Lavita by Emaar in The Oasis construction updates cover image featuring a project rendering of a contemporary mansion with a swimming pool, palm trees and landscaped garden in Dubai - Presented by Tohid Fetrat

Emaar · The Oasis

Lavita at The Oasis Construction Updates

The Verified Build Record for 49 Canal-Side Mansions in The Oasis

Lavita at The Oasis recorded 20.13% construction at its 02 June 2026 RERA inspection, an early baseline for 49 basement-level mansions rising beside The Oasis canals.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

20.13%Construction Progress
02 June 2026Latest RERA Inspection
49 mansionsTotal Units
Project 3266DLD Registration

Construction Snapshot

Lavita at The Oasis at a Glance

Lavita at The Oasis is Emaar's collection of 49 six and seven bedroom mansions on plot 1212 in Me'Aisem Second, strung along the outer rim of The Oasis. About twenty months separate its 01 October 2024 construction start from the 20.13% certified at the 02 June 2026 inspection, with handover set for Q1 2029. Because each of the 49 mansions sits over its own basement, this record follows 49 separate excavations and structures moving at uneven speeds, not one building climbing floor by floor.

DLD Project Number

3266

Project Status

Active

Construction Start

01 October 2024

Total Units

49 mansions

Total Built-Up Area

123,286.46 sq m

Registered Completion Date

31 January 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Lavita at The Oasis Construction Update Timeline

Two readings make up Lavita's record so far: an earlier inspection at 10%, whose date the DLD app does not show, and the 20.13% certified on 02 June 2026, the first reading with a date and the one that opens the monthly Lavita series. Both sit as dots on the track below, and the June 2026 row links the full monthly update with the inspection detail behind the figure.

Inspection MonthConstruction ProgressInspection DateFull Update
June 202620.13%02 June 2026View the June 2026 update

Pace Analysis

How Fast Lavita at The Oasis Has Been Built

A pace figure needs two dated readings, and Lavita's record holds only one so far. This is what the dates in the DLD record do support:

  • 01 Oct 2024 to 02 Jun 2026: construction start to the first dated reading of 20.13%About 20 months elapsed
  • Previous reading to 02 Jun 2026: 10% to 20.13%, earlier date not in the DLD recordUp 10.13 points, no monthly rate
  • 02 Jun 2026 to 31 Jan 2029: 20.13% to the registered completion date79.87 points in about 32 months

With a single dated reading, Lavita has no curve to read yet, and a points-per-month figure built on the undated 10% would be a guess presented as analysis. What the record does reveal is structural: 49 separate mansions, each over its own basement, advance plot by plot, so one site-wide percentage blends foundation, structural and MEP work sitting at different points across the collection. The first genuine pace figure arrives with the next dated inspection. For an end user planning around Q1 2029, that reading shows whether the 79.87 remaining points are being covered at a workable rate; for an investor, it is the first hard number on how quickly Emaar is carrying these mansions toward the 50% construction stage in the payment schedule of record.

Get the Next Inspection Figure First

Tell me you are tracking Lavita at The Oasis and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Lavita at The Oasis at The Oasis Emaar

A 20.13% reading means more once you know what the finished collection is meant to be. The project guide covers the mansions this record is tracking toward:

Lavita at The Oasis by Emaar six bedroom mansion with illuminated evening exterior and landscaped garden in Dubai. Presented by Tohid Fetrat.

Lavita at The Oasis: Six and Seven Bedroom Canal-Side Mansions

Lavita at The Oasis is a gated Emaar collection of 49 six and seven bedroom mansions along the canals and lagoons.

View the Lavita at The Oasis Project Guide

Considering an Early-Construction Entry?

Buying into Lavita at this stage means choosing a plot before the mansions take visible shape, and with a collection this small, plot choice narrows as sales continue. If the record on this page is what brought you here, ask me for current availability before the remaining choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Lavita at The Oasis Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it occupies in Lavita's own record, from the 10 September 2024 registration to the 31 January 2029 completion date in the DLD register, so you can see where a collection of basement-level mansions stands today and which stages have no reading yet.

Sep 2024 to Oct 2024

Registration and Construction Start

Lavita entered the DLD register as project 3266 on 10 September 2024, with construction recorded as starting on 01 October 2024 on plot 1212 in Me'Aisem Second.

Oct 2024 to the undated 10% reading

Mobilization and Enabling Works

Site set-up, enabling works and early foundation works across the plots, leading to the earlier 10% reading, whose date the DLD record does not show.

Current PhaseTo 02 Jun 2026, 20.13% at last reading

Basements, Structure and MEP in Parallel

The 02 June 2026 inspection certified 20.13%, with mobilization still under way and foundation, structural, MEP and internal works spread unevenly across the 49 plots.

Ahead, toward the 50% and 70% stages

Mansion Superstructure and Roofs

Not yet reached in the record: completing ground and first floor structures on every plot, plus the roof floors of the larger Ayanna and Aman designs.

Ahead, toward Q1 2029

Finishes, Amenities and Handover

Still to come: internal and external finishes, then the canals, gym, play areas, gatehouses and clubhouses, ending at the 31 January 2029 registered completion date and handover in Q1 2029.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Lavita at The Oasis's own record.

