Emaar · The Oasis
Lavita at The Oasis Construction Updates
The Verified Build Record for 49 Canal-Side Mansions in The Oasis
Lavita at The Oasis recorded 20.13% construction at its 02 June 2026 RERA inspection, an early baseline for 49 basement-level mansions rising beside The Oasis canals.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Lavita at The Oasis at a Glance
Lavita at The Oasis is Emaar's collection of 49 six and seven bedroom mansions on plot 1212 in Me'Aisem Second, strung along the outer rim of The Oasis. About twenty months separate its 01 October 2024 construction start from the 20.13% certified at the 02 June 2026 inspection, with handover set for Q1 2029. Because each of the 49 mansions sits over its own basement, this record follows 49 separate excavations and structures moving at uneven speeds, not one building climbing floor by floor.
3266
Active
01 October 2024
49 mansions
123,286.46 sq m
31 January 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Lavita at The Oasis Construction Update Timeline
Two readings make up Lavita's record so far: an earlier inspection at 10%, whose date the DLD app does not show, and the 20.13% certified on 02 June 2026, the first reading with a date and the one that opens the monthly Lavita series. Both sit as dots on the track below, and the June 2026 row links the full monthly update with the inspection detail behind the figure.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 20.13% | 02 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Lavita at The Oasis Has Been Built
A pace figure needs two dated readings, and Lavita's record holds only one so far. This is what the dates in the DLD record do support:
- 01 Oct 2024 to 02 Jun 2026: construction start to the first dated reading of 20.13%About 20 months elapsed
- Previous reading to 02 Jun 2026: 10% to 20.13%, earlier date not in the DLD recordUp 10.13 points, no monthly rate
- 02 Jun 2026 to 31 Jan 2029: 20.13% to the registered completion date79.87 points in about 32 months
With a single dated reading, Lavita has no curve to read yet, and a points-per-month figure built on the undated 10% would be a guess presented as analysis. What the record does reveal is structural: 49 separate mansions, each over its own basement, advance plot by plot, so one site-wide percentage blends foundation, structural and MEP work sitting at different points across the collection. The first genuine pace figure arrives with the next dated inspection. For an end user planning around Q1 2029, that reading shows whether the 79.87 remaining points are being covered at a workable rate; for an investor, it is the first hard number on how quickly Emaar is carrying these mansions toward the 50% construction stage in the payment schedule of record.
Get the Next Inspection Figure First
Tell me you are tracking Lavita at The Oasis and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Lavita at The Oasis at The Oasis Emaar
A 20.13% reading means more once you know what the finished collection is meant to be. The project guide covers the mansions this record is tracking toward:

Lavita at The Oasis: Six and Seven Bedroom Canal-Side Mansions
Lavita at The Oasis is a gated Emaar collection of 49 six and seven bedroom mansions along the canals and lagoons.
View the Lavita at The Oasis Project GuideConsidering an Early-Construction Entry?
Buying into Lavita at this stage means choosing a plot before the mansions take visible shape, and with a collection this small, plot choice narrows as sales continue. If the record on this page is what brought you here, ask me for current availability before the remaining choice narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Lavita at The Oasis Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it occupies in Lavita's own record, from the 10 September 2024 registration to the 31 January 2029 completion date in the DLD register, so you can see where a collection of basement-level mansions stands today and which stages have no reading yet.
Registration and Construction Start
Lavita entered the DLD register as project 3266 on 10 September 2024, with construction recorded as starting on 01 October 2024 on plot 1212 in Me'Aisem Second.
Mobilization and Enabling Works
Site set-up, enabling works and early foundation works across the plots, leading to the earlier 10% reading, whose date the DLD record does not show.
Basements, Structure and MEP in Parallel
The 02 June 2026 inspection certified 20.13%, with mobilization still under way and foundation, structural, MEP and internal works spread unevenly across the 49 plots.
Mansion Superstructure and Roofs
Not yet reached in the record: completing ground and first floor structures on every plot, plus the roof floors of the larger Ayanna and Aman designs.
Finishes, Amenities and Handover
Still to come: internal and external finishes, then the canals, gym, play areas, gatehouses and clubhouses, ending at the 31 January 2029 registered completion date and handover in Q1 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Lavita at The Oasis's own record.
Buyer Position
Tracking Your Position at Lavita at The Oasis
This page is one of four project resources that together cover a Lavita at The Oasis purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Lavita at The Oasis Construction Updates
This page: the RERA inspection record for Lavita's 49 mansions, from October 2024 to handover.

