Beyond Developments · Dubai Maritime City · Construction Update

Kanyon Construction Update - April 2026

April 2026 Inspection Records Kanyon at 0% Construction Progress in Dubai Maritime City

Site mobilization had not begun at Kanyon when RERA inspected on 22 April 2026, with construction registered to start on 30 June 2026.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
22 April 2026Inspection Date
Q2 2029Expected Handover
4050DLD Project Number

Verified DLD Inspection Data

Kanyon Construction Snapshot

Zero points of recorded movement place Kanyon at the opening end of the tracking scale, the stage where registration, escrow, and the shape of the payment calendar decide far more than anything visible on site. The register's earlier inspection entry also reads 0% and carries no date of its own, so 22 April 2026 is the first dated reading on this project's file.

Project Name

Kanyon by Beyond

Project Number

4050

Project Status

Active

Construction Progress

0%

Inspection Date

22 April 2026

Construction Start

30 June 2026

Total Units

411 residential units

Total Built Area

45,943.40 sq m

Expected Completion

Q2 2029

Data source: RERA inspection conducted on 22 April 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Kanyon Construction Progress Summary

Kanyon holds at 0% on 22 April 2026, unchanged from an undated earlier entry that reads the same, and the inspectors logged the reason in plain terms: no construction activities had been started. What the cycle does confirm is the paperwork underneath the project, from a DLD registration dated 30 October 2025 to a trust account already standing at Emirates NBD Bank, and a registered construction start of 30 June 2026 that sat ten weeks beyond the inspection date.

Completed
  • DLD project registration recorded on 30 October 2025
  • Escrow account established with Emirates NBD Bank (P.J.S.C)
  • Plot 540 in Madinat Dubai Almelaheyah allocated to project 4050
In Progress at 0%
  • No construction activities recorded at the 22 April 2026 visit
  • RERA progress status returned as not applicable this cycle
  • Run-up to the registered construction start date of 30 June 2026
  • Sales release across the 411 residences and the tower's retail component
Ahead of Handover
  • Enabling works, piling, and substructure on the reclaimed plot
  • Superstructure through the podium levels and 45 residential floors
  • Facade, mechanical and electrical fit out, and interior finishes
  • The full sequence of RERA inspection cycles toward Q2 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Registered start30 June 2026 per the DLD record, ten weeks after this inspection was carried out.
Remaining distanceThe whole 100 point scale still lies between this reading and a handover ready building.

Payment Linked Progress

What 0% Progress Means for Kanyon Buyers

A certified zero is not an empty reading: it fixes the baseline every later percentage is measured against, and it tells you which protections are already active while nothing is yet built. Four actions carry the most weight at this point in the Kanyon record.

Before Your First Transfer

Verify the escrow account

Every payment ahead of handover belongs in the DLD regulated escrow account registered for project 4050, which the April 2026 inspection file records at Emirates NBD Bank. Kanyon escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Each Dated Instalment

Read your instalment dates, not the progress bar

The published Kanyon schedule runs on fixed calendar dates rather than construction milestones, so a 0% reading postpones nothing and the two records move independently. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

At Purchase and Shortly After

Confirm your Oqood registration

Interim registration with the Dubai Land Department is what places your unit on the public record years before a title deed exists. Ask for the Oqood certificate covering your unit in project 4050 and file it alongside the sale and purchase agreement, because at 0% it is the clearest evidence of what you hold.

Every Cycle

Track the record from its baseline

Kanyon opens its inspection history at zero, so each future reading is a clean measure of pace rather than a revision of someone else's estimate. Kanyon construction updates hub collects every cycle as it publishes.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering at the opening of the record is the mirror image of a late-stage purchase: the delivery horizon is long, the whole payment calendar still lies ahead, and the choice of floor and orientation is at its widest across 45 residential levels. Every payment goes to the DLD-registered escrow account for project 4050, released against certified construction progress.

Entering Now at 0%
  • Half the purchase value stays deferred until completion in Q2 2029
  • Widest choice of one, two, and three bedroom layouts in the tower
  • Outgoings sit on known calendar dates rather than moving build stages
Typical Late-Stage Entry
  • Most construction risk already retired by certified progress
  • A large balance falls due within months of signing
  • Choice narrowed to whatever stock remains unsold
AED 2.44M ≈ USD 664KStarting Price
50/50 Plan50% Due on Completion
From Q2 2029Expected Handover

20+ units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Kanyon Project Details

Kanyon by Beyond Developments in Dubai Maritime City residential tower rising above a landscaped park with mature trees and pedestrian paths in Dubai - Presented by Tohid Fetrat
Dubai Maritime City · Beyond Developments

With the record still at its baseline, Kanyon is a pre-construction development registered in the G+3P+45+1MECH+R format: 411 one, two, and three bedroom residences above podium levels and a retail component on plot 540. Starting prices: AED 2.44M ≈ USD 664K.