Buyer Position

Tracking Your Position at Lavita at The Oasis

This page is one of four project resources that together cover a Lavita at The Oasis purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Lavita by Emaar in The Oasis construction updates cover image featuring a project rendering of a contemporary mansion with a swimming pool, palm trees and landscaped garden in Dubai - Presented by Tohid Fetrat
You Are Here

Lavita at The Oasis Construction Updates

This page: the RERA inspection record for Lavita's 49 mansions, from October 2024 to handover.

Lavita by Emaar in The Oasis Golden Visa graphic with a gold visa card above a project rendering of a contemporary mansion, palm trees and street view in Dubai - Presented by Tohid Fetrat

Lavita at The Oasis Golden Visa: One Mansion, Many Times Over

Lavita at The Oasis is Emaar's freehold collection of 49 mansions, and both its 6 and 7 bedroom tiers qualify individually.

Read the Lavita at The Oasis Golden Visa Guide
Lavita by Emaar in The Oasis escrow account protection graphic with shield and padlock icons above a project rendering of a contemporary mansion, swimming pool and landscaped garden in Dubai - Presented by Tohid Fetrat

Lavita at The Oasis Escrow: An Intimate 49-Unit Account

Lavita at The Oasis puts 49 units in Abu Dhabi Commercial Bank escrow as DLD project 3266, certified 20.13% June 2026.

Verify the Lavita at The Oasis Escrow Account

Approaching Handover

Between 20.13% and Handover: What Lavita at The Oasis Buyers Should Do Now

At the 02 June 2026 reading of 20.13%, Lavita sat 29.87 points below the 50% construction stage that the payment schedule of record links to its fourth instalment, a stage that schedule estimated for September 2026. Whether your agreement bills that instalment on the estimated date or on a certified percentage decides when money leaves your account, so the three steps below belong in this window, not after a payment notice arrives.

First, make sure every remaining payment reaches the right account; the Lavita at The Oasis escrow account page shows how to confirm the project 3266 trust account before you transfer.

Second, keep the certified record in view: the June 2026 Lavita construction update holds the inspection detail behind the 20.13% figure, and each later reading joins the timeline on this page as it posts.

Third, if UAE residency is part of the plan, work through the Lavita Golden Visa guide now, so the residency question is settled well before Q1 2029 rather than at handover.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore The Oasis Emaar Structure

Lavita's 49 mansions are one collection inside a 100 million sq ft masterplan that is still taking shape. These three pages put its construction record in market, community and developer context:

The Oasis villa by Emaar with private pool, landscaped garden, floor to ceiling windows and modern outdoor seating in Dubai Presented by Tohid Fetrat

The Oasis Emaar Properties for Sale

Browse waterfront villas and mansions for sale across The Oasis clusters, with prices, layouts and payment plans.

See The Oasis Emaar Properties for Sale
Evening view of lagoon front villas at The Oasis by Emaar with landscaped pathways palm trees and a resident walking a dog presented by Tohid Fetrat.

The Oasis by Emaar: Lagoon Villas and Mansions in Dubailand

The Oasis holds about 3,100 villas and mansions in Dubailand, with more than 40 percent of its land given to lagoons.

Explore the The Oasis Emaar Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Lavita at The Oasis Construction Updates Frequently Asked Questions

Lavita at The Oasis is an active DLD-registered project (number 3266) in its early structural phase, certified at 20.13% construction progress at the RERA inspection of 02 June 2026, with a progress status of Main Contract - Progressing. Every reading so far is set out in the Lavita inspection timeline above.

The 02 June 2026 inspection recorded 20.13% construction progress at Lavita at The Oasis, up 10.13 points from a previous reading of 10% whose date the DLD app does not show. The inspection detail sits in the Lavita at The Oasis June 2026 construction update.

The DLD register records completion for project 3266 as 31 January 2029, a date that has not yet passed, and handover of Lavita at The Oasis is scheduled for Q1 2029. At the 02 June 2026 inspection the project stood at 20.13%, leaving 79.87 points to certify in about 32 months; Emaar confirms the actual handover as final inspections complete, and this page's record is updated as each new inspection is recorded.

Lavita at The Oasis comprises 49 mansions, the unit count shown for project 3266 in the DLD register, split between six bedroom mansions of about 19,099 sq ft and seven bedroom mansions of about 28,039 sq ft. Each one is built over its own basement, so the 20.13% reading of 02 June 2026 averages progress across 49 separate structures.

Construction at Lavita at The Oasis officially started on 01 October 2024, three weeks after the project entered the DLD register on 10 September 2024. The first dated reading in this record, 20.13% on 02 June 2026, came about 20 months later; an earlier 10% reading appears in the DLD app without a date.

As of the 02 June 2026 inspection at 20.13%, work at Lavita at The Oasis covered site mobilization, which was still under way, alongside enabling works, foundations, structural works, and MEP and internal works at uneven points across the plots, with infrastructure inside the project also advancing. The remaining 79.87 points cover the rest of the structure, the finishes, and amenities such as the gatehouses and clubhouses.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Lavita at The Oasis construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status