Hills Park by Emaar in Dubai Hills Estate construction updates cover image featuring a project rendering of the residential buildings and landscaped podium in Dubai - Presented by Tohid Fetrat

Emaar · Dubai Hills Estate

Hills Park at Dubai Hills Estate Construction Updates

The Closed Build Record of a Handover Ready Emaar Address

The 08 October 2025 RERA inspection recorded Hills Park at 100%, closing a thirty five month build in Dubai Hills Estate with handover status Ready.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
08 October 2025Latest RERA Inspection
444 residential unitsTotal Units
Project 2428DLD Registration

Construction Snapshot

Hills Park at Dubai Hills Estate at a Glance

Hills Park is Emaar's 444 apartment residential and retail building on plot 4792 in Dubai Hills Estate, entered on the Dubai Land Department register as project 2428 on 28 July 2022. Thirty five months separate its 05 November 2022 construction start from the 100% recorded at the inspection of 08 October 2025, and the six figures below are the registered anchors behind that record. The record itself is unusually short for a build of that length: one published reading, and it is the closing one, because tracking here begins at the point the building was already certified complete.

DLD Project Number

2428

Project Status

Finished

Construction Start

05 November 2022

Total Units

444 residential units

Total Built-Up Area

37,961.23 sq m

Registered Completion Date

30 April 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Hills Park at Dubai Hills Estate Construction Update Timeline

One inspection carries this record. The DLD file for project 2428 shows 100% current progress on 08 October 2025 against 98.95% at the reading before it, and enters the RERA progress status as Completed, which is why no further inspection date follows it. The track below marks that closing reading against the November 2022 site start, and the row beneath opens the October 2025 report with the certification dates and site notes behind the figure.

Inspection MonthConstruction ProgressInspection DateFull Update
October 2025100%08 October 2025View the October 2025 update
!

Reading the dates: the completion date registered for project 2428 is 30 April 2026, recorded when the project was entered on the register on 28 July 2022. Construction was certified at 100% on 08 October 2025, nearly seven months earlier, so a registered date now behind us sits beside a building the register already carries as Finished. Handover of an individual apartment is confirmed by Emaar unit by unit.

Pace Analysis

How Fast Hills Park at Dubai Hills Estate Has Been Built

With a single published reading, pace here is read across the whole build rather than between inspections. Two numbers carry it:

  • Nov 2022 to Oct 2025: site start to certified completion, 0% to 100%About 2.8 points per month
  • Closing cycle to 08 Oct 2025: snagging, cleaning and certification, 98.95% to 100%A closing gain of 1.05 points

Two numbers describe the whole file. An average of about 2.8 points per month across thirty five months is a steady rate for a building of two podium levels and nineteen floors, and steadiness rather than acceleration is what a record closing on its first published reading implies: no stalled window long enough to leave a hole in the file, and no late surge needed to reach the line. The last 1.05 points then bought paperwork rather than concrete, because civil defence clearance on 20 August 2025 and the completion certificate on 23 September 2025 were both in hand before the inspector arrived. For an end user that removes the delivery variable entirely and hands the remaining calendar to snagging and key collection. For an investor it means Emaar closed project 2428 nearly seven months inside the 30 April 2026 registered horizon, with letting or resale possible from a certified building rather than a projected one.

Get the Next Inspection Figure First

Tell me you are tracking Hills Park at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Hills Park at Dubai Hills Estate

A build percentage only matters against what it delivers. The full project guide covers the apartments behind the 100% on this page:

Hills Park by Emaar in Dubai Hills Estate residential building exterior with stacked balconies and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Hills Park at Dubai Hills Estate Project Guide

Layouts across 444 apartments in one, two and three bedroom formats, the park facing position inside the Dubai Hills Estate masterplan, and the full investment case behind Emaar's plot 4792 building.

View the Hills Park at Dubai Hills Estate Project Guide

Considering a Completed Hills Park Apartment?

Availability keeps narrowing now that the building is finished and an apartment here can be occupied or let from the day the keys change hands. If the record on this page is what brought you here, the current list of remaining apartments is the next thing to see.

Ask About Remaining Availability on WhatsApp

Stage Record

Hills Park at Dubai Hills Estate Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is anchored to the window it occupied in this project's own file, between the 28 July 2022 registration and the closing inspection of 08 October 2025.

Jul 2022 to Nov 2022

Registration and Site Start

Project 2428 was entered on the DLD register on 28 July 2022, with construction starting on 05 November 2022 on plot 4792 in the Hadaeq Sheikh Mohammed Bin Rashid district.

Nov 2022 onward

Concrete Structure and Block Work

The registered design is G+2P+19F+R: two podium levels and nineteen floors over ground, in concrete structure and block. No interim reading is published between the site start and the closing cycle.

To mid 2025

Internal and External Finishes

Finishes ran to the point the inspector later recorded as substantially completed across the whole building, alongside the electricity, gas and water connections found live at the October 2025 inspection.