Lavita at The Oasis Golden Visa: One Mansion, Many Times Over
Lavita at The Oasis is Emaar's freehold collection of 49 mansions, and both its 6 and 7 bedroom tiers qualify individually.
Read the Lavita at The Oasis Golden Visa Guide
Lavita at The Oasis Escrow: An Intimate 49-Unit Account
Lavita at The Oasis puts 49 units in Abu Dhabi Commercial Bank escrow as DLD project 3266, certified 20.13% June 2026.
Verify the Lavita at The Oasis Escrow AccountApproaching Handover
Between 20.13% and Handover: What Lavita at The Oasis Buyers Should Do Now
At the 02 June 2026 reading of 20.13%, Lavita sat 29.87 points below the 50% construction stage that the payment schedule of record links to its fourth instalment, a stage that schedule estimated for September 2026. Whether your agreement bills that instalment on the estimated date or on a certified percentage decides when money leaves your account, so the three steps below belong in this window, not after a payment notice arrives.
First, make sure every remaining payment reaches the right account; the Lavita at The Oasis escrow account page shows how to confirm the project 3266 trust account before you transfer.
Second, keep the certified record in view: the June 2026 Lavita construction update holds the inspection detail behind the 20.13% figure, and each later reading joins the timeline on this page as it posts.
Third, if UAE residency is part of the plan, work through the Lavita Golden Visa guide now, so the residency question is settled well before Q1 2029 rather than at handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore The Oasis Emaar Structure
Lavita's 49 mansions are one collection inside a 100 million sq ft masterplan that is still taking shape. These three pages put its construction record in market, community and developer context:

The Oasis Emaar Properties for Sale
Browse waterfront villas and mansions for sale across The Oasis clusters, with prices, layouts and payment plans.
See The Oasis Emaar Properties for Sale
The Oasis by Emaar: Lagoon Villas and Mansions in Dubailand
The Oasis holds about 3,100 villas and mansions in Dubailand, with more than 40 percent of its land given to lagoons.
Explore the The Oasis Emaar Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Lavita at The Oasis Construction Updates Frequently Asked Questions
Lavita at The Oasis is an active DLD-registered project (number 3266) in its early structural phase, certified at 20.13% construction progress at the RERA inspection of 02 June 2026, with a progress status of Main Contract - Progressing. Every reading so far is set out in the Lavita inspection timeline above.
The 02 June 2026 inspection recorded 20.13% construction progress at Lavita at The Oasis, up 10.13 points from a previous reading of 10% whose date the DLD app does not show. The inspection detail sits in the Lavita at The Oasis June 2026 construction update.
The DLD register records completion for project 3266 as 31 January 2029, a date that has not yet passed, and handover of Lavita at The Oasis is scheduled for Q1 2029. At the 02 June 2026 inspection the project stood at 20.13%, leaving 79.87 points to certify in about 32 months; Emaar confirms the actual handover as final inspections complete, and this page's record is updated as each new inspection is recorded.
Lavita at The Oasis comprises 49 mansions, the unit count shown for project 3266 in the DLD register, split between six bedroom mansions of about 19,099 sq ft and seven bedroom mansions of about 28,039 sq ft. Each one is built over its own basement, so the 20.13% reading of 02 June 2026 averages progress across 49 separate structures.
Construction at Lavita at The Oasis officially started on 01 October 2024, three weeks after the project entered the DLD register on 10 September 2024. The first dated reading in this record, 20.13% on 02 June 2026, came about 20 months later; an earlier 10% reading appears in the DLD app without a date.
As of the 02 June 2026 inspection at 20.13%, work at Lavita at The Oasis covered site mobilization, which was still under way, alongside enabling works, foundations, structural works, and MEP and internal works at uneven points across the plots, with infrastructure inside the project also advancing. The remaining 79.87 points cover the rest of the structure, the finishes, and amenities such as the gatehouses and clubhouses.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Lavita at The Oasis construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.