For buyers entering here, the trade off is a long delivery horizon against the widest choice in the building and a 50/50 calendar plan, with handover expected from Q2 2029.

Site Context This Cycle

Explore Kanyon Location on Dubai Map

Kanyon takes plot 540 in Madinat Dubai Almelaheyah, the reclaimed Dubai Maritime City peninsula that sits between Port Rashid and the open Gulf, and the April 2026 file records that ground as untouched by site works. That is why this cycle reports position rather than progress: everything the inspection could confirm concerns where the tower will stand, not how far it has risen.

The district itself is still filling in around the plot, which matters more here than it would on a finished street: the roads, marina frontage, and Forest District landscaping that will frame Kanyon are being delivered on their own timetable alongside the tower, and buyers weighing occupancy or rental plans against a Q2 2029 handover should track both. Trace where plot 540 sits against the rest of the district on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Kanyon Before Construction Begins

Pre-construction is where residency planning and payment protection do the heavy lifting, long before a handover date starts to matter. Each resource below is matched to where Kanyon stands right now.

Kanyon by Beyond Developments in Dubai Maritime City construction updates cover image featuring project renderings of the residential tower above landscaped surroundings and the waterfront in Dubai - Presented by Tohid Fetrat
You Are Here

Kanyon Construction Updates

This page: the verified April 2026 inspection record for Kanyon, from registration to first site works.

Kanyon by Beyond Developments in Dubai Maritime City Golden Visa concept with a gold card beside the residential tower and waterfront skyline in Dubai - Presented by Tohid Fetrat

Kanyon by Beyond in Dubai Maritime City Golden Visa From One Bedroom

All three tiers at Kanyon by Beyond in Dubai Maritime City qualify individually in this freehold Forest District tower.

Read Kanyon Golden Visa Guide
Kanyon by Beyond Developments in Dubai Maritime City escrow account protection concept with shield and padlock icons above the landscaped tower entrance in Dubai - Presented by Tohid Fetrat

Kanyon by Beyond in Dubai Maritime City: A Fresh Escrow Account

Kanyon by Beyond in Dubai Maritime City, DLD project 4050, escrows 411 units with Emirates NBD, 0% certified April 2026.

Verify Kanyon Escrow Account

Update Timeline

Other Kanyon Construction Updates

April 2026 opens the inspection history for Kanyon. Every cycle from here is filed on the hub, so the climb off zero stays readable reading by reading.

All UpdatesKanyon Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Kanyon Construction Updates

FAQs

Kanyon Construction Progress in April 2026: Frequently Asked Questions

As of the RERA inspection conducted on 22 April 2026, Kanyon stands at 0% construction progress in the DLD project register, and the RERA progress status field is returned as not applicable for this cycle.

Not as of 22 April 2026. The inspection notes for that visit state that no construction activities had been started on site. The register carries a construction start date of 30 June 2026, which fell after this inspection, so the next published cycle is the first one able to show movement off zero.

Nothing has moved. The previous inspection entry in the register also reads 0%, and it carries no date of its own, which makes 22 April 2026 the first dated reading on the Kanyon record. How inspection cycles are recorded and published is covered on the Kanyon construction updates hub.

No. The published Kanyon schedule runs on fixed calendar dates rather than construction milestones, so a certified 0% does not postpone an instalment. That is the practical difference buyers most often miss at this stage: the payment calendar and the progress record move independently of each other, and only your own sale and purchase agreement can confirm which dates bind you.

Handover is expected in Q2 2029, roughly three years after the 22 April 2026 inspection. Expected completion entries in the DLD register are revised between inspection cycles as a project advances, so each future update on this page restates the position as it stands at that reading.

The April 2026 inspection file records Emirates NBD Bank (P.J.S.C) as the trust account bank for project 4050, developed by Cobia Real Estate Development L.L.C under developer number 2316. Those details are the ones to match against the DLD project record before any transfer is made.

The register describes a mixed use residential and retail development in the G+3P+45+1MECH+R format, on plot 540 in Madinat Dubai Almelaheyah. Kanyon holds 411 residences in one, two, and three bedroom layouts across a built-up area of 45,943.40 square metres.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Kanyon by Beyond in Dubai Maritime City correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts