pool Deck and Handover
Interior finishes in 131 apartments, the central pool deck between the Tower A and Tower B wings, and resident amenities such as the outdoor cinema close the record at 100%.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Evergreens at DAMAC Hills 2's own record.
Buyer Position
Tracking Your Position at Evergreens at DAMAC Hills 2
This page is one of four project resources that together cover a Evergreens at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Evergreens at DAMAC Hills 2 Construction Updates
This page: the Evergreens record from the July 2024 start to 26.43% on 5 May 2026.

Evergreens at DAMAC Hills 2 Golden Visa: A Clear Threshold Check
Neither the 1 nor 2 bedroom at Evergreens at DAMAC Hills 2, DAMAC's 131-residence project, qualifies alone, under Oqood now.
Read the Evergreens at DAMAC Hills 2 Golden Visa Guide
Evergreens at DAMAC Hills 2 Escrow: DAMAC's Emirates NBD Account
Evergreens at DAMAC Hills 2 is DLD project 3092, its 131 units escrowed at Emirates NBD, 26.43% certified in May 2026.
Verify the Evergreens at DAMAC Hills 2 Escrow AccountApproaching Handover
Between 26.43% and Handover: What Evergreens at DAMAC Hills 2 Buyers Should Do Now
At 26.43% on 5 May 2026, Evergreens buyers are paying through the construction phase rather than preparing for keys: the 20/50/30 plan places 50% across construction per the developer's schedule and 30% on handover, targeted for Q4 2026. Each new register reading lands alongside those installment decisions, so the three checks below belong before the next payment rather than after it.
First, confirm that every construction-share installment goes to the DLD-registered trust account for project 3092 at Emirates NBD; the Evergreens escrow account guide shows how to check the register entry before you transfer.
Second, settle residency expectations early: neither Evergreens apartment type reaches the Golden Visa property threshold on its own, and the Evergreens Golden Visa explainer sets out what that means for your purchase.
Third, match your unit and price to the plan before the next installment falls due, using the Evergreens project page for the current 1 and 2 bedroom prices and the 20/50/30 structure.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills 2 Structure
A single building's record reads better against its surroundings. These three pages place the Evergreens build inside the DAMAC Hills 2 market, its master community and DAMAC's developer portfolio:

DAMAC Hills 2 Properties for Sale
Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.
See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 Community Overview
Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.
Explore the DAMAC Hills 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Evergreens at DAMAC Hills 2 Construction Updates Frequently Asked Questions
Evergreens, DLD project 3092, holds Active status on the Dubai Land Department register, which put its construction at 26.43% on 5 May 2026. The RERA report from that same day lists the main contract as progressing, so the 131-residence building stood in its superstructure stage at that reading; the dated record sits in the Evergreens inspection timeline above.
The Evergreens timeline runs from DLD registration on 23 May 2024 to a construction start on 3 July 2024 and a single dated reading of 26.43% on 5 May 2026. The same inspection card shows a previous field of 17.19% with no date attached, so that earlier reading appears on the track as an undated point rather than a table row; the dated reading is covered in full in the Evergreens May 2026 construction update.
Progress at Evergreens is tracked through the Dubai Land Department project register for project 3092, which showed 26.43% on 5 May 2026, read together with the RERA Independent Progress Monitoring Report from that same visit. The RERA document carries site notes and the status Main Contract, Progressing but no percentage, so every figure on this page is a DLD register reading, re-verified against the register before each update. The general method is set out on the Dubai Construction Updates methodology hub.
The DLD record for project 3092 carries no registered completion date: its completion field holds a blank placeholder rather than a date, so there is no registered deadline for Evergreens to be measured against and nothing on the record has lapsed. The handover target used throughout this page is Q4 2026, set against a register reading of 26.43% on 5 May 2026; actual handover is confirmed by DAMAC as final works and inspections complete, and this record is updated as each new reading posts.
Measured from the 3 July 2024 construction start, Evergreens averaged about 1.18 percentage points per month to reach 26.43% on 5 May 2026, an average that folds in the earlier mobilization, enabling and foundation phases. Reaching 100% by 31 December 2026, the last day of the Q4 2026 handover target, works out at about 9.20 points per month from that reading. Both figures are arithmetic, not a forecast, and no inspection-to-inspection rate exists yet because the 17.19% previous reading is undated; the Evergreens pace analysis shows the workings.
Evergreens includes 131 residential units, all 1 bedroom and 2 bedroom apartments, the same count shown on the DLD register for project 3092. The RERA progress report of 5 May 2026 describes a mid-rise residential building of ground, podium, seven upper floors and roof, while the developer floor plans arrange the residences in two wings, labelled Tower A and Tower B, around a central pool deck with park-view and pool-view orientations. The record used for this page carries no built-up area figure.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Evergreens at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.