DAMAC Properties · DAMAC Hills · Construction Update
Golf Gate 2 Construction Update - November 2025
November 2025 Inspection Confirms Golf Gate 2 Reaches 43.25% Construction Progress at DAMAC Hills
Structure works at advanced stages, with internal, MEP, and finishing packages running in parallel, place Golf Gate 2 at 43.25 percent in the November 2025 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Golf Gate 2 Construction Snapshot
A 13.13 point rise since the previous recorded inspection places Golf Gate 2 in the superstructure band, the stage where the tower gains height faster than it gains finishes, and where the payment schedule still runs on calendar dates rather than on certified progress.
Golf Gate 2 at DAMAC Hills
2698
Active
43.25%
27 November 2025
03 August 2023
464 apartments
78,793.05 sq m
Not stated in the DLD record
Data source: RERA Independent Progress Monitoring Report for the inspection conducted on 27 November 2025, tracked against the DLD project register for project 2698. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.
This Inspection Cycle
Golf Gate 2 Construction Progress Summary
Golf Gate 2 moved from 30.12% to 43.25% between its last two RERA readings, a 13.13 point gain earned inside the concrete frame of the G+2P+27 tower rather than in anything a passer by would recognize as a finished building. The inspector recorded structure works at advanced stages, with block work, MEP, and finishing packages already opened on the floors below. The project is registered to DAMAC Crescent Properties, developer number 954, on plot 2128 in Al Hebiah Third.
- Enabling and foundation works across plot 2128
- Ground and podium levels carrying the level 3 amenity deck
- Lower residential floors of the 27 storey concrete frame
- Structure works on the upper floors, recorded at advanced stages
- Block work and internal partitions on the completed floors
- MEP first fix: mechanical, electrical, and plumbing rough in
- Finishing packages opened at different stages across the tower
- External finishes and facade closure on the golf course elevations
- Fit out of the 464 apartments and the podium leisure levels
- Remaining RERA cycles toward completion certification
Payment Linked Progress
What 43.25% Progress Means for Golf Gate 2 Buyers
Dubai off plan plans tie installments either to the calendar or to certified construction milestones, and the published DAMAC schedule for Golf Gate 2 does both, so a verified reading of 43.25% tells you precisely which triggers are behind you and which are still ahead. At this stage of the tower, four actions matter most.
Verify the escrow account
Every payment ahead of handover should reach only the DLD regulated escrow account registered for project 2698, whose trust account sits with Dubai Islamic Bank on the RERA record. The Golf Gate 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA against the milestone triggers
The published plan runs monthly installments from the sale date, then adds completion linked payments at the 70%, 80%, and 90% milestones with 20% falling due on completion. At 43.25% the first of those construction triggers is still 26.75 points away. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Track the register, not the render
The 13.13 point gain to 43.25% was structural, and the register is where any slowdown in the frame would surface before it reached a marketing update. The Golf Gate 2 construction updates hub carries each inspection cycle as it publishes.
Plan the snagging window early
Booking a pre handover inspection is premature at 43.25%: the window opens once a project passes roughly 70% recorded progress or falls inside nine months of handover. The Golf Gate 2 snagging inspection guide sets out what the appointment covers so the booking is ready when the window does open.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 43.25%?
Entering mid superstructure is the opposite trade to buying near handover: the frame is certified but not closed, the handover date is still a developer target rather than a registered one, and most of the payment runway is ahead of you rather than behind. Every payment goes to the DLD-registered escrow account for project 2698, released against certified construction progress.
- Certified progress: 43.25% recorded on 27 November 2025
- Structure works at advanced stages per the inspection notes
- Completion linked payments begin at the 70% milestone, still ahead
- Construction risk carried from excavation through to handover
- Two to four years of waiting is the usual delivery horizon
- Longer installment runway, priced at launch levels
Unit availability at Golf Gate 2 shifts between inspection cycles; ask for the current release before relying on any figure published earlier in the build.
About the Development
Golf Gate 2 Project Details

