Emaar · Dubai Hills Estate
Hills Park at Dubai Hills Estate Construction Updates
The Closed Build Record of a Handover Ready Emaar Address
The 08 October 2025 RERA inspection recorded Hills Park at 100%, closing a thirty five month build in Dubai Hills Estate with handover status Ready.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Hills Park at Dubai Hills Estate at a Glance
Hills Park is Emaar's 444 apartment residential and retail building on plot 4792 in Dubai Hills Estate, entered on the Dubai Land Department register as project 2428 on 28 July 2022. Thirty five months separate its 05 November 2022 construction start from the 100% recorded at the inspection of 08 October 2025, and the six figures below are the registered anchors behind that record. The record itself is unusually short for a build of that length: one published reading, and it is the closing one, because tracking here begins at the point the building was already certified complete.
2428
Finished
05 November 2022
444 residential units
37,961.23 sq m
30 April 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Hills Park at Dubai Hills Estate Construction Update Timeline
One inspection carries this record. The DLD file for project 2428 shows 100% current progress on 08 October 2025 against 98.95% at the reading before it, and enters the RERA progress status as Completed, which is why no further inspection date follows it. The track below marks that closing reading against the November 2022 site start, and the row beneath opens the October 2025 report with the certification dates and site notes behind the figure.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2025 | 100% | 08 October 2025 | View the October 2025 update |
Reading the dates: the completion date registered for project 2428 is 30 April 2026, recorded when the project was entered on the register on 28 July 2022. Construction was certified at 100% on 08 October 2025, nearly seven months earlier, so a registered date now behind us sits beside a building the register already carries as Finished. Handover of an individual apartment is confirmed by Emaar unit by unit.
Pace Analysis
How Fast Hills Park at Dubai Hills Estate Has Been Built
With a single published reading, pace here is read across the whole build rather than between inspections. Two numbers carry it:
- Nov 2022 to Oct 2025: site start to certified completion, 0% to 100%About 2.8 points per month
- Closing cycle to 08 Oct 2025: snagging, cleaning and certification, 98.95% to 100%A closing gain of 1.05 points
Two numbers describe the whole file. An average of about 2.8 points per month across thirty five months is a steady rate for a building of two podium levels and nineteen floors, and steadiness rather than acceleration is what a record closing on its first published reading implies: no stalled window long enough to leave a hole in the file, and no late surge needed to reach the line. The last 1.05 points then bought paperwork rather than concrete, because civil defence clearance on 20 August 2025 and the completion certificate on 23 September 2025 were both in hand before the inspector arrived. For an end user that removes the delivery variable entirely and hands the remaining calendar to snagging and key collection. For an investor it means Emaar closed project 2428 nearly seven months inside the 30 April 2026 registered horizon, with letting or resale possible from a certified building rather than a projected one.
Get the Next Inspection Figure First
Tell me you are tracking Hills Park at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Hills Park at Dubai Hills Estate
A build percentage only matters against what it delivers. The full project guide covers the apartments behind the 100% on this page:

Hills Park at Dubai Hills Estate Project Guide
Layouts across 444 apartments in one, two and three bedroom formats, the park facing position inside the Dubai Hills Estate masterplan, and the full investment case behind Emaar's plot 4792 building.
View the Hills Park at Dubai Hills Estate Project GuideConsidering a Completed Hills Park Apartment?
Availability keeps narrowing now that the building is finished and an apartment here can be occupied or let from the day the keys change hands. If the record on this page is what brought you here, the current list of remaining apartments is the next thing to see.
Ask About Remaining Availability on WhatsAppStage Record
Hills Park at Dubai Hills Estate Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it occupied in this project's own file, between the 28 July 2022 registration and the closing inspection of 08 October 2025.
Registration and Site Start
Project 2428 was entered on the DLD register on 28 July 2022, with construction starting on 05 November 2022 on plot 4792 in the Hadaeq Sheikh Mohammed Bin Rashid district.