Aug 2025 to Sep 2025

Certification and Meter Connections

Dubai Civil Defence clearance was issued on 20 August 2025 and the Dubai Development Authority issued the building completion certificate on 23 September 2025, the pair that turns a finished building into a deliverable one.

Current PhaseOct 2025 onward, 100% at the closing reading

Snagging, Deep Cleaning and Handover

The 08 October 2025 inspection recorded 100% with snagging works and deep cleaning progressing on site, and the register carries progress status Completed against handover status Ready.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Hills Park at Dubai Hills Estate's own record.

Buyer Position

Tracking Your Position at Hills Park at Dubai Hills Estate

This page is one of four project resources that together cover a Hills Park at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Hills Park by Emaar in Dubai Hills Estate construction updates cover image featuring a project rendering of the residential buildings and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Hills Park at Dubai Hills Estate Construction Updates

This page: the verified Hills Park inspection record, from the 2022 site start to certified completion.

Hills Park by Emaar in Dubai Hills Estate Golden Visa card graphic beside a project rendering of the residential building in Dubai - Presented by Tohid Fetrat

Hills Park at Dubai Hills Estate Golden Visa

Check whether a Hills Park apartment, now handover ready, clears the ten year Golden Visa threshold.

Read the Hills Park at Dubai Hills Estate Golden Visa Guide
Hills Park by Emaar in Dubai Hills Estate escrow account protection graphic with shield and padlock icons over a residential street scene in Dubai - Presented by Tohid Fetrat

Hills Park at Dubai Hills Estate Escrow Account

Confirm the project 2428 escrow account at Emirates Islamic Bank before releasing your closing instalment.

Verify the Hills Park at Dubai Hills Estate Escrow Account
Hills Park by Emaar in Dubai Hills Estate snagging inspection graphic featuring a furnished living room and inspection badge in Dubai - Presented by Tohid Fetrat

Hills Park at Dubai Hills Estate Snagging Inspection

With snagging works recorded on site in October 2025, document defects before accepting your apartment.

Book Hills Park at Dubai Hills Estate Snagging

Approaching Handover

Between 100% and Handover: What Hills Park at Dubai Hills Estate Buyers Should Do Now

Nothing on the construction side is outstanding: the closing 1.05 points were recorded on 08 October 2025, and the building holds its civil defence clearance and its completion certificate. What remains open is your own unit file, and handover notices leave buyers a short window to complete the appointment, so the three steps below belong before the notice lands rather than after it.

First, arrange independent snagging while the developer side snagging works are themselves still on record; the Hills Park snagging inspection guide covers the window before you sign for the apartment.

Second, check the closing instalment your payment plan ties to 100% completion against the Hills Park escrow account record, so the final transfer goes to the account registered for project 2428.

Third, if the purchase may support residency, settle eligibility through the Hills Park Golden Visa eligibility guide before the title deed is issued, since deed timing shapes the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Hills Estate Structure

A build record is half the picture; the other half is the community it was delivered into and the developer that delivered it. These three pages hold the rest:

Dubai Hills Estate properties for sale overlooking the central park with modern residential buildings and landscaped green spaces. Presented by Tohid Fetrat.

Dubai Hills Estate Properties for Sale

Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.

See Dubai Hills Estate Properties for Sale
Dubai Hills Estate 18-hole championship golf course with view of Burj Khalifa and Dubai skyline

Dubai Hills Estate Community Overview

Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.

Explore the Dubai Hills Estate Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties Developer Profile

Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Hills Park at Dubai Hills Estate Construction Updates Frequently Asked Questions

Hills Park at Dubai Hills Estate carries the status Finished on the DLD register for project 2428, with construction recorded at 100% at the inspection of 08 October 2025 and handover status Ready. The reading and the report behind it sit in the inspection timeline above.

The 08 October 2025 inspection recorded 100% construction progress, up 1.05 points from the 98.95% reading before it, and entered the RERA progress status as Completed. The certification dates and site notes behind that figure are in the October 2025 Hills Park construction update.

Construction started on 05 November 2022 and was certified at 100% on 08 October 2025, thirty five months later, an average of about 2.8 percentage points per month for a building of two podium levels and nineteen floors. The arithmetic is set out in the pace analysis above.

Construction is already complete. The completion date registered for project 2428 is 30 April 2026, recorded when the project was entered on the register on 28 July 2022, and the 08 October 2025 inspection certified 100% nearly seven months before that date. Handover status is Ready, and this record closes with that inspection.

The project is 444 residential units in one, two and three bedroom layouts, inside a G+2P+19F+R residential and retail building with a total built-up area of 37,961.23 sq m on plot 4792 in Dubai Hills Estate.

Project 2428 was entered on the DLD register on 28 July 2022 and construction started on 05 November 2022. The first published reading on this record is also its last: 100% on 08 October 2025, against 98.95% at the reading before it.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Hills Park at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.