With the concrete frame at advanced stages and finishes only beginning, Golf Gate 2 is a superstructure stage tower of 464 one and two bedroom apartments facing the championship golf course at DAMAC Hills. Starting prices: AED 818K ≈ USD 223K for one bedroom, AED 1.47M ≈ USD 401K for two.
Entering at this stage means a longer wait in exchange for a payment structure that is still mostly ahead of you, with DAMAC targeting Q4 2026 for handover and the DLD register carrying no completion date at this cycle.
Golf Gate 2 at DAMAC Hills Project GuideSite Context This Cycle
Explore Golf Gate 2 Location on Dubai Map
Golf Gate 2 sits on plot 2128 in Al Hebiah Third, on the golf course edge of DAMAC Hills, and its single G+2P+27 massing means this cycle's progress is vertical rather than lateral: each point added to the register came from another floor of the frame rather than from ground works spread across a large plot, which is why a 13.13 point gain is visible as height rather than as footprint.
DAMAC Hills is a delivered master community with occupied clusters, schools, supermarkets, and the Trump International golf course already in use, so Golf Gate 2 is being built into a working neighborhood rather than ahead of one, and that matters at 43.25%: the surroundings a buyer is paying toward exist today, while the apartment itself is still a concrete shell. See the project's position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Golf Gate 2 During Superstructure Progress
The superstructure band is where payment protection and tracking discipline earn their keep, and where residency planning is still a forward question rather than an immediate one. Each resource below is matched to where Golf Gate 2 stands right now.

Golf Gate 2 Construction Updates
This page: the verified November 2025 inspection record for Golf Gate 2, from foundations to superstructure.
Golf Gate 2 Golden Visa
Check how a Golf Gate 2 purchase measures against the property threshold for 10-year UAE residency.
Read the Golf Gate 2 Golden Visa Guide
Golf Gate 2 Escrow Account
Confirm the DLD registered escrow account for project 2698 before releasing any further monthly installment.
Verify the Golf Gate 2 Escrow Account
Golf Gate 2 Snagging Inspection
At 43.25% the booking window is still ahead; learn what defect documentation covers before you accept.
Read the Golf Gate 2 Snagging GuideUpdate Timeline
Other Golf Gate 2 Construction Updates
November 2025 is the first inspection cycle published for Golf Gate 2 on this site, so the timeline runs forward from here, reading by reading, as each RERA report is released.
Where This Update Fits
Explore Golf Gate 2 Structure
This monthly report is one node in the wider record: the community that surrounds the site, the developer delivering it, and the homes already trading around it.

DAMAC Hills Villas and Townhouses for Sale
Compare delivered DAMAC Hills homes available now against a Golf Gate 2 apartment still under construction.
DAMAC Hills Villas and Townhouses for Sale
About DAMAC Hills Master Community
See how the golf course, schools, and retail already operating at DAMAC Hills frame this site.
DAMAC Hills Community GuideDAMAC Properties Developer Profile
Review DAMAC's delivery record across DAMAC Hills before your remaining monthly installments fall due.
DAMAC Properties Developer ProfileFAQs
Golf Gate 2 Construction Progress in November 2025: Frequently Asked Questions
As of the RERA inspection conducted on 27 November 2025, Golf Gate 2 stands at 43.25% construction progress in the DLD project register, across 78,793.05 sq m of built area on plot 2128 in Al Hebiah Third.
The register records 30.12% at the previous inspection and 43.25% on 27 November 2025, a gain of 13.13 points concentrated in the concrete frame of the G+2P+27 tower. No date is published against that earlier reading, so the gain is stated without a cycle length.
The DLD project register carried no completion date at the November 2025 cycle: the field returns a system null rather than a date. DAMAC states a Q4 2026 handover target, which is a developer figure and not a registered one, so the two should never be quoted as the same thing. How inspection cycles and completion certification work is covered on the Golf Gate 2 construction updates hub.
The inspection notes record structure works progressing at advanced stages on the concrete frame, with internal, MEP, and finishing works progressing at different stages across the completed floors, and main contract mobilization still ongoing on site.
Not by itself. The published DAMAC plan runs monthly installments from the sale date, and its construction linked payments begin at the 70% completion milestone, which is 26.75 points above the November 2025 reading, followed by steps at 80% and 90% and 20% on completion. Your own SPA is the governing document for the schedule that applies to your unit.
Not at this reading. The practical booking window opens once a project passes roughly 70% recorded progress or comes within about nine months of handover, and at 43.25% in November 2025 Golf Gate 2 met neither condition: the frame was still rising and no apartment interiors were near completion.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the November 2025 inspection record for Golf Gate 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.