Concrete Structure and Block Work
The registered design is G+2P+19F+R: two podium levels and nineteen floors over ground, in concrete structure and block. No interim reading is published between the site start and the closing cycle.
Internal and External Finishes
Finishes ran to the point the inspector later recorded as substantially completed across the whole building, alongside the electricity, gas and water connections found live at the October 2025 inspection.
Certification and Meter Connections
Dubai Civil Defence clearance was issued on 20 August 2025 and the Dubai Development Authority issued the building completion certificate on 23 September 2025, the pair that turns a finished building into a deliverable one.
Snagging, Deep Cleaning and Handover
The 08 October 2025 inspection recorded 100% with snagging works and deep cleaning progressing on site, and the register carries progress status Completed against handover status Ready.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Hills Park at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Hills Park at Dubai Hills Estate
This page is one of four project resources that together cover a Hills Park at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Hills Park at Dubai Hills Estate Construction Updates
This page: the verified Hills Park inspection record, from the 2022 site start to certified completion.

Hills Park at Dubai Hills Estate Golden Visa
Check whether a Hills Park apartment, now handover ready, clears the ten year Golden Visa threshold.
Read the Hills Park at Dubai Hills Estate Golden Visa Guide
Hills Park at Dubai Hills Estate Escrow Account
Confirm the project 2428 escrow account at Emirates Islamic Bank before releasing your closing instalment.
Verify the Hills Park at Dubai Hills Estate Escrow Account
Hills Park at Dubai Hills Estate Snagging Inspection
With snagging works recorded on site in October 2025, document defects before accepting your apartment.
Book Hills Park at Dubai Hills Estate SnaggingApproaching Handover
Between 100% and Handover: What Hills Park at Dubai Hills Estate Buyers Should Do Now
Nothing on the construction side is outstanding: the closing 1.05 points were recorded on 08 October 2025, and the building holds its civil defence clearance and its completion certificate. What remains open is your own unit file, and handover notices leave buyers a short window to complete the appointment, so the three steps below belong before the notice lands rather than after it.
First, arrange independent snagging while the developer side snagging works are themselves still on record; the Hills Park snagging inspection guide covers the window before you sign for the apartment.
Second, check the closing instalment your payment plan ties to 100% completion against the Hills Park escrow account record, so the final transfer goes to the account registered for project 2428.
Third, if the purchase may support residency, settle eligibility through the Hills Park Golden Visa eligibility guide before the title deed is issued, since deed timing shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record is half the picture; the other half is the community it was delivered into and the developer that delivered it. These three pages hold the rest:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties Developer Profile
Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Hills Park at Dubai Hills Estate Construction Updates Frequently Asked Questions
Hills Park at Dubai Hills Estate carries the status Finished on the DLD register for project 2428, with construction recorded at 100% at the inspection of 08 October 2025 and handover status Ready. The reading and the report behind it sit in the inspection timeline above.
The 08 October 2025 inspection recorded 100% construction progress, up 1.05 points from the 98.95% reading before it, and entered the RERA progress status as Completed. The certification dates and site notes behind that figure are in the October 2025 Hills Park construction update.
Construction started on 05 November 2022 and was certified at 100% on 08 October 2025, thirty five months later, an average of about 2.8 percentage points per month for a building of two podium levels and nineteen floors. The arithmetic is set out in the pace analysis above.
Construction is already complete. The completion date registered for project 2428 is 30 April 2026, recorded when the project was entered on the register on 28 July 2022, and the 08 October 2025 inspection certified 100% nearly seven months before that date. Handover status is Ready, and this record closes with that inspection.
The project is 444 residential units in one, two and three bedroom layouts, inside a G+2P+19F+R residential and retail building with a total built-up area of 37,961.23 sq m on plot 4792 in Dubai Hills Estate.
Project 2428 was entered on the DLD register on 28 July 2022 and construction started on 05 November 2022. The first published reading on this record is also its last: 100% on 08 October 2025, against 98.95% at the reading before it.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Hills Park